Berliner Energieagentur GmbH WP 2 training session EPC project development models Berlin, 2006-02-08 Dipl.Ing. Vollrad Kuhn, Berliner Energieagentur GmbH.

Slides:



Advertisements
Similar presentations
Institute for Road Construction and Maintenance - Vienna University of Technology ISTU O PTIMIZED P AVEMENT D ESIGN W ITH R ESPECT TO Q UALITY AND E CONOMY.
Advertisements

PROJECT MANAGEMENT & BUSINESS PLANNING PROCESS
Monitoring and tender procedures for infrastructure projects Baltic Retreat 2013 Federal Department of Foreign Affairs FDFA Swiss Agency for Development.
Procurement Management
Session 8 Implementing PPPs
Presentationby Construction Association of Bhutan.
A case of Armenia: Legal framework for E-procurement in Public Procurement Sector Mr Karen Brutyan, PhD, PFM and PP EBRD Consultant, Wolf Theiss 1-2 December.
Confederation of International Contractors’ Associations ______________________________________________________________________________________________________________________________________________.
Module 11 Session 11.2 Visual 1 Module 11 Executing and Controlling the Work Session 11. 2: Managing Contracts.
1 Use and content of the RFP  Request for Proposals (RFP) is similar to bidding documents and include all information of the assignment, selection of.
© Prentice Hall CHAPTER 10 Alternative Approach: Purchasing Systems.
Marcy Mealy Procurement Specialist CDBG Program
Control procedures in polish public procurement law Public Procurement Office 2007.
1 MANUFACTURING AND PRODUCTION OF BIOLOGICAL PRODUCTS (ERT 455) HAZARD ANALYSIS AND CRITICAL CONTROL POINT (HACCP) SYSTEM Munira Mohamed Nazari School.
Project Cost Management Estimation Budget Cost Control
Phases of A BOT Project Prepared By :Afaf Bu-khawa Course title: Technology Implementation,MGT 620.
Circular A-110 Everything You Didn’t Want to Know.
EPC: baseline adaption. Berliner Energieagentur GmbH EPC: baseline adaption Yearly accounting of energy savings - overview corrected energy costs costs.
Risk management. Berliner Energieagentur GmbH Risks of EPC Equipment transfered into the property of building owner at the moment of installation and/or.
Energy Performance Contracting Approach David Birr President Synchronous Energy Solutions.
Construction Engineering 380 Professional Design Services Chapter 12 Appendix G.
INNOVATIVE PROCUREMENT The Next Steps Anthony Cachia Director (Operations) Department of Contracts.
© OECD A joint initiative of the OECD and the European Union, principally financed by the EU Martin Oder, LL.M. The Emerging Role of the Competitive Dialogue.
1 EU Public Procurement Lab Meeting - London (c) Kathrin Hornbanger, MBL-HSG Federal Procurement Agency in Austria - Chances and risks of central public.
The Importance of the Qualifications Based Selection (QBS) Process
1 1 Module II. Bidding and Evaluation Process I.Bidding documents (Stages of bidding & preparation of bidding document) II.Bid evaluation methods (principles.
Nabil dmaidi1 Bid Submission Documents A LATE BID IS NO BID.
M. Reimeris, The Ministry of Finance of Lithuania (Managing Authority)
Phoenix Convention Center Phoenix, Arizona A Review of the Current DOE IDIQ Track 5: Project Financing Session 3: ESPC Large and Small: The Basics of ESPC.
S10 CONS5Q25 Lara Tookey. Review of estimators workings Decision on what margin to apply Bid submission details Submit your Tender.
EARTO – working group on quality issues – 2 nd session Anneli Karttunen, Quality Manager VTT Technical Research Centre of Finland This presentation.
Developing and Issuing the RFP. Why should qualifications be your procurement focus? n Having the necessary range of capabilities is more important than.
Public-Private Education Facilities and Infrastructure Act 2002 (PPEA) Joe Damico.
1 Ensuring the protection of bidders’ rights.  The Federal Law of № 94-FZ "On placing orders for goods, works and services for state and municipal.
