SM18 Vertical/Horizontal Test Setup LHC Crab Cavity Engineering Meeting Session: Cavity Cryostat Testing & Integration in SM18Cavity Cryostat Testing &

Slides:



Advertisements
Similar presentations
SRF Cryomodule Assembly Facility Plans Tug Arkan AAC, May 10-12, 2005.
Advertisements

DESIGN OF A HIGH POWER TEST STAND FOR ESS SPOKE CAVITIES
RF Unit Test Facility at NML & CM1 Test Plan Bob Kephart Fermilab IWLC-10 October 20, 2010.
Possible Assembly and Test of the Crab cryomodule in SM18 at CERN P. Maesen LHC Crab Cav meeting, 17 Sep’ 09 LHC-CC09Cryomodule Assembly & Test Stand.
Cleanroom refurbishment in SM18 Upgrade for the SPL high gradient resonators 26/11/2010J. Chambrillon - CERN BE/RF1.
Cavity Vertical Test and Diagnostics Kitty Liao Second Open Collaboration Meeting on Superconducting Linacs for High Power Proton Beams.
SLHC-PP – WP7 Critical Components for Injector Upgrade Plasma Generator – CERN, DESY, STFC-RAL Linac4 2MHz RF source Thermal Modeling Gas Measurement and.
H. Hayano, KEK, New SRF Facility at Belgrade SRF-WG.
ILCTA_NML Progress at Fermilab Jerry Leibfritz September 10, 2007.
Test Stands Roger Ruber Uppsala University ESS TAC4 16 Feb
RF power & FPC status Eric Montesinos, CERN BE-RF on behalf of all people involved, great thanks to all of them !
Conceptual Design Study - Cryogenic Requirements How to decide the layout of ILC cryogenic system Conceptual design of cryogenic system Layout of cryogenic.
Needs of a European SCRF Facility - the BIG plan Lutz Lilje DESY -MPY- DESY 11/2006 Planning Resource needs.
Workshop on cryogenic and vacuum sectorisations of the SPL CERN, 9 th -10 th November 2009 Workshop Organisation and Goals Vittorio Parma TE-MSC.
STF plan overview H. Hayano, KEK LCPAC 02/25/2005.
3 June 2012 BE-KT Innovation Day Prevessin, CERN, Switzerland
STF EP, VT commissioning by FNAL AES001 H. Hayano, KEK
STF status Mar.22,2005 H. Hayano, KEK. STF Phase 1 Test Accelerator DC gun : 200kV CsTe photocathode for quick start UV(262nm) Laser (337ns spacing, 2820bunches)
Orsay, Sergio Calatroni - CERN 1 CERN facilities for Superconducting RF S. Calatroni, J.-P. Delahaye, J. Tückmantel, B. Vullierme.
SM18 INFRASTRUCTURE Crab Cavity CryoModule – Conceptual Design Meeting
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Revised SPL-study work-plan W. Weingarten 3 May 20101SPL Cavity WG Meeting.
Aug 23, 2006 Half Current Option: Impact on Linac Cost Chris Adolphsen With input from Mike Neubauer, Chris Nantista and Tom Peterson.
Experience with LEP (and LHC) cryo-modules Workshop on cryogenic and vacuum sectorisations of the SPL O.Brunner – November ’09.
Assembly Procedures of the cavities Ancillaries (RF power coupler, Tuning system, RF cables) 19/03/2014Mathieu Therasse BE/RF/SRF1 Special Linac WG meeting:
Test plan for SPL short cryomodule O. Brunner, W. Weingarten WW 1SPL cryo-module meeting 19 October 2010.
ILC Test Facility at New Muon Lab (NML) S. Nagaitsev Fermilab April 16, 2007.
CRAB for HL-LHC KEK activity 2010DEC Yoshiyuki MORITA.
New plans for high power RF tests places at CERN O. Brunner BE/RF/KS – January ‘10.
Diagnostics Tests and Studies for SPL cavities Kitty Liao CERN BE-RF-KS First Open Collaboration Meeting on Superconducting Linacs for High Power Proton.
High power RF tests places at CERN O. Brunner, CERN 4th SPL Collaboration Meeting jointly with ESS.
EN-CV Progress EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2016/01/21.
The SPL Short Cryo-module: Status Report V.Parma, CERN, TE-MSC On bahalf of the Cryomodule development team SPL seminar December 2012, 6-7 December 2012,
NML - RF Unit Test Facility Jerry Leibfritz Fermilab.
Preparation procedure and RF processining of cERL-ML power coupler at KEK Hiroshi Sakai, Takaaki Furuya, Masato Sato, Kenji Shinoe, Kensei Umemori, Kazuhiro.
26 April, 2016 LCLS II Cryomodules and Cryoplant, Joe Preble LCLS-II Overview JLAB Organization for LCLS-II JLAB responsibilities & Schedule and Status.
SM18 Vertical & Horizontal Test 110/12/2013Mathieu Therasse CERN BE/RF A. Benoit, O. Brunner, E. Jensen, A. Macpherson, P. Maesen, K. Schirm, W. Venturini.
HiLumi-LHC/LARP Crab Cavity System External Review 5-6 May 2014, BNL SPS - RF Power and Coupler status Erk Jensen, Eric Montesinos, CERN BE-RF.
Status of Vertical Test Stand at RRCAT P Shrivastava, P Mohania,D.Baxy, Vikas Rajput S C Joshi, S Raghavendra,S K Suhane RRCAT, Indore November 26, 2012.
Wish list from ESS Christine Darve H-ECCTD Kick-off meeting 16 March
Status and Perspectives of the SPL R&D R. Garoby – 6/12/2012 SPL Seminar 2012 December 6-7, 2012 CERN.
ILCTA_NML Progress at Fermilab Jerry Leibfritz August 16, 2007.
Development of Cryo-Module Test Stand (CMTS) for Fermi Lab (R.L.Suthar, Head,CDM, BARC) Cryo-Module Test stand (CMTS) is a very sophisticated equipment.
TEST FACILITY STATUS FOR TESTING CERN Marta Bajko WP10. EUCARD 2 Task 4 - HTS Magnet Tests, June 2015.
OUTCOME OF FIRST CAVITY TESTS With help of T. Junginger, N. Schwerg, K. Liao, P. Maesen, M. Gourragne, A. Benoit, O. Brunner SPL Seminar 2012 at CERN 112/07/2012Mathieu.
SRF Test Facilities – Functions and Costs Alexander Romanenko Test Facilities Review 17 Mar 2015.
ILC-HiGrade annual meeting - 22 November 2010 ILC-HiGrade Meeting Cavity-Treatment at CEA Saclay (WP6) F. Eozénou.
TDR Cryogenics Parameters Tom Peterson 28 September 2011.
EURISOL CB MEETING – PSI – 15 JUNE 2006 Sébastien Bousson IPN Orsay – Accelerator Division TASK 8 STATUS REPORT INFN – Legnaro IPN Orsay.
EN-CV Progress EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2016/01/14.
Infrastructure status and plans at CERN 1) W. Weingarten/CERN TTC Milano 28 February - 3 March W. Weingarten/CERN 1)Most of the slides are based.
EN-CV Progress EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2016/02/04.
Session VI: Cryomodule Construction Summary
CC LLRF SM18 test plan and BA6 infrastructure
Cryomodule test stand at ESS site
HL-LHC IT STRING and Series test of SC link
WP5 Elliptical cavities
High Energy Proton Synchrotrons
(4 areas/website front)
RF-SRF Infrastructure: Operation,Maintenance&Upgrades
Cleanroom Upgrade in SM18 Optical Inspection bench
Evolving an ILC focused SCRF Facility from the XFEL Infrastructure
Mathieu, Gabriel, Max, Spyros, Guillaume
ESS RF Development at Uppsala University
P. Maesen for CERN BE/RF-SRF team
UK RFD Pre-Series cryomodule
SRF Section Cuvée 2014.
TEST PLANS for HL LHC IT STRING
INSTITUTE OF HIGH ENERGY PHYSICS
Saclay Test Facilities
Presentation transcript:

