LS1 planning meeting 22.3.2013. Activities weeks 13, 14 & 15 22/3/13LS1 planning meeting - A.Tauro2.

Slides:



Advertisements
Similar presentations
TC meeting /11/14TC meeting2 ALICE LS1 plan from now till MarchWeeks Install TRD infrastructure46 TRD4&5 (and counterweights removal)47.
Advertisements

LHCC referee meeting – 03/07/2007 LHCC referee meeting – 03/07/2007 Status of the TRD at CERN as of July 2007 TRD Group Physikalisches Institut Universität.
1 Installation of Delphi Frame  ITS Installation.
ALICE planning meeting /12/10 ALICE planning meeting2 Outline ALICE Christmas break schedule –Access UX25, L3 and MNF Services interruption.
ALICE planning meeting /12/10 ALICE planning meeting2 Outline ALICE Christmas break schedule –Access UX25, L3 and MNF Services interruption.
ALICE planning meeting /1/11 ALICE planning meeting2 Outline ALICE Christmas break schedule –Access UX25, L3 and MNF Services interruption.
L.Jirden1 Update on Power Supplies DCS WS L.Jirden u Wiener u Caen u Global Support Contracts.
R. Divià, U. Fuchs, P. Vande Vyvre – CERN/PH 13 June 2012.
TC meeting P2 planning wks 7&8 A.Tauro
Notes After TIG 17/7/08 HF+ Move out of garage: Aug 15* Platform+table+collars+racks+BP support (jack up for platform) = 3 days Controls for motors = 1.
1 5 December 2012 Laurent Roy Infrastructure / Electronics Upgrade -Cabling (long distance) -Rack and Crate (space, electrical distribution, cooling) -Detector.
DCS - general Unscheduled power cut Wed. morning ( , human error) –DCS (and HLT) off, due to UPS on bypass –In the middle of DB migration, had.
winter shutdown preparatory meeting A.Tauro /1/12ALICE winter shutdown schedule - A.Tauro 1.
winter shutdown planning A.Tauro
Installation and Commissioning Planning Leslie Camilleri Calorimeter Commissioning Meeting 5 th September 2006.
LS1 reference slides LS1 plans Detector’s plans Services and central systems availability 8/2/13LS1 planning meeting - A.Tauro1.
ALICE 5 o’clock meeting Wk 50. INDICO You’ll find this meeting here: – The full shutdown planning.
Claudio Bortolin. 1 st June: PT100 electrical connection failure (Temp Chiller water In&Out) 1) it required an access to the cavern to be fixed 2) access.
LS1 planning meeting Comments on LS1 schedule Schedule reviewed last week with Yann + TC…  sequence after OD looked too squeezed  therefore.
ALICE Collaboration Meeting Heidelberg Services Update  Progress on services Detector cabling Gas systems Cooling systems  Rack footprint  Primary electrical.
P2 status, LS1 planning A.Tauro - W.Riegler. Outline TS2 activities Detector activities during LS1 Proposal for ALICE recommissionig plan in 2014 Conclusions.
TS4 preparatory meeting TS4 – weeks Underground access possible in week 51 – as from Monday morning 9:30 –Ulli and Philippe will start.
winter shutdown preparatory meeting A.Tauro /12/11ALICE winter shutdown schedule - A.Tauro 1.
Run 12: STAR Status and Schedule Update RHIC Coordination Meeting October 18, 2011 Bill Christie BNL Outline Status update Schedule update and issues Summary.
ALICE 5 o’clock meeting Wk 51. INDICO You’ll find this meeting here: – The full shutdown planning.
ALICE TC meeting – Plans for the next technical stop A. Tauro.
TS planning meeting 7 to 11 Nov Technical stop Wk 45: Monday 7 th to Friday 11 th November Ramp down magnets (SL): Mon 8:00 – 8:30 (latest) RP search.
winter shutdown planning A.Tauro
winter shutdown planning A.Tauro
TS May 9-12 – Schedule SL instructions: Both magnets ramped down Monday May 9 th 7:00 latest Thursday: check with CCC before restarting magnets: – TE-EPC.
LS1 planning meeting /4/13 ALICE TBStatus of LS1 activities - A.Tauro2 LS1 plan 2013Weeks Remove plug, mobile shielding, open doors8-9 Prepare.
ALICE planning meeting /2/11 ALICE planning meeting2 Outline ALICE Christmas break schedule –Access UX25, L3 and MNF Services interruption.
TC meeting P2 planning wks 9&10 A.Tauro
TC meeting LS1 plan 2013Weeks Remove plug, mobile shielding, open doors8-9 Prepare for PHOS extraction, remove RB24 beampipe and PMD10 Remove.
February 14, Comprehensive Review B. Schmidt Outline: Status and overview of activities: –Platforms and staircases –Muon Filters and beam plugs.
André Augustinus Infrastructure  Turbines  Radmon  Thermocouple readout  Netgear redundancy  Other cavern items  Cooling CRs  Other CR and surface.
Michel RAYMOND – July 1 st, 2013 Technical Support Activities in PH-ADO-PO Summary of 2013 activities.
TPC Collaboration Meeting Peter Glassel 1 Reminder on Installation Schedule (ALICE Forum June 2002)  Install Muon magnet directly into experimental.
ALICE 5 o’clock meeting Wk 49. INDICO You’ll find this meeting here: – The full shutdown planning.
winter shutdown planning A.Tauro /1/12ALICE winter shutdown schedule - A.Tauro 1.
DCal Insertion Tooling 24/02/ DCal Insertion Tooling DCal Insertion System feature following main components 1. One rotator : cylindric welded structure.
TC meeting P2 planning wks 5&6 A.Tauro
TS2 preparatory meeting A.Tauro. General information LHC- TS2: from Monday 31st 6am, to Friday 4th 5pm LHC beam stops on Monday morning.
LS1 planning meeting /7/13LS1 planning meeting - A.Tauro2 LS1 plan 2013Weeks Remove plug, mobile shielding, open doors8-9 Prepare for PHOS.
TOF status and LS1 plansTOF status and LS1 plans 27/06/2012.
1 Planning DCS WS L.Jirdén. 2 TPC HMPID ACORDE FE PC Console DSS Disk SRV DB-SRV App GW sensors actuators DSS sensors actuators PC room SXL2.
1 Update on Power Supplies TB L.Jirden u LV u Concerns u Orders & deliveries u Maintenance u HV u Overview u purchasing.
TS3 preparatory meeting 14/9/2012 TS3: 17-21/
ALICE 5 o’clock meeting Wk INDICO You’ll find this meeting here: – The full shutdown planning.
TS3 preparatory meeting A.Tauro. General information LHC-TS3: from Mon 9 6am, to Fri 13 5pm LHC beam stops on Mon morning at 6:00.
TC meeting P2 planning wks 3&4 A.Tauro
ALICE planning meeting /11/10 ALICE planning meeting2 Outline ALICE Christmas break schedule –Access UX25, L3 and MNF Services interruption.
ALICE planning meeting /1/11 ALICE planning meeting2 Outline ALICE Christmas break schedule –Access UX25, L3 and MNF Services interruption.
DCal-ALICE integration and installation plan and status A. Tauro.
Plans for the UT Installation LHCb infrastructure workshop February Burkhard Schmidt for the UT group.
21 Mar 2007ALICE - Paul Dauncey1 ALICE CR07: Installation and Commissioning Paul Dauncey Material from: L. Leistam: “ALICE Status” W. Riegler: “Commissioning.
ALICE Installation: Planning Meeting Agenda: 1- ALICE shutdown schedule 2- Miniframe removal sequence.
ALICE 5 o’clock meeting Wk 50. INDICO You’ll find this meeting here: – The full shutdown planning.
EYETS planning A.Tauro.
ALICE 5 o’clock meeting Wk 51.
ALICE planning meeting
TS2 preparatory meeting
LS1 planning meeting - A.Tauro
LS1 planning meeting
ALICE 5 o’clock meeting Wk
TS1 preparatory meeting
ALICE TC meeting – Plans for the next technical stop
Fiber Installation for RUN 3&4
Shutdown conclusion, LS1 and LS2 planning - A.Tauro
ALICE 5 o’clock meeting Wk
Presentation transcript:

LS1 planning meeting

Activities weeks 13, 14 & 15 22/3/13LS1 planning meeting - A.Tauro2

Access situation No access restrictions foreseen in the coming weeks L3 access will be “less comfortable” (O-side staircase) on Mon 8 and Tue 9 April due to TRD17 removal 22/3/13LS1 planning meeting - A.Tauro3

Recap week 11 (11-17/3) P2tech + ALTEAD + PHOS: remove PHOS modules and cradle (Mon-Thu) P2tech: open miniframe false floor (Mon PM or Tue) – No access on MNF during PHOS removal P2tech + ALTEAD: remove PHOS rail extensions and shuttle (Fri) TPC laser / FMD (Borge) (Thu-Fri): –Check laser intensity with lower laser power - for reference. –Remove a broken electronics board and bring it home for repair. –Inspect the FMD cooling pipes on the C side. Muon TRK: dismount and soldering of CH5R (whole week) T0: detector inspection (Fri) – had to open the T0 protection BE-ABP-SU: survey ALICE network points ALTEAD: unload UPS racks (SR building) (Tue PM) – Put in SX2 P2tech: unfold PHOS LV cables – There are still a few (5) cables not belonging to PHOS!!! EN-HE-LM: maintenance cavern lift (4:00 to 6:00 AM) and CR lift (6:00 to 8:00) (Fri) SPIE: install cable-trays and pull UPS cables PX24 L3: EMC: replace FEE cards (whole week) P2tech: install modified rails SR4 (2 days around the end of the week) 22/3/13LS1 planning meeting - A.Tauro4

Recap week 12 (18-24/3) Ouvaroff: scaffolding inside L3 + C-O side (Wed-Thu) – Scaffolding too close to SF!!! Arturo to contact Gianluca SSD: remove CAEN LVPS (120). Need crane! BE-ABP-SU: survey Space Frame and Cal-Frame Muon TRK: work on CH6L and CH5 R (whole week) ALTEAD + P2tech: test insertion tooling for DCal rails (O-side) P2tech: modify PHOS LV PP Removal barracks: 6124 (V0), 6253 (TRD) and 6204 (PMD) (Mon-Thu) EN-HE: replace UX25 door (SAS downstairs) ALTEAD: put beampipe box above L3 (ACORDE area) ALTEAD: displace beam in SX2 for UPS project (Mon) EN-CV-DC: remove water from TRD (today) and TOF cooling plants L3: EMC: change the existing (RCU-based) readout to the new (SRU-based) readout (whole week) TPC work (C-side) – ongoing P2tech: transfer TOF crates to spaceframe (whole week) - ongoing 22/3/13LS1 planning meeting - A.Tauro5

Week 13 (25-31/3) ALTEAD + P2tech: test insertion tooling for DCal rails (I-side) (Mon-Wed) P2tech: L3 services modifications (whole week) BE-ABP-SU: survey TRD SMs Muon TRK: work on CH6R and CH5 R (whole week) – need ALTEAD to install rail on Wed GS-ASE: SNIFFER maintenance Delivery of a DCal standard SM (3 rd ) (Tue) P2tech + ALTEAD + Nantes: mount DCal rotator and install PHOS rails in SXL2 (Tue-Thu) Arrival 45 racks + doors CR1 (exact date tbc) – storage inside SR2 L3: P2tech: L3 services modifications (whole week) EN-EL-CF: displace PHOS-HMPID optical patch panel + check for spare fibers in EMCal patch panel EMC: change the existing (RCU-based) readout to the new (SRU-based) readout (whole week) TPC work (A&C sides) P2tech: transfer TOF crates to spaceframe (whole week) 22/3/13LS1 planning meeting - A.Tauro6

Week 14 (1-7/4) UX25: P2tech: L3 services modifications (whole week) P2tech: preparation C-side support for DCal beams (whole week) P2tech + ALTEAD: install L3 staircase to O-side (Tue) P2tech + ALTEAD: remove miniframe staircase and install temporary ladder (Thu) ALTEAD: bring yellow platform + rotator to UX25 cavern (Thu PM) ALTEAD: remove L3 staircase from I-side (Fri) – L3 access from O-side only P2tech + ALTEAD: install rail for yellow platform on I-side (Fri) ALTEAD: install yellow platform on I-side (Fri) BE-ABP-SU: survey babyframe + A-side beampipe flange + TPC feet P2tech + SPD: connect old inlet lines to SPD cooling plant (1/2 day) L3: P2tech: L3 services modifications (whole week) P2tech: remove old PHOS cooling pipes along I-side beam EMC: change the existing (RCU-based) readout to the new (SRU-based) readout (whole week) TPC work (A&C sides) Surface: P2tech: load test DCal extension ribs (Tue-Wed) ALTEAD: remove 35t beams from SX2 (rent Frederici truck) (Tue-Wed) Removal barracks 6120 (HLT), 6121 (MTR) and 6122 (MTG) (Thu-Fri) 22/3/13LS1 planning meeting - A.Tauro7

Week 15 (8-14/4) UX25: P2tech: L3 services modifications (whole week) TRD + P2tech: take out TRD17 (Mon) – L3 access from O-side only P2tech + ALTEAD: move L3 staircase from O-side to I-side (Tue) P2tech + ALTEAD: install yellow platform on O-side (Tue) TRD + ALTEAD: take out TRD7 (Wed-Thu) TRD: modify TRD7 in Low-Beta (Thu) TRD + ALTEAD: reinstall TRD7 (Fri) TRD + ALTEAD: remove TRD8 (Sat) – ALTEAD, Yannick, Werner available? Muon TRK: work on CH6L and CH5 R (whole week) BE-ABP-SU: survey babyframe, TRD feet and A-side beampipe flange during/after each TRD removal (whole week) L3: SPD: drill filter SR3 P2tech: L3 services modifications (whole week) EMC: change the existing (RCU-based) readout to the new (SRU-based) readout (whole week) TPC work (tbc) Surface: P2tech + ALTEAD + Nantes: DCal insertion test in SXL2 (60 and 40deg) (whole week) P2tech: install ZDC fences in SXL2 (provided by ALTEAD) SDD: swap SuperCarlosRX boards in CR4 (whole week) 22/3/13LS1 planning meeting - A.Tauro8

TPC FEC replacement Task: – 9 Front End Cards need to be replaced – One readout branch (C00 rp0) is not working properly and maybe all 9 FECs should be replaced there Plan: – Week 12: Start on C side – Weeks 13-14: Finish C side and move to A side – Week 15: In case of delay Status: – Week 12 used mainly to set up and start with easy cases – 4 FECs replaced so far 9

FEC kaputt: List 1)A03Rp3BrAFec03 PASA/ALTRO 7 dead (no pulses) 2)A03Rp3BrBFec06 PASA/ALTRO 6 dead (no pulses) 3)A09Rp3BrAFec06 PASA/ALTRO 7 dead (no pulses) 4)A12Rp5BrAFec03 hot, but works ok 5)A13Rp0BrAFec07 data corruption 6)C00Rp0BrAFec04 needs detailed investigation 7)C01Rp5BrBFec05 conn 0 bad or PASA kaputt 8)C03Rp0BrBFec05 conn 0 bad or PASA 0 and 1 kaputt 9)C13Rp4BrBFec00 conn 5 bad or PASA 7 kaputt (3 ch) 10)C16Rp3BrBFec07 conn 5 bad or PASA 7 kaputt FEC not workingMany channels not working Some channels not working 10

Visits in the coming weeks 22/3/13LS1 planning meeting - A.Tauro11

AOB On 2 nd April there will be a software upgrade to some routers on the General Purpose Network. This will affect for P2 the GPN routers in 2275 (SR2). This is the entry point of the GPN (and others) for P2, so by that it will affect all P2. The impact is a 10min interruption of the connectivity (the time to install firmware and reboot). On 1 st June there will be a similar intervention, again on GPN, but CERN-wide 22/3/13LS1 planning meeting - A.Tauro12