Blondel Compliance. Update to IMO Wholesale Revenue Metering Standard V2.0 Section 4.3.3 - Considerations for non-Blondel Meter Installations a. 3 CT’s.

Slides:



Advertisements
Similar presentations
Bonding and Grounding What? Why? How?
Advertisements

Questions about AVR & PSS
Chapter 4 Transformer Connections
Wiring of the Electric Motor By Irri-Gator Products (Pty) Ltd.
The MMUTCD New Compliance Dates Sign Retroreflectivity
Presentation : IMS – Tech Managers ConferenceAuthor : IMS StaffCreation date : 08 March 2012Classification : D3Conservation :Page : ‹#› 10 – Three Phase.
Revenue Metering. 2 The Settlements Process Transfer Funds $ $ Invoice Participants Reconcile Markets Gather and Process Metering Data.
 E4 Electrical Installation #1 Power Distribution.
Chapter 24 Three-Phase Systems.
1 PJH Charlotte, NC March 18, 2008 Liquid Dielectric Test Tables Task Force (C ) Rev 16 Charlotte, NC March 18, 2008.
Stray Current Investigations A Method of Troubleshooting Stray Current on Underground Residential Distribution (URD) Loops Stacey Mighty Malcolm Distribution.
Presentation on ELECTRICITY DISTRIBUTION LOSSES & CONCEPT OF AGGREGATE TECHNICAL AND COMMERCIAL (AT&C) LOSS R.V. Shahi Former Power Secretary, Govt.
1 1 Substation Asset Strategy Kevin Dasso, Senior Director Engineering and Operations IEEE/PES Annual Substations Committee Meeting April 7, 2008.
Chapter 3 Wireless Field Devices. Wireless Devices - Process Industry  Most wireless field devices designed for use in the process industry are based.
in the Age of the Photovoltaic
POLYPHASE CIRCUITS LEARNING GOALS Three Phase Circuits Advantages of polyphase circuits Three Phase Connections Basic configurations for three phase circuits.
Faculty of Electrical Engineering Universiti Teknologi Malaysia
Unit 29 Three-Phase Transformers. Objectives: Discuss the construction of three-phase transformers. Discuss the formation of a three-phase transformer.
Make the most of your energy December 2008 PowerLogic Enercept Submetering ….when space is at a premium PowerLogic® Enercept Meter.
Line and Phase Voltages for a Wye Circuit.
Coal Mine Connections Lessons from Experience. Why are we talking about Coal mine connections Because we had a situation where the customer wanted a service.
Electrical Power Distribution in America % Coal 20.4% Nuclear 20.3% Natural Gas 6% Hydro Electric 3.4% Other
1 Introduction to Power Systems Expensive! Influential!Intrusive! Source: Riadh W. Y. Habash, Electromagnetic Fields and Radiation, Marcel Dekker, New.
HV Field Testing and CCVT Re-verification December 2013.
We ground the neutral of our Distribution capacitor banks- Why?
October 28, 2014 Update to RMS 1. * Reviewed and Discussed: * ERCOT Protocols and Retail Market Guide Requirements * TDSPs’ Data Processes for IDR vs.
ELG4125 Transmission and Distribution Systems
Grounds on Cap Banks. Why do we ground some cap banks and not others? We ground 12kV Cap We ground 12kV Cap We do not ground 23 and 25kV banks We do not.
1 Air Conditioning Three Phase Power. 2 Most common in commercial and industrial buildings Three hot legs, one ground, and one neutral L1, L2, L3, N,
Review 1. Review of Phasors Goal of phasor analysis is to simplify the analysis of constant frequency ac systems: v(t) = V max cos(  t +  v ), i(t)
EE1 PEEE Refresher Class Power Part 2 notes by T. Ernst EE1 – Power Part 2 NotesFall 2011, Page 1.
1 60 Hertz Over Voltages For Arrester Applications For Arrester Applications.
Hour Ahead Dispatchable Loads Applicable Updates to Procedures Presentation to the Market Operations Standing Committee April 23, 2003
Lecture-5. Md.Kausher ahmed Electrical department.
Electrical Power Distribution. Forms of Energy All forms of energy fall under two categories POTENTIAL Stored energy or energy of position (gravitational)
Electrical Power Distribution. Forms of Energy All forms of energy fall under two categories POTENTIAL Stored energy or energy of position (gravitational)
Lecture 11Electro Mechanical System1 Delta-Delta Connection  Three single-phase transformers connected delta-delta  H 1 terminal of each transformer.
January 14, 2016 MWG Meeting. Topics for discussion: 1.) ERCOT Anti-Trust Admonition (D. Sumbera)9:30 – 9:35 2.) Attendance roll-call and introduction.
Measurement Error Correction (MEC)  Voltage transformers (VTs) and current transformers (CTs) that do not meet the 0.3 Accuracy Class of IEEE Std C57.13.
IMO Audit Findings - IT’s. As per Market Rules, IT’s must be Measurement Canada approved or operating under Measurement Canada Temporary Permit - which.
Transformer Current & Voltage Practice
Power Systems J. Sandberg July 2006 RHIC Retreat 2006.
DISTRIBUTED GENERATION ISSUES Technical Issues Non-Technical Issues.
Field Problems with Instrument Transformer Installations
Wholesale Revenue Metering Standard - Hardware November 2003.
Advanced Meter School August 18-20, 2015 INSTRUMENT TRANSFORMER SIZING 2015 David L. Johnson.
Lesson 7: Power and Energy Measurement
E4 Electrical Installation
Simple Resistive Circuites
Interconnect Protection of Dispersed Generators
Smitty’s Two Minute Drills
Three-Phase Power.
E4 Electrical Installation
CIRCUITS by Ulaby & Maharbiz
Design of Electric Power Systems and Utilities
Distributed Generation (DG) Modeling Criteria
AC Power.
Calculations: Transformers and Service Conductor Calculations
12/6/2018.
12/6/2018.
Exercise 10 Power systems.
EET 323 – Electrical System Design Lecture 9: Grounding
Smitty’s Two Minute Drill Grounding and Bonding
SMART Program Specific Metering Wiring Diagrams May 2019
2020 National Electric Code
Electrical components and systems
IMO Audit Findings - IT’s
POLYPHASE CIRCUITS LEARNING GOALS Three Phase Circuits
Presentation transcript:

