Condenser supply contract report Jose Botelho Direito EN/CV/DC Thermosyphon cooling workshop §5 Thursday, October 20, 2011.

Slides:



Advertisements
Similar presentations
Quiz – An organic liquid enters a in. ID horizontal steel tube, 3.5 ft long, at a rate of 5000 lb/hr. You are given that the specific.
Advertisements

HEAT EXCHANGERS in food process engineering Energy balance methodology used to design industrial equipments 1 FIP-DES Bertrand Broyart, Violaine Athès.
System and Component Efficiency with Refrigerant R410a A. T. Setiawan 1, A. Olsson 2, H. Hager 2 1 Department of Energy Technology, Div. Of Applied Thermodynamics.
Spiral Condensors. Working Principle The Spiral Condensor consists of two sheets stainless steel strips which have been wounded from the centre.
The WA105 17m3 LArCryostat pre-experience M.Ne. Status Tender done for the membrane part, 1 German firm selected A lot of time wasted to renegotiate the.
FSTS Leak Rate Qualification Procedure J. Botelho Direito EN/CV/PJ 29/11/2012 FSTS - Leak Rate Qualification Procedure.
GTK WG Meeting April 5 th 2011 Update on Microchannel Cooling - Paolo Petagna 1/15 PH-DT Update on Microchannel Cooling J. Daguin (CERN PH/DT) A. Mapelli.
M. Battistin – 1 st September 2009 EN/CV/DC 1 M. Battistin (EN/CV/DC) 1 st October 2009 ATLAS cooling Group - Thermosiphon solution for ATLAS ID cooling.
For more information, please contact 19/11/2010 EN/CV/DC Chiller design and purchase by Elena Perez Rodriguez.
Paolo Guglielmini TS / CV / DC08th April 2005 BIDDERS’ CONFERENCE Invitation to Tender 3307 Supply and Installation of water cooling equipment for the.
Pierre Bonneau EN/CV/DC
Tracker Thermal Control System 2015年9月13日星期日 2015年9月13日星期日 2015年9月13日星期日 1 AMS-TTCS Status Report AMS-TIM meeting, CERN, Oct.28 th, 2008 ZH He On behalf.
Outline (1) Heat Exchanger Types (2) Heat Exchanger Analysis Methods
Detector Cooling Project Thermosiphon Project Status Report
CMS CO2 Test Stand Specifications and Installation Status Erik Voirin Fermilab PPD - Process Engineering Group CMS CO2 Cooling Test Stand1.
Heat Exchangers This is session 19 in curriculum manual.
Heat Transfer Equations For “thin walled” tubes, A i = A o.
European Organization for Nuclear Research - Organisation européenne pour la recherche nucléaire 1CERN - 4th November 2011 Experience from Construction.
4/5/2005FLARE Cryogenics, RLSchmitt1 Argon Refrigeration Supply Purity.
Table of Content Introduction of heat exchanger. Design of Coolers.
F-595 Chiller contract report Jose Botelho Direito EN/CV/DC Thermosyphon cooling workshop §5 Thursday, October 20, 2011.
Hydrogen system R&D. R&D programme – general points Hydrogen absorber system incorporates 2 novel aspects Hydrogen storage using a hydride bed Hydrogen.
19 th November 2010EN/CV/DC Thermosiphon project IV review - Overall cost estimation and planning Michele Battistin Elena Perez Rodriguez 19 th November.
CMS FPIX Cooling System Studies Joe Howell, Fermilab for the FPIX Upgrade Mechanical Working Group CMS Upgrade Workshop April 27,
J. Direito - M. Battistin – 28 th May 2010EN/CV/DC J. Direito, M. Battistin (EN/CV/DC) 28 th May 2010 Detector Cooling Project III Thermosiphon Workshop.
M. Battistin – 1 st September 2009 EN/CV/DC 1 M. Battistin (EN/CV/DC) 1 st September 2009 ATLAS Working Group Thermo-siphon review - Low temperature condensation.
Equipment Design Designed by Eman A. Khajah. Outline Design of Heater. Design of Stripper.
Full Scale Thermosyphon Design Parameters and Technical Description Jose Botelho Direito EN/CV/DC 19 November, th Thermosyphon Workshop.
Cooling plant upgrade Jose Botelho Direito, Michele Battistin, Stephane Berry, Sebastien Roussee 2 nd SPD Cooling Workshop 30/11/201112nd SPD.
Heat Transfer Equations For “thin walled” tubes, A i = A o.
Thermosiphon project management and quality assurance EN/CV/DC Presentation done by Elena Perez Rodriguez For further information contact
March 19, 2013W. Bertl, PSI Status of BPIX Cooling Activities W. Bertl, PSI.
Michele Battistin Elena Perez Rodriguez 10 November 2010
1 Status of PT Cryocooler for Final Calorimeter KEK, ICEPP Tom HARUYAMA / Satoshi MIHARA MEG Pre-Meeting 1. Heat load and PT cryoooler 2.
M. Battistin, J. Botelho – 20 October 2011EN/CV/DC Detector Cooling Project V Thermosiphon Workshop - Cost and Planning Michele Battistin Jose Botelho.
For more information, please contact 14/12/2010 EN/CV/DC Technical specification IT-3684 by Elena Perez Rodriguez.
A.Henriques (JCOV meeting 31/5/2001) ATLAS Calorimeter cooling project Goal: u Definition of a common frame work for the cooling of the ATLAS calorimeter.
Table of Content Introduction of heat exchanger. Design of Coolers. Introduction of fixed bed reactors. Design of reactors.
Refrigeration and Cryogenics Maciej Chorowski Faculty of Mechanical and Power Engineering.
Thermosiphon Project for ATLAS ID C 3 F 8 Evaporative Cooling - Status Report ATLAS ID Week CERN – Geneva October 28 th, 2013 M. Battistin & all TS team.
ID week 27 th of April 15 C3F8 cooling- Compressors & C3F8 status O. Crespo-Lopez EN/CV.
Aachen Status Report: CO 2 Cooling for the CMS Tracker at SLHC Lutz Feld, Waclaw Karpinski, Jennifer Merz and Michael Wlochal RWTH Aachen University, 1.
Exercises for Q1. Insulated copper tube A thin walled 10 mm copper tube is used to transport a low-temperature refrigerant with a temperature that is.
EXTRACTION OF HIGH VOLUME CRYOGENIC HEAT LOAD
110 th November 2010EN/CV/DC Detector Cooling Project - advancement status of Work Package N3 Thermosiphon project Michele Battistin 18 May 2011.
M. Battistin –6 th July 2009 EN/CV/DC 1 M. Battistin (EN/CV/DC) 6 th July 2009 DCP WP3 First thermo-siphon workshop - Low temperature condensation.
7 February 2012 Annekathrin Frankenberger (HEPHY Vienna) Open CO 2 Cooling System at the beam test Belle II SVD-PXD Meeting.
Date of download: 6/23/2016 Copyright © ASME. All rights reserved. From: Heat Transfer and Pressure Drop Analysis of Chilled Water and Ice Slurry in a.
V Thermo-siphon Workshop Test protocol Jan Godlewski PH/DT-PO On behalf of thermo-siphon working group
For more information, please contact 24/11/2010 EN/CV/DC Chiller design and purchase by Elena Perez Rodriguez.
KIT – University of the State of Baden-Wuerttemberg and National Research Center of the Helmholtz Association Institut für Experimentelle Kernphysik
Heat Exchangers Jorge Seda #84012 José Luis García #69260 Billy Gerena #73656 Robert De Aza #66880 Prof. Eduardo Cabrera ME
Demineralised water cooling system
For the CMS Pixel detector
Date of download: 10/3/2017 Copyright © ASME. All rights reserved.
Design of the thermosiphon Test Facilities 2nd Thermosiphon Workshop
Heat Exchangers and Condensers
Closed loop cooling system Plant closed loop cooling
Dana M. Arenius Jefferson Laboratory Cryogenics Dept Head
SPS cryogenic proximity equipment and SM18 validation
Date of download: 11/8/2017 Copyright © ASME. All rights reserved.
Aachen Status Report: CO2 Cooling for the CMS Tracker at SLHC
WHAT IS HX……??? Heat exchangers are equipment that transfer
Low temperature chiller Market Survey
Pixel CO2 Cooling Status
Process Equipment Design and Heuristics – Heat Exchangers
ESS elliptical cryomodule
Steam traps Applications and Recommendations
Tests of Endcap capillary & Heat exchangers at CERN
For the CMS Pixel detector
Presentation transcript:

Condenser supply contract report Jose Botelho Direito EN/CV/DC Thermosyphon cooling workshop §5 Thursday, October 20, 2011

Outline Technical Requirements Request for Quotation Design from D.A.T.E. Construction Schedule 20/10/2011Thermosyphon cooling workshop §52

Technical Requirements Thermal Requirements: – Total Condenser cooling power: 170kW De-superheating: 28.7 kW Condensing: kW Sub-cooling: 5.5 kW DO-26673/EN-CV – EMDS document number /10/2011Thermosyphon cooling workshop §53

Technical Requirements Stainless Steel Shell and Cupronickel or SSt cooling tubes FOAMGLAS Insulation Storage capacity of 2.5m3 Pressure: PN25 Design temperature from -70°C to 63°C Leak tightness of mbar.lt/s Standards: – Pressure Equipment Directive 97/23 (PED) – Leak tightness: BS EN13184:2001 – Cleaning: ASTM A380 – Earthquake loading: EUROCODE 8 20/10/2011Thermosyphon cooling workshop §54

Request for Quotation Companies contacted (11x): – AEL (de); KLIMAL (de); ALFA LAVAL (se); APPARETEBAU-CRIMMITSCHAU (de); ARSOPI (pt); BOWMAN (uk); D.A.T.E. (fr); Novoa Equipment Limited (uk); Onda (it); SWEP (se); GEA (de). Offers received (3x): – D.A.T.E. – ARSOPI – GEA DO-26673/EN-CV – EMDS document number /10/2011Thermosyphon cooling workshop §55

Design proposal from D.A.T.E. 20/10/2011Thermosyphon cooling workshop §56 DESUPERHEATING and CONDENSATION ZONESUBCOOLING ZONE HEAT TRANSFER COEFFICIENT 299,65 W.m. -2 °C ,8 W.m. -2 °C -1 HEAT TRANSFERT SURFACE 86,85 m 2 9,07 m 2 PRESSURE DROP 6 mbar10 mbar NUMBER OF TUBES 240 tubes28 tubes Thermosyphon C3F8 Liquid outlet Thermosyphon C3F8 Vapour inlet Brine Condenser IN Brine Condenser OUT Brine Sub-cooler IN Brine Sub-cooler OUT De-superheating & Condensing tubes (240x) Sub-cooling tubes (28x)

Construction Schedule Condenser Construction Schedule – October 2011: Contract start – November 2011: Detailed design – January 2012 : Purchasing of material – March 2012: Condenser construction – April 2012: Final pressure tests – April 2012: Insulation of the condenser – April 2012: Delivery at CERN 20/10/2011Thermosyphon cooling workshop §57

Any questions? 20/10/2011Thermosyphon cooling workshop §58