SM18 Vertical/Horizontal Test Setup LHC Crab Cavity Engineering Meeting Session: Cavity Cryostat Testing & Integration in SM18Cavity Cryostat Testing & Integration in SM18 112/14/2012Mathieu Therasse CERN BE/RF A. Benoit, O. Brunner, J. Chambrillon, E. Jensen, K. Liao, P. Maesen BE/RF at CERN

OUTLINE CAVITY PREPARATION AND ASSEMBLY AT CERN - EXISTING ASSEMBLY AREA AND CLEAN ROOMS - CLEANROOM LAYOUT (Existing facility in SM18) - CLEANROOM LAYOUT (Updated) - HIGH PRESSURE RINSING (HPR) AND ULTRA PURE WATER PRODUCTION RF TEST FACILITES - NEW RF CRYO INFRASTRUCTURE AT SM18 - RF POWER ZONE - AVAILABILITY FOR CRAB CAVITY - RF CONTROL ROOM DIAGNOSTIC SYSTEMS - OSCILLATING SUPERLEAK TRANSDUCER AND TEMPERATURE MAPING - OPTICAL INSPECTION CONCLUSIONS 2

CAVITY PREPARATION AND ASSEMBLY AT CERN 3

Building 252: - Low pressure ultra pure water rinsing (max 10 bars) - Two clean room ISO 5 SM18: - Assembly area ≈ 120 m 2 - “Baldaquin”: ISO 5 clean room (for tall items such as HIE ISOLDE cavities, main couplers) - Two 13 meters long clean rooms (ISO 7, ISO 4) Well adapted for crab cavities preparation and assembly EXISTING ASSEMBLY AREA AND CLEAN ROOMS 4

CLEANROOM LAYOUT (Existing facility in SM18) Cleanroom facility RF facilities Magnet Cryogenic SM18, plan 5

CLEANROOM LAYOUT (Actual) ISO 7ISO 4 Air Box Built in Goals : Increase cleanliness. Create a rinsing room. Get ride of the Air Box to gain space. ISO FS

CLEANROOM LAYOUT (Updated) 7 Extension of the rinsing room Creation of a preparing room outside of the facility ISO 5ISO 4 Optical Inspection ISO 5

8 Refurbishment of the filtering system with Fan Filter Unit (FFU). Rinsing room extended to 4.5m high to held the HPR. Preparing room based on softwall design. CLEANROOM LAYOUT (Updated)

HIGH PRESSURE RINSING (HPR) HPR from SPEC (US) HP pump (140 bar, 1.1 m 3 3 stages to prevent vibration Rinsing cabinet with top wand design (needed in SM18) Cabinet should shall have a pass trough design => load/unload from different class cleanrooms Drying of the cavity by blowing hot N 2 Rinsing nozzle to be designed 9

ULTRA PURE WATER PRODUCTION Pre-design of the installation Production capacity of 1 m 3 /h UV lamp (185 nm) to prevent bacteria growing and decrease Total Organic Carbone (TOC): C X H Y O Z -> CO 2 + H 2 0 -> H 2 CO 3 -> H + + HCO 3- HCO 3- absorbed by polishing resin. Need to cool down the recirculation water due to the temperature in SM18 10

11 RF TEST FACILITES

NEW RF CRYO INFRASTRUCTURE AT SM18 12 The new cryo line is under replacement (hardware and process) available in march 2013 Vertical test stands 2 cryostats for measurement at 4.5K - 1 long (4m) for spare LHC cavities - 1 short (2.4m) for HIE-ISOLDE 2 new cryostats for measurement at 2K - 1 Long (h= 4m) for Crab (400 MHz) and SPL (704 MHz) cavities - 1 short cryostat (2.5m) New cryostat for 2K measurement - Welded connection - Integrated pumping - Active screening - Earth magnetic field compensation

13 Horizontal test stands Bunker A: -Linac 4 RF structure tests: -> end 2012 Makes use of the existing 352 MHz power system & rad. safe bunker -SPL: MHz RF power system will replace the 352 MHz system 4.5K and 2K measurement Hard cryogenic connection Bunker B: -LHC Spare cryo modules tests, development of LLRF electronics & control tool -HIE-ISOLDE cryo modules (end of 2013) 4.5K and 2K measurement Flexible cryogenic connection NEW RF CRYO INFRASTRUCTURE AT SM18 CCDTL Dismantling old lines

Very crowded area: Cannot be significantly extended (unfortunately) Installation of additional power source + associated power distribution system to be studied in details…but look rather complicated! RF POWER ZONE 14 Equipped with: Demineralized cooling water 100 kV, 40 A power converter 400 MHz, 300 kW CW LHC power system 352 MHz, 1.2 MW pulsed power system (1.6ms/2Hz) - Later a 704 MHz pulsed power system will be installed (1.6 ms / 50 Hz)

AVAILABILITY FOR CRAB CAVITY 15 Cavity tests: Possible (we did a first test in November) Need to improve the cavity support on the insert (under study for the next test) Cryo-module tests: Power source is ok (400 MHz, 300 KW), difficulty for 400 MHz at 2K Bunker B: need of adaption for the cryo connection for 2K (flexible to hard) Bunker A: need to install a new power distribution Complicated (no space), we have to study this in detail, and manage with the other projects One additional cost is to be expected

Common control room for: Each vertical cryostats Each RF bunkers - Complete LHC LLRF system RF CONTROL ROOM 16

17 RF CONTROL RACK FOR VERTICAL TEST STAND

18 TEST CONTROL PANEL PROGRAM Improvement: automatic control of the PLL, τ measurement Labview Program by A. Benoit BE/RF 18

DIAGNOSTIC SYSTEMS 19

20 OSCILLATING SUPERLEAK TRANSDUCER AND TEMPERATURE MAPING OSTs installed around the 4 rods Localized hot spot (default) with 2 nd sound propagation in He superfluid method Ref: K. Liao BE/RF Temperature mapping for elliptical cavity : Using Allen-Bradley resistors temperature sensor (K.Liao) can be adapted for crab cavity

OPTICAL INSPECTION Camera: 3488 x ips Cavity can: – Slide – Rotate Camera can: – Rotate over 180° 21 We have to study how can we adapt it for the crab cavity inspection (support, diameter 70 mm) Ref: J.Chambrillon BE/RF

CONCLUSIONS Preparation and assembly: - Clean room upgrade for high performance cavity at SM18 - New HPR Diagnostic systems: - OST - Temperature mapping - Optical inspection Low power tests: - Four vertical cryostats (2 K & 4.5 K) - New RF cryo line High power tests: - Two bunkers - Bunker A (4.5K): LHC, HIE ISOLDE - Bunker B (2 K): Linac4, SPL - High power area: & 400 MHz high power sources available 400 MHz or/and 2 K need adaptation for the cryo connections or need to install a new power distribution line over cost 22