CLIC Permanent Magnet Quadrupole Engineering Development Norbert Collomb, STFC Daresbury Laboratory 1N. Collomb 2/07/2010.

Slides:



Advertisements
Similar presentations
CLIC two-beam module integration issues 4 th CLIC Advisory Committee (CLIC-ACE), May 26-28, 2009 CLIC two-beam module integration issues G. Riddone on.
Advertisements

BARTOSZEK ENGINEERING 1 The Design of the Booster Collimators Larry Bartoszek BARTOSZEK ENGINEERING 3/10/03.
James Richmond09/09/20101 CLIC Permanent Magnet Quadrupole - Proposed Mechanism Prepared by James Richmond Presented by Norbert Collomb STFC Daresbury.
MICE Radiation Shield Design review for the proposed ‘Direct Drive’ MICE Spectrometer Radiation Shield 17/11/2011Norbert Collomb.
, CLIC Test Module Meeting Status of the DB Quad adjustable support design Mateusz Sosin CLIC Module WG Meeting, 22-May-2013.
Alignment of DB and MB quadrupoles Hélène MAINAUD DURAND 17/11/2011 With a lot of input from Sylvain GRIFFET.
Fiber Repositioning System NanoDrop December 11, 2006 Chris Czech Charles Dielmann Mark Howe Dana Kimpton Christopher Sherman.
Progress on the MICE 201 MHz Cavity Design Steve Virostek Lawrence Berkeley National Lab RF Working Group Fermilab August 22, 2007  automatic.
1 RF-Structures Mock-Up FEA Assembly Tooling V. Soldatov, F. Rossi, R. Raatikainen
Rolling element bearings A. Lozzi 09
H. MAINAUD DURAND on behalf of the CLIC active pre-alignement team with 3D views and data from Hubert Gerwig, Richard Rosing and Juha Kemppinen Pre-alignment.
Industrial Challenges of Compact Magnet Production N. Collomb 27/11/ Norbert Collomb, STFC J. Clarke, B. Shepherd, N. Marks, STFC-ASTeC M. Modena,
MICE Radiation Shield Installation 1 18 th October2012 Summary of initial test N. Collomb.
Status of vacuum & interconnections of the CLIC main linac modules C. Garion TE/VSC TBMWG, 9 th November 2009.
INTEGRATION OF RF STRUCTURES IN THE TWO-BEAM MODULE DESIGN G. Riddone, CERN, Geneva, Switzerland A. Samoshkin, D. Gudkov, JINR, Dubna, Russia Abstract.
1 Progress On The Design And Manufacture Of The New Stator Geoff Barber Imperial College.
Friedrich Lackner (TS-SU) CLIC08 Workshop. CLIC Main Beam Quadrupole Magnet The Alignment Concept Expected Properties of a the Support Structure Foreseen.
FOOTINGS. FOOTINGS Introduction Footings are structural elements that transmit column or wall loads to the underlying soil below the structure. Footings.
MARS 2 Design Review-Optomechanical Review 07 Nov 2002 GLW1 MARS 2 Mechanical Design Review.
Gek 16/6/041 ITRP Comments on Question 19 GEK 9/06/04 19) For the X-band (warm) technology, detail the status of the tests of the full rf delivery system.
CLIC Permanent Magnet Quadrupole Engineering Development update Norbert Collomb, STFC Daresbury Laboratory 1N. Collomb 13/09/2012.
Tomelleri S.r.l. ® Copyright 2007 © ASTRONOMY AND RESEARCH September 19th 2008 VST Meeting1.
F.E.T.S. RFQ Mechanical Design by Peter Savage 7 th January 2010.
STATUS of the final PACMAN bench integration PACMAN meeting 11/06/2015 Hélène Mainaud Durand.
Permanent Magnet Quadrupoles for the CLIC Drive Beam Jim Clarke, Norbert Collomb, Neil Marks, James Richmond, and Ben Shepherd STFC Daresbury Laboratory,
ASTeC Report for CLIC-UK Jim Clarke on behalf of all ASTeC & Technology Department staff contributing to CLIC-UK STFC Daresbury Laboratory, UK CERN-UK.
Cavity support scheme options Thomas Jones 25/06/15 to 06/07/15 1.
1 Status of the CLIC two-beam module program A. Samochkine, G. Riddone Acknowledgements to the Module WG members 4 February 2014 CLIC Workshop 2014 (3-7.
CLIC Permanent Magnet Quadrupole update 1 st December 2010 Mechanical Engineering status N. Collomb1.
DBQ support – motorization and performance upgrade Mateusz Sosin EN/MEF-SU.
Status of North Area Target (TCC2) & prospects EATM 28/07/2015D. Grenier1 Targets (T2, T4, T6 and T10) replaced in 2014 during LS1 (+ 4 spares) Previous.
ABSTRACT The Compact Linear Collider (CLIC) is currently under development at CERN as a potential multi-TeV e + e – collider. The manufacturing and assembly.
Magnet Design & Construction for EMMA
CLIC Permanent Magnet Quadrupole Engineering Development of second family member Norbert Collomb, STFC Daresbury Laboratory 1N. Collomb 07/11/2012.
CLIC08 workshop CLIC module layout and main requirements G. Riddone, on behalf of the CMWG Home page of the TBM WG:
CLIC Module meeting, 22/08/2011 N. Chritin (EN/MME) Cradles design for CLIC module supporting system (EDMS )  General principle  Main inputs an.
Copyright  2012 McGraw-Hill Australia Pty Ltd PPTs t/a Engineering Drawing 8e by Boundy 2-1 Chapter Two Dimensioning Drawings: Symbols, Methods, Common.
CLIC Workshop th -17 th October 2008 Thomas Zickler AT/MCS/MNC 1 CLIC Main Linac Quadrupoles Preliminary design of a quadrupole for the stabilization.
cern.ch 1 A. Samoshkin 28-Feb-2011 Progress on CDR module design.
cern.ch International Workshop on Linear Colliders 2010 CLIC TWO-BEAM MODULE DESIGN & INTEGRATION 21-Oct-2010 WG 8 «TECHNICAL SYSTEMS»
Global Design Effort - CFS DESY Accelerator Design and Integration Meeting 1 ACCELERATOR INTEGRATION AND DESIGN MEETING CONVENTIONAL FACILITIES.
CLIC Stabilisation Day’08 18 th March 2008 Thomas Zickler AT/MCS/MNC/tz 1 CLIC Quadrupoles Th. Zickler CERN.
Drive Beam Quadrupoles Jim Clarke, Norbert Collomb, Ben Shepherd, Graham Stokes STFC Daresbury Laboratory, UK Antonio Bartalesi, Michele Modena, and Mike.
cern.ch CLIC MEETING (17-Dec-2010) CLIC TWO-BEAM MODULE LAYOUT (short introduction) BE / RF 1.
Artwork: S. Kimball. The CLIC Drive Beam The drive beam decelerates from 2.4 GeV to 0.24 GeV transferring energy to the main beam As the electrons decelerate,
Upgrade PO M. Tyndel, MIWG Review plans p1 Nov 1 st, CERN Module integration Review – Decision process  Information will be gathered for each concept.
CLIC Permanent Magnet Quadrupole Engineering Development update Norbert Collomb, STFC Daresbury Laboratory 1N. Collomb 03/10/2011.
Jeff T. Collins Undulator Support/Mover System 20 October 2005 LCLSLCLSLCLSLCLS LCLS Undulator Support/Mover System.
CLIC Permanent Magnet Quadrupole update 27 th January 2011 Mechanical Engineering status update N. Collomb1.
Practical aspects of small aperture quadrupoles Dr Ben Leigh Tesla Engineering Ltd.
SPS movable table Joanna Swieszek, Kurt Artoos (EN-MME) 14/04/2016.
P15342 Linear RF Measurement System Kate Gunderson Matt Chauncey Will Tourtillotte.
Page 1 GSI, Hydraulic Actuators for PANDA Target Spectrometer Jost Lühning, GSI Darmstadt Functional Specifications for moving the TS: Two synchronous.
CLIC Permanent Magnet Dipole Feasibility Proposal
Two-beam module layout
CNC FEED DRIVES.
CLIC Parameter Working Group Two Beam Module Design
Update on the DB Girders FE Analyses
Telescope - Mechanical
Page Headline CBETA Splitter.
TEST MODULE WG Cradles for CLIC module supporting system
Alignment methods developed for the validation of the thermal and mechanical behavior of the Two Beam Test Modules for the CLIC project Hélène MAINAUD.
Thermal-Structural Finite Element Analysis of CLIC module T0#2
Thermal-Structural Finite Element Analysis of CLIC module T0#2
Alex Bainbridge1, Ben shepherd1, Jim Clarke1,
CLIC Workshop 2016, CERN 20th January 2016
Pierre-Alexandre Thonet
10th Feb 2017, CLIC Implementation Meeting
PERMANENT MAGNET QUADRUPOLE FOR THE LINAC 4 CCDTL
Permanent Magnet Quadrupoles and Dipoles for CLIC
Presentation transcript:

CLIC Permanent Magnet Quadrupole Engineering Development Norbert Collomb, STFC Daresbury Laboratory 1N. Collomb 2/07/2010

CLIC Permanent Magnet Quadrupole Revisit points from last meeting Engineering specification Principle evaluation Schematics for 3 options Model 5.53 for smaller envelope Discussion with manufacturers and suppliers Automation for high volume production Next steps –Detail design of one or two options –Finite Element Analysis to predict performance compliance –Programme Summary N. Collomb 2/07/2010 2

Previous meeting points Movement principles – Linear Motion Ball screw system Option 5.19 to be developed further Confirmation of envelope (supply of CAD info for module to corroborate constraints) Revisit existing design according to above point Manufacturer discussion –Motor –Gearbox –Backlash coupling –Ball Screw and Nut –PM material and manufacture Specifications for components above Integration of components into CAD model and CAD QA Next steps N. Collomb3 2/07/2010

Option 5.19 previous Schematic N. Collomb4 60mm position (approx. 30T/m) 60mm from full gradient position 2/07/2010 Linear Actuator or Screw-jack “Faceplate” to hold yokes in position Permanent Magnet (black) Linear Friction strips “Support pillars”

Option 5.19 previous summary Can be made to fit into specified envelope (just). Then ‘Current’ design indicates height as 526mm and width as 410mm Mechanism design is being revised as we speak (done, need validation) First indications: –Requires independent halves (we assume this is still the case) –Two linear actuators or jack screws essential (jack screws not sufficiently accurate and force design to exceed envelope) –Requires linear encoder to provide feedback for synchronisation (can be eliminated using Stepper motors) –PM enclosure contains bearing system to eliminate 5 D.O.F. Still applicable The solution currently under investigation needs careful design The design must definitely be validated by Finite Element Analysis and prototyping Despite being mechanically more challenging than solutions 5.21 and 5.20, the magnetic characteristics favour this solution. Decided to pursue this option further. N. Collomb 2/07/2010 5

N. Collomb 2/07/ MB QUAD ACCELER. STRUCTURE (BRAZED DISKS) RF DISTRIBUTION GIRDER CRADLE VACUUM MANIFOLDS ALIGNMENT SYSTEM BEAM INSTRUMENTATION DB QUAD COOLING CIRCUITS RF LOAD PETS ( OCTANTS, MINI-TANK ) RF SPLITTER W/ CHOKE- MODE FLANGE Drive beam 100 A PETS ON-OFF MECHANISM Main beam ~1 A WAKE- FIELD MONITOR Module CAD Info image

N. Collomb 2/07/ Option 5.19 current Schematic Gearbox (Planetary) Stepper motor Backlash coupling Ball Screw Ball Screw Nut (preloaded) Faceplate with Linear Cross Roller bearing preload features Linear Cross Roller Bearing system Height: 466 mm Width: 340 mm Length: 270mm

N. Collomb 2/07/ Option 5.19 current Schematic Magnet Aperture Ø28 mm Aluminium Support Pillars fastened to yoke Face-plate fastening holes Diamond dowelSplit line, top - bottom Permanent Magnet moving up and down to adjust field ‘Cantilever’ arm bonded to PM 75 mm max. 25 mm

Engineering Specification Sufficient info to discuss specification with manufacturer Static Force of 3.2 kN to overcome Stroke of 75 mm Accuracy from CERN document and Ben’s gradient graph equates to 15 μm repeatability, including ‘creep’ and ‘backlash’. Motor should operate on 12/24V DC preferably and be of the Stepper type using 400 true steps per revolution, mounting with flange or collar. Gearbox should be low or preferably no backlash type (Planetary preferred) and the ratio in conjunction with the motor accuracy and lead screw pitch has been worked out to be 30:1 The Ball screw and Nut need to be pre-loaded and the accuracy to C1 over the stroke length. The forces in the system indicate a diameter of 16 mm with a 5 mm lead (pitch). Validation required via FEA. Envelope constraints for drive system: length 255, width 135 and depth 55 mm Materials of low magnetic permeability are to be used where possible and plastics need to be radiation resistant if absolutely needed. Stepper motors use permanent magnets and we need to evaluate their influence on the field of the Quad and function of the motor. N. Collomb 29/04/2010 9

Principle Evaluation Version 5.19 schematic fits inside envelope Envelope: 391 (W) x 471 (H) x 270 (L) mm Movement range covers 120 – 7% requirement, provided we use a family of three, i.e. 120 – 49%, 93 – 28% and 66% - 7% Accuracy can be achieved (pending feedback from manufacturer) Repeatability depends on home position, must provide map of position vs field Synchronisation not as much an issue as initially thought N. Collomb 29/04/

Schematic for 3 options Family of three range, –120 – 49%, –93 – 28% and –66% - 7% Achievable by reduction in length Components remain the same (provisional) Height and width remain the same (provisional) Accuracy and repeatability remain the same (assumed) Synchronisation equally (in)sensitive across range Map required with range adjusted accordingly. N. Collomb 29/04/

5.53 Model for smaller envelope N. Collomb 29/04/ Height: 390 mm Width: 340 mm Length: 270mm Ferromagnetic Steel enclosure with 20mm thickness walls

5.53 Model for smaller envelope N. Collomb 29/04/ Least gradient position 45mm Maximum gradient position Permanent Magnet moves as per Option 5.19

Manufacturer and supplier discussions N. Collomb 2/07/ Magnet manufacturer discussion’s have continued and we are expecting information on queries very soon. Especially on the latest development for the PM Quadrupole.

N. Collomb 29/04/ Manufacturer and supplier discussions Linear motion system: As per specification in previous slide, we had invited a manufacturer to supply the following components: 1.Motor (advice was provided on Stepper and Servo motor) 2.Gearbox (manufacturer recommended Planetary system based on requirements) 3.Backlash coupling (not usually supplied by manufacturer, but may be build in) 4.Ball Screw and Nut (discussed accuracy and repeatability – will provide advice from HQ engineers) 5.Brake (it is envisaged to incorporate this in the motor/gearbox) The manufacturer has been requested to provide a cost effective solution and look at ‘off-the-shelf solutions first. The brake has a double function in terms of ‘creep’ and fail safety. Information has been requested from their head office engineers. Should we pursue solution 5.19 (5.53) then the effects of the PM material in the Quad on the Stepper motor (and vice versa) need to be investigated further. Radiation is an unknown for the manufacturer, however they are investigating this in general terms at their head office.

Automation for high volume production (unchanged) Draw up manufacturing and assembly process flow chart Identify areas that can be automated Design of jigs and fixtures to assemble components Design Quality Control process and required hardware for testing Establish safe working procedures N. Collomb 2/07/

Next steps: Design Complete system schematic for solution 5.19 (complete) (Re-)Evaluate magnet design and decide on one or two solutions (complete) Develop the solution(s) in detail Carry out Finite Element Analysis to evaluate and validate component and assembly stresses remain within acceptable limits Complete detail design and carry out cost analysis –A summer student has commenced work on Expected design duration: 4 months (includes new mechanism design for new quad option) N. Collomb 2/07/

Next steps: Manufacture Request quotes from manufacturers Discuss process if required and associated tolerances (in progress) Agree price and lead times Discuss possibility of supplying part assemblies (in progress) Expected manufacturing duration: 6 months N. Collomb 2/07/

Next steps: Assembly Assemble manufactured components Analyse assembly process and identify automation processes Write assembly procedure Identify jigs and fixtures required for assembly process Expected assembly duration: 2 months N. Collomb 2/07/

Next steps: Testing Identify required instruments and measurement equipment (manual and automated) Measure magnetic characteristics Measure mechanical tolerances Specify ‘Go and No-Go’ criteria Mark up any deviation for installation purposes Rework or adjust if required Create map of position versus field strength Expected testing duration: 3 months Prototype completion expected within: 15 months N. Collomb 2/07/

CLIC PM Quadrupole summary Solutions exist – need to decide on one to develop in more detail James Richmond (Summer student) may help in reducing the design time. He is competent in CAD and with guidance can provide design suggestions/solutions. Part of his appointment is the task of carrying out the Finite Element Analysis of components and assemblies to validate the design. Solution(s) need to be validated through analysis and ultimately prototype(s) Time scale: –Design: 4 months (unchanged, pending version decision) –Manufacture: 6 months –Assembly: 2 months –Testing: 3 months –Total: 15 months Procedures and processes (automation) need to be established for mass production Cost analysis for manufacture, assembly and testing as primary contributor needs to be carried out Commissioning, Installation, Maintenance and operation costs can be estimated as secondary overall contributor N. Collomb 2/07/