Blondel Compliance

Update to IMO Wholesale Revenue Metering Standard V2.0 Section Considerations for non-Blondel Meter Installations a. 3 CT’s and 2 PT’s (phase-N) using 2.5 element meter b. 3 CT’s (delta connected) and 2 PT’s (phase-N) using 2 element meter c. 2 CT’s and 3 PT’s (69V phase-N) using a 2 element meter d. 2 CT’s and 2 PT’s using 2 element meter where Neutral is not available Section Registration of non-Blondel Meter Installations –At seal expiry, MI registered under 4.3.3b must be upgraded to 4.3.3a with a conforming 2.5 element Main meter that calculates the missing voltage and records the missing voltage (V2h) in channel 6 (ION Meter)

Blondel Compliance Section Compliance with Measurement Canada Rulings Existing installations shall comply with any future Measurement Canada rulings on two and one- half element metering (or two-element metering, using three delta connected current transformers and two voltage transformers connected phase to ground). As per Measurement Canada Bulletin E-24E (rev.1) dated , “5.1 Effective April 1, 2003, all new and all reconstruction of existing 3- phase 4-wire wye configured metering installations shall use metering that is compliant to Blondel’s theorem such as 3-element metering. An example of a reconstructed metering installation may include service upgrades and, or instrument transformer replacement. Reconstruction of existing metering installation, sites that do not have sufficient physical space to accommodate the additional voltage transformer will not be required to meet 5.1 above”

Blondel Compliance

In some cases, the Metering requirements may differ depending on the location of the Meter Installation Within a facility (TS) –Grounded system requires 3 element metering. PT’s connected phase- neutral for 4 distribution system or phase-ground for 3 wire distribution system. –Ungrounded system requires 2 element metering* Within a distribution system (outside of TS) –4-Wire distribution requires 3 element metering kV Wye –3-Wire distribution requires 2 element metering - 46 kV (Wye or Delta)

Blondel Compliance What happens when meter is not located at the defined Meter Point (feeder meter located outside of the TS)? –Meter Installation is 2 element but declared non-Blondel –Non-Blondel MEC’s apply Do we need to simplify the metering requirements for NEW meter installations? –3 element meter installation irregardless of the # of wires (3 or 4) or meter location. –Research industry practices and develop standard. IMO and NRC to perform study on non-Blondel installations (2 element metering on a grounded system).