California Public Utilities Commission Regulation and Natural Gas Infrastructure Richard Myers CPUC Energy Division May 14, 2009.

Slides:



Advertisements
Similar presentations
Procuring Our Way to Compliance IEP 27 th Annual Meeting September 23, 2008 Fong Wan, PG&E.
Advertisements

May 2013 Tehachapi Renewable Transmission Project (TRTP)
ACC Workshop Regarding Notice of Inquiry on Natural Gas Infrastructure September 10, 2003.
California Energy Commission Retail Electric Rate Scenarios: Key Drivers and Structure 2015 Integrated Energy Policy Report California Energy Commission.
CPUC Procurement Policies Robert L. Strauss California Public Utilities Commission Energy Division - Procurement Section.
David Howarth MRW & Associates Oakland, California 1 JUST THE FACTS: RESOURCE PLANNING AND PROCUREMENT INDEPENDENT ENERGY PRODUCERS ANNUAL.
Public Interest Energy Research –Natural Gas Program Status Presentation to Air Emissions Advisory Committee May 12, 2005 Philip Misemer California Energy.
North American Natural Gas Infrastructure Needs Donald F. Santa, Jr. President Interstate Natural Gas Association of America The Independent Petroleum.
KERN RIVER GAS TRANSMISSION COMPANY Wyoming Pipeline Authority Casper, Wyoming August 21, 2007 John Dushinske Vice President of Marketing & Regulatory.
1 CARB Public Consultation Meeting Compressed Natural Gas Specifications August 3, 2005 WSPA/CIPA Presentation Western States Petroleum Association (WSPA)
Natural Gas In California LNG Imports UCSB Bren School Corporate Partners Summit May 14, 2004.
How the Implementation of the Network Code Does Help Infrastructure Users Vasile FLOREA Director of Commercial Balancing SNTGN TRANSGAZ SA Medias.
DRA Advocacy Joe Como, Acting Director. 2 DRA Facts The Voice of Consumers, Making a Difference! 3  History: CPUC created DRA (formerly known as the.
R Southwest Gas Corporation February 16, 2001 Southwest Gas Corporation Update on Factors Affecting Gas Prices n Storage u Storage levels continue below.
NOI on Arizona Natural Gas Infrastructure Strawman Proposal and Workshop Comments of Sempra Energy Global Enterprises September 25, 2003.
IMPERIAL VALLEY CONFERENCE July 21, SOLICITