Urban Transport -How to address the commercial road blocks Urban Transport Congress India 2010, Mumbai 25 th June, 2010 Brijgopal Ladda, Head – CRISIL.

Slides:



Advertisements
Similar presentations
STATE REVOLVING FUNDS: THE INDIAN CONTEXT PARIS 2003.
Advertisements

Introduction to PPP in the EU RCC PPP Conference, Sarajevo, 25 September 2009 Michael Burnett, Director, European PPP Forum, European Institute of Public.
West Michigan Transit Linkages Study Wednesday, June 4 th, :00 a.m. Grand Valley State University Kirkhof Center Conference Room 2266.
Transport for Canberra 07 November2013. Transport for NSW: Regional Transport Plan ACT, whilst not part of the region, is an important destination Transport.
A framework for organising and financing infrastructure provision Jan-Eric Nilsson, VTI.
Second Annual Conference on Intra-City Transportation Systems
Funding Growth Projects Doug Devereaux Clara Asmail NIST MEP Presentation to INEAP April 25,
Public Debt Management with emphasis on PPP 1 Ministry of Finance 08 th Dec 2014.
The new LIFE Programme INFO Day Brussels 12/5/2014 Antongiulio Marin Policy officer – DG CLIMA.
DMICDC  Landscaping & signage  Street lighting  Building works  Telecommunications  Gas grid  Captive power plant  Renewable energy plant  Light.
Summary of Conference Proceedings Prof H. M. Shivanand Swamy CEPT University September 8, 2012 Ahmedabad Management Association.
White Paper 2011 and Development Perspectives of Transport System in Latvia Guntars Jansons Manager Development Planning.
Markham Centre TDM and Land Development Case Study ACT Canada – TDM Summit October 21, 2008.
Dr Lina Shbeeb Minister of Transport. Jordan
Brief Overview of the Passenger Transport Sector in the Philippines Gilberto M. Llanto C.P. ROMULO HALL, NEDA SA MAKATI BUILDING May 7, 2013.
3 rd Annual California Passenger Rail Summit Innovative Transportation Financing Art Guzzetti Vice President – Policy American Public Transportation Association.
Urban Transport Benchmarking Initiative Paris and the Urban Transport Benchmarking Initiative Isabelle Bachmann- RATP- Paris.
Viability Gap Funding By Ashok Chawla Additional Secretary Department of Economic Affairs, Government of India 20 th December, th December, 2006.
ROLE OF DIFFERENT STAKEHOLDERS AND HYBRID FINANCIAL MECHANISM OF MHI Public Private Partnerships or PPPs as Means of Financing Infrastructure in MHI Projects.
1 India - Opportunities in Infrastructure for Foreign Investors Arvind Mayaram Department of Economic Affairs Ministry of Finance Government of India.
Finance for Rental Housing Steve Bevington Managing Director Community Housing Limited Group, Australia.
BETTER AIR QUALITY 2004 SPECIFIC TRANSPORT MEASURES TO REDUCE EMISSIONS IN HYDERABAD, INDIA Yash Sachdeva, RITES Ltd Viresh Goel, RITES Ltd D.S.Chari,
Presentation by: Permanent Secretary - PMORALG Mr. Jumanne Sagini 3 rd June 2014.
1. 2 VIA Long Range Plan  Vision for High-Capacity Transit across VIA service area by 2035  From extensive public and stakeholder input  Prioritization.
Urban Transport in the Developing World. Elements of Urban Transport Sector Urban public transport: Urban public transport: On-street systems (for buses,
Financing Urban Public Infrastructure
AFD’s strategy of intervention towards Sustainable Urban Transport in China Herve Breton AFD Shanghai Nov.2008.
Materials developed by K. Watkins, J. LaMondia and C. Brakewood Regulation & Finance Unit 7: Forecasting and Encouraging Ridership.
Paul Roberts – TIF Technical Manager Presentation to the TPS – 3 June 2009.
Beech Grove, Indiana TAX INCREMENT FINANCING Heather R. James, Ice Miller LLP April 18, 2013.
Competition Reforms in Bus transport sector In Zambia National Advocacy Plan (CREW Project) CREW NRG-IV Meeting, 22 nd April, Lusaka.
INDIA’S INFRASTRUCTURE – Issues and Prospects PRESENTATION BY SS Kohli Chairman & Managing Director INDIA INFRASTRUCTURE FINANCE COMPANY LTD NEW DELHI.
LOCAL GOVERNMENT INFRASTRUCTURE NEEDS vs DEVELOPMENT CHARGES.
Leveraging Urbanization in South Asia
Jeff’s slides. Transportation Kitchener Transportation Master Plan Define and prioritize a transportation network that is supportive of all modes of.
 City of Hamilton – Transportation Sustainable Mobility Summit – October 27, 2013.
CREW Project Research Findings of Diagnostic Country Report (DCR), Ghana Bus Transport Sector.
Green Transport Dr Lina Shbeeb Minister of Transport. Jordan.
The Palestinian Perspective on the Cooperation in R&D in Sustainable Urban Mobility Khaled Al-Sahili An-Najah National University Palestine Rabat 19 May.
NEW STRATEGY FOR TRANSPORT GOVERNANCE IN MONTREAL March EMTA Meeting, Madrid.
TRANSPORT The Cambridge Futures response to the Draft Structure Plan Dr Tony Hargreaves, Cambridge Futures.
Seite 1 REETA Planning Workshop, Georgetown 11./12. February 2014 Developing Public-Private Partnerships for Sustainable Energy.
Project Information Brief project description Cairo, Egypt Bus Rapid Transit System with potential capacity of 45,000 people per person per direction Phase.
Transit Revitalization Investment Districts Planning and Implementation of Act 238 of 2004 July 2006 Getting to TRID Lynn Colosi Clear View Strategies.
February 2014 Bus Rapid Transit for Chennai. Chennai city bus service GOOD PATRONAGE  50 lakh daily passenger trips  3650 buses  Maximum flow of.
Public and Private Partnerships in the Baltic Region: Experience of Riga City.
Public Private Partnerships (PPPs) and The World Bank
Presentation on Strategies for Infrastructure Development in Karnataka By: V. P. Baligar.
7 May 2014 Sustainable transport vision for Greater Cairo.
Venture Capital. Venture capital refers to organized private or institutional financing that can provide substantial amounts of capital mostly through.
1 Presented to the Transportation Planning Board October 15, 2008 Item 9 Metrobus Priority Corridor Network.
International Logistics Centres for Western NIS and the Caucasus Georgia: Areas in the vicinity of Tbilisi airport Ministry of Economy and Sustainable.
Kiichiro Fukasaku Development Centre
CAI-Asia is building an air quality management community in Asia Investment Implications of the Action Plan Sustainable Urban.
THE PUBLIC FINANCE DEBATES: “It’s time…New Zealand extended charging for public infrastructure” Opponent: Peter Conway.
Submission Document went to cabinet … Planning for the Future Core Strategy and Urban Core Plan (the Plan) is a key planning document and sets out the.
 Contract by Public Authority for provision of asset and/or services  With private entity  Private finance used to fund asset/service  Long-term in.
Raising finance for a ULB Strengthening Urban Management ASCI / WBI Workshop, January 21, 2003.
Mortgage Finance Opportunities and Challenges By Taimur Afzal, Chairman ASSOCIATION OF MORTGAGE BANKERS (AMB) March 25th
Budget Workshop Capital Improvement Plan Presentation on Public Private Partnership and Strategy for Municipal Complex, HWY 50, and Coast to Coast Trail.
World Bank Financing Instruments and Projects in Serbia
Using Public-Private Partnerships to Move More People The Story of HOT Lanes in Northern Virginia January 30, 2017 Morteza Farajian, Ph.D.
Greater Toronto Transportation System
The Hong Kong Mortgage Corporation Limited (HKMC)
FINANCING URBAN TRANSPORT INFRASTRUCTURE: INDIA
Challenges in Financing Renewable Energy
Public Private Partnerships
Transportation Task Force Mission and Vision
Blended Finance Options for Local Development
BASICS OF PUBLIC PRIVATE PARTNERSHIPS
Presentation transcript:

Urban Transport -How to address the commercial road blocks Urban Transport Congress India 2010, Mumbai 25 th June, 2010 Brijgopal Ladda, Head – CRISIL Infrastructure Advisory

2. In Nutshell- The Indian Transport sector There is a huge transit demand In large cities public transportation however inadequate, high level of rider-ship is observed during peak-hoursIn large cities public transportation however inadequate, high level of rider-ship is observed during peak-hours Incidence of car trips are bound to rise due to raise in income levels and affordability Consensus and policy framework is in place for mass transits system that is sustainable, efficient, reliable and affordable- The National Urban Transport Policy Few initiative exist in this direction, their success would need to be reviewed and to be replicated in other cities

3. Urban Travel Demand- In India Cities By 2021 the travel demand is likely to increase by over 2.5 times Current level of Public Transport system will not be able to meet this demand Planned & Mass Public Transport System is the need of the hour……

4. Mode Share – In India Cities A recent study indicated that during the period the share of public transport has declined considerably across all category of cities City CategoryWSA- 2007Rites – 1994 % Trips by Public Transport Cities with Population < 0.5 Million Cities with Population Million Cities with Population Million Cities with Population Million Cities with Population Million Cities with Population > 8 Million Note: WSA Results based on survey of 87 cities, while RITES results are based on 21 cities Source: Traffic & Transportation Policies and Strategies on Urban Areas- A study by WSA Inc & CRISIL However in large cities public transport is still the single largest carrier The lower patronage can be attributed quality & reliability of public transport system…..

5. The Key challenges in urban transport… 1/2 Arriving at the right affordable transport model for the city to address: –Dispersed growth – low-medium density –Expansion of cities -increasing trip lengths Ridership – demand estimation need to be realistic –In most projects demand estimation have surpassed than what was conceived Issues- related to planning process –In most cities urban transport is not primary responsibility of ULBs –Substantial delays in land acquisition leading to cost escalation –Overlapping jurisdiction in large urban agglomerations – need for unified transport authority

6. Implementing Agency- Perspective –High investment needs and budgetary constraints –Fare-box revenues alone not sufficient for viability –Need to explore alternate revenues to finance projects  Need to have densification and TDR policy  Need to capture incremental benefits & indirect revenues Developers Perspective –Large project size –Long gestation period –Non availability of attractive PPP Models Financial institutions –Reluctant & Selective to fund large projects –Lenders expects higher equity contribution –Concerns on contractual provisions to protect lenders interest The Key challenges in urban transport… Stakeholders perspective (2/2)

7. High Investment Need– Limited Finances By 2027 an investment of Rs. 4,350 bn is required to meet the urban transport needs Investments leaning towards capital intensive mass transit systems- BRT & Rail based Financing shall be a constraint –19 BRTS projects have been sanctioned under JNNURM with a project cost of Rs bn –But funding under JNNURM is limited –Few MRTS projects in pipeline –Viability Gap Funding is limited to a maximum of 20%-40% of project cost Source: Traffic & Transportation Policies and Strategies in Urban Areas in India, MoUD Study by WSA Inc Above estimates are based on study of 87 cities in India for a period of 20 years

8. How these concerns are impacting the Projects? Mumbai Metro- Line 2 –Project Cost : Over Rs. 7,500 crores –Of the seven qualified bidder only one submitted the Financial –Requested for 27% VGF Mumbai Sea Link Project –Project cost : Over Rs crores –Only 2 out of 17 qualified bidders submitted bids Hyderabad Metro ?

9. Should these concerns tempt for public funding in UT ? Currently private sector investments are low in urban transport Currently real estate component is not that attractive Should government move towards public funded infrastructure ?- No –Government is constrained by its budget, so can’t finance many projects –These large project need new skills sets –It would discourage private sector to invest in infrastructure Having developed PPP market Government should: –Facilitate & promote more private finance in infrastructure : –Explore alternate project finance options intermittent to Public funding and PPPExplore alternate project finance options intermittent to Public funding and PPP –Increase project viability by targeting indirect beneficiaries/sourcesIncrease project viability by targeting indirect beneficiaries/sources

10. Explore Intermediate options The extreme ends of the PPP continuum are not workable in situations of crisis Hence need to develop intermediate Public funded and private operated Private funded and private operated Continuum of PPPs Service contract Management contract Concession Annuity projects Viability Gap Funding assisted projects Unlocking value Intermediate options

11. Direct and Indirect beneficiaries Passengers of a public transport system Vehicle owners using a flyover/facility Businesses based on the infrastructure- advertisers on the system, vendors Indirect Beneficiaries Property owners near the developed transport system- gaining from higher potentail value of property Business around the transport system- gaining from better connectivity Local Government- gaining higher property taxes in the region due to escalation in property prices Direct Beneficiaries

12. PCMC BRTS Model– Is a model to be replicated ?

13. Concept of Pimpri Chinchwad Municipal Corporation Corridor Densification by TDR -linked Land Use Control and Infrastructure Financing Mechanism

14. Pimpri Chinchwad Municipal Corporation (PCMC) is developing 130 km of bus based mass transit corridors PCMC has set up an Urban Transport Fund (UTF) to finance the project The UTF to be managed by a SPV wholly owned by PCMC A zone of 100 m on either side of the corridor designated as BRT influence zone Loading of Transferable Development Rights (TDR) PCMC allows TDR from other parts of the city to be loaded on the BRT influence zone on the payment of a loading premium Building permission charges in the zone The building permission charges in the influence zone allowed to the UTF Incremental Property Taxes The BRT influence zone is designated as high tax rate zone- the incremental revenue is allowed to the UTF Real Estate, Advertisements & lease of utility ducts Value unlocked from Indirect Beneficiaries Unlocking value from indirect beneficiaries in Pimpri-Chinchwad

15. Design of the fund Notified 100 m on either side of BRT route as BRT corridor zone –Increased ceiling FSI from 1 to 1.80 –0.80 loading is through TDR with payment of a premium Advantages –Does not release additional FSI in the city; only realigns the FSI from other zones to BRT Corridor –Will protect the value of TDR and make it more attractive –PCMC can plan higher order infrastructure in BRT corridor and facilitate focused service provision by densification –Ensures the attractiveness of mass transit

16. SPV for BRTS – PCMC Infrastructure Company Ltd The SPV is 100% owned and controlled by PCMC Will help PCMC to raise long term loans (12 yrs +) from multilateral agencies IFC, ADB SPV ensures focussed and timely implementation, necessary for projects with borrowing SPV will focus on generating the revenues for the projects Strengthens the transit corridor densification approach for project sustainability

17. Sustainability of the model The road network designed to cater to future growth patterns of the city –It is a priority based approach –Will spur substantial real estate development Funding model is designed to capture this future growth benefits to fund road development Fund makes the revenues secure which helps raise finance from lending agencies Without fund structure it will be difficult to channelize earnings from indirect beneficiaries into development

18. Strategies to make to BRT attractive State of Art BRT system for fast and cost effective transit Higher order infrastructure for attracting densification –24/ 7 water supply –100% sewerage provision –Dust Bin free zone Road design –Service lanes for mobility of local traffic –Provision for pedestrians – under pass, walk ways –Provision for non motorized vehicles – cycle track Facilities for vehicle parking –100% extra parking; –25% to be handed over to PCMC for public parking Miscellaneous –Wi Fi connectivity –Hawker zones

19. Key Take aways The key factors for success of PCMC Model –The model requires real estate momentum to ensure that TDR loading –Mumbai Pune corridor has already been commissioned – land rates have seen upward revision –Mumbai Pune and Aundh Rawet will create the necessary momentum for sustaining the cycle for other roads –The stage is now set for scaling up Key aspects for success of public transport –Planning  Proposals to be backed by comprehensive traffic studies and realistic forecast  To be linked with land use –Financing  Exploit all sources of revenue to improve the financial viability  Creation of an Urban Transport Fund (UTF) by pooling non fare based revenue to fund projects  Create of a Special Purpose Vehicle to manage the UTF –Contracting/Management  Risk allocation between government and private sector need to realistic  It is impossible to plan for all contingencies- Need for flexibility in concession agreement to renegotiate

Thank You

21. Other PPP models complementing the project Awarded contract on PPP basis for road furniture –Bus stops –Public toilets –Landscaping –General Maintenance Advertising rights offered for 5 years on specific locations on Mumbai Pune road – 12 kms Total benefit of Rs Crores to PCMC

22. Total income potential of BRT corridors – Rs Crs

23. Funding model Rs Crores Total Project cost1500 Funding model JNNURM (GoI and GoM)475 PCMC internal sources100 Debt from DFI, Multi laterals, Banks650 Internal accruals and exploitation of land275 Total sources1500

24. Important questions Why increase by only 0.80 and not more? –Follow approved practice and not attract litigation by going for more –Keep the infrastructure provisioning within manageable limits and improve it by focused provisioning –Maintain equilibrium between generation and absorption of TDR Why change the philosophy of spreading away from main roads? –Densification supports use of mass transit and increase its attractiveness –Can sustain development by increasing earnings (premium) from direct beneficiaries