III Astana Economic Forum. Ensuring Sustainable Economic Growth of Countries in Post-Crisis Period July 1-2, 2010 JSC «Kazakhstan public-private partnership.
Presentation made by 3D High School G.B. Bodoni.  What is it? Business Plan is a planning document that describe in detail the business project and allows.
Bank guarantees or letters of guarantee Know the letter of guarantee or bank guarantee is a written undertaking by a Bank, usually at the request of the.
1 E F F I C I E N C Y D E C I D E S State Properties and public Buildings. Energy costs: about 3.5 billion €/year Source: Umweltbundesamt, 2000 and own.
Contractor Alternate Design Serving the Public’s Best Interest.
PPP Legal & Regulatory Framework. PPP Policy In July 2008 GOK approved the PPP policy directive through which: PPPs are identified as a method for investing.
Application procedure From theory to practice Dieter H. Henzler, Steinbeis-Transfercenter Cultural Resources Management, Berlin.
Outsourcing of Census Operations United Nations Statistics Division UNSD-ESCWA Regional Workshop on Census Data Processing in the ESCWA region: Contemporary.
EMTA General Meeting Prague May 2012 Round table on PSO Regulation 1370/2007 “Two years after enforcement, where are we? How efficient is the regulation?
Outsourcing of Census Operations United Nations Statistics Division Regional Workshop on the 2010 World Programme on Population and Housing Censuses: International.
The Design/Build Contract. What Is A Design/Build Contract? Contract that combines design & construction into one agreement The design/build team provides.
Energy Auditing – Energy Conservation and Efficiency Measures PRESENTER Mr. A. Hamukale BENG, Meng,MBA,PEEIZ,REng.
NAMA potential of Vietnam Vuong Xuan Hoa Institute of Meteorology, Hydrology and Environment Ministry of Natural Resources and Environment Climate Change.
Improving performance, reducing risk Dr Apostolos Noulis, Lead Assessor, Business Development Mgr Thessaloniki, 02 June 2014 ISO Energy Management.
PRE-PLANNING FOR CONSTRUCTION PROJECTS. OVERVIEW ASSESSING OWNER CAPABILITIES ANALYSIS OF RESOURCES REGULATORY REQUIREMENTS SITE DEVELOPMENT REVIEWING.
Instruction of NCP to Procurement and Small Scale Contracting funded from the EEA and Norwegian Funds Czech-Norwegian research programme CZ09.
The Public Tendering and Bidding (招投标) Law of the People's Republic of China Effective since January 1, 2000.
Contract management 1. Acquiring software from external supplier This could be: a bespoke system - created specially for the customer off-the-shelf -
ROMANIA NATIONAL NATURAL GAS REGULATORY AUTHORITY Public Service Obligations in Romanian Gas Sector Ligia Medrea General Manager – Authorizing, Licensing,
Assessment of the Bidding Process in Construction Project ABDULLAH H. ABU ZANT. AYMAN K. ILAIWI. MOHAMMED FADEL. SODQI M. ALHNAINI. AN-NAJAH NATIONAL UNIVERSITY.
Make or Buy transport.
EPC CONCEPTS and BUSINESS CASES
Reconstruction site Investigation, Planning, Scheduling, Estimating and Design Eng. Fahmi Tarazi.
12.2 Conduct Procurements The process of obtaining seller responses, selecting a seller and awarding the contract The team applies selection criteria.
M. Reimeris, The Ministry of Finance of Lithuania (Managing Authority)
International Open Procedure (1) – PRAG 4.3
PRE-BID MEETING ITB UNDP Design and Construction of a new medical warehouse in Bissau, Guinea Bissau 15th August 2017 Presented by Antoine Fadoul UNDP-
Business environment in the EU Prepared by Dr. Endre Domonkos (PhD)
Developing and Issuing the RFP
FIVE PROJECT PHASES 5C-3 Sun. 8:00-10:00am 21/ 2/2016.
Malama Chileshe Energy Economist COMESA Secretariat
PROJECT DELIVERY METHODS
Flexibility options in Energy performance contracts
Training module EPC facilitators A role to play Add date.
The Estonian experience with ex-ante evaluation – set-up and progress
Presentation transcript:

Berliner Energieagentur GmbH WP 2 training session EPC project development models Berlin, Dipl.Ing. Vollrad Kuhn, Berliner Energieagentur GmbH

Berliner Energieagentur GmbH EPC project development models Two different project development models: Single-stage procedure (e.g. Energy Saving Guarantee Contract from the Hesse guidelines, guidelines was elaborated from BE/legal experts for Hesse Environmental Ministry, published 2003) Two-stage procedure (e.g. Success Guarantee Contract from the dena guidelines, published from German Energy Agency dena for the Federal Ministry of Transport, Building and Urban Affairs 2003)

Berliner Energieagentur GmbH EPC project development models Main differences between both models Single-stage model: Bidder as potential contractor has to provide an energy saving guarantee already after performance of the energy rough analysis (including the 1st validation of building data, determination of energy and cost saving potential, concret energy efficiency measures) no separate project planning contract, no separate remunaration of the bidders planning costs for rough and fine analysis 2nd validation of building data / fine analysis is part of the preparation phase of project implementation phase

Berliner Energieagentur GmbH EPC project development models Main differences between both models two-stage model: Bidder as potential contractor has to provide also an energy saving guarantee after performance of the energy rough analysis (including the 1st validation of building data, determination of energy and cost saving potential, calculation of planning costs for fine analysis), but selected Contractor must verify the saving potential and specify his rough analysis results before the project implementation Stage 1: Contractor has obligation for fine analysis (detailed 2nd validation of potential energy and cost savings) on basis of separate project planning contract for fine analysis prior to conclusion of EPC contract (or planning contract is part of the whole EPC contract), he can adjust the building data sheets, saving measures separate remuneration of the contractors planning costs for fine analysis (if there is a confirmation with rough analysis, but decision against start of the stage 2 by client) Stage 2: implementation of energy eficiency measures/performances and success guarantee by the Contractor (if confirmation of rough analysis or seperate decision of the client)

Berliner Energieagentur GmbH EPC project development models Course of the negotiation procedure Phase I:request for submission of a tender and sending of the bidding documents two-stage model: requirements for fine analysis are content of the documents Phase II:negotiation of the tenders (1 – 2 negotiation rounds), negotiation closing Phase III:review, evaluation and award or cancellation of the negotiation procedure After award decision, contract conclusion start of project implementation by the Contractor Two-stage model: Contractor has to start with stage 1 (fine analysis), if the results confirm rough analysis, client can choose from two alternatives Order to start with stage 2, fine analysis costs are content of calculated basic remuneration for the EPC services Decision against implementation of stage 2 (due to fair reasons by the client), remuneration of contractors fine analysis costs by the client

Berliner Energieagentur GmbH Tasks of project development and implementation I Frame establishing  description / communication of the project  Checking the data situation Building selection / definition of targets  Energy costs for electricity, heat etc.  Using data (operating hours, numbers of pupils etc.)  Description of the sites/buildings Integration of decision maker / professional departments approval authorities step 0: step 1: Fixing of Energy cost-baseline System request Project preparation and -development

Berliner Energieagentur GmbH Call for tender  Announcement with giving kind of project development model, award procedure  Call for expression of interest / prequalification  Dispatch of request Rough analysis / laying of offer  Site-visits at the buildings  Validation of data  Determination of saving guarantee (and planning costs fine analysis) Presentation of model contract (single- ore two-stage model) assessment criterias step 2: step 3: Offer with saving guarantee catalogue with measurements, investment costs (planning costs and duration of fine analysis) Tasks of project development and implementation II competition

Berliner Energieagentur GmbH Checking the offer / negotiations  Condensing the competition step by step  Negotiations with max. 3 best bidders  Offer comparison with exactly assessment criterias and with own direction Contract signature  Approval by the authorities  Proof of the economy Benefit amount-analysis integrated technical-economical analysis ecological assessment step 4: step 5: Contract includes rights and responsibilities cooperation principles (stage 1: project planning contract, stage 2: performances and success guarantee) Tasks of project development and implementation III competition

Berliner Energieagentur GmbH Tasks of project development and implementation IV Energy saving-guarantee-contract / Project implementation (single-stage model) Preparation phase  Detailled planning and  realisation of the saving measures inspection  End of construction measurements by Contractor  Inspection by building owner Contractor is responsible for Planning, financing and construction in coordination with the building owner step 6: step 7: Building owner get property of the realised facilities

Berliner Energieagentur GmbH Tasks of project development and implementation IV Energy saving-guarantee-contract / fine analysis (two-stage model) Stage 1: fine analysis  Detailed validation of energy and cost savings  Verification of the rough analysis energy saving prognosis Comparison of the results, final decison of the building owner  Confirmation of rough analysis: order to start with stage 2  Confirmation of rough analysis: decision against start of stage 2 (due to fair reasons, e.g. changes in utilization)  Nonconfirmation: cancellation of project (or other decision by the building owner, if he is responsible for nonconform.) Contractor is responsible for Detailed calculation/estimation of economic saving potential of the planned efficiency measures including the investment costs step 6: step 7: Building owner get the ownership on the results If confirmation and decison against stage 2: remunaration of contractors planning costs

Berliner Energieagentur GmbH Tasks of project development and implementation V Energy saving-guarantee-contract / Project implementation (stage 2 of the two-stage model) Preparation phase  Detailled planning and  realisation of the saving measures (from fine analysis) inspection  End of construction measurements by Contractor  Inspection by building owner Contractor is responsible of Planning, financing and construction in coordination with the building owner step 8: step 9: Building owner get property of the realised facilities/plants

Berliner Energieagentur GmbH Tasks of project development and implementation V / VI Energy saving-guarantee-contract (both models) Main performance phase  Begin of the energy management and -controlling as well as  Implementation of user motivation Expiration of contractual time Contractor guaranteed consumption- and cost decrease operating safety step 8 (10): step 9 (11): Building owner get Responsibilty of operation Full advantage of saving

Berliner Energieagentur GmbH EPC project development models Comparison of advantages and disadvantages General: both models models have advantages and disadvantages two-stage model current opinion of ESCOs is that there are lower risks the model gives more opportunities for approximation regarding the project goals and solution approaches between potential client and bidder the planning costs for fine analysis are covered (remuneration in most cases) Contractor can try to give objective reasons if the results of fine analysis not confirm the rough analysis Single-stage model Bidder has to make an accurate validation of building energy data in the frame of rough analysis, that means higher risks (due to uncertainties for calculation of energy saving measures and saving guarantee at this early stage of project development) most of the bidders take security premiums in their calculations

Berliner Energieagentur GmbH EPC project development models Comparison of advantages and disadvantages (I) Single-stage procedureTwo-stage procedure applicationFor single buildings and building pools, but rather for not too complex buildings rather for complex buildings (e.g. large hospitals), estimation of energy saving potential is more difficult Duration, complexity Shorter, easierLonger, more complex Advanta- ges for the client Client get the promise of guarantees directly with the offer (final guarantees as result of contract negotiations) Client get better and more accurate building energy data and planning data for energy efficiency measures (content of fine analysis) Disadvan- tages for the ESCO Bidder has to make an accurate validation of building energy data in the frame of the rough analysis with high risks (large uncertainties for calculation of energy saving measures, saving guarantee) and without remuneration for his rough analysis costs Longer procedure, the ESCO can get the remuneration later

Berliner Energieagentur GmbH EPC project development models Comparison of advantages and disadvantages (II) Single-stage procedureTwo-stage procedure Advanta- ges for the ESCO Shorter procedure, the ESCO can get the remuneration faster after start of main phase of obligation to perform Lower risks for the ESCO; Contractor has a contractual claim to implement the energy saving measures or to get a remuneration for fine analysis (if there is a confirmation with rough analysis) Disadvan- tages for the client security premiums in the calculations of bidders; After Baseline adjustment in some cases (energy costs determined by the client have been changed) measures to compensate disadvantages to the contractor are necessary Client get the final confir-mation for the guarantees (promised by bidder with offer) not until fine analysis results (if there is a confir- mation with rough analysis), he has to pay for the fine analysis (confirmation of rough analysis, but decision against EPC by the client)

Berliner Energieagentur GmbH EPC project development models Thank you for your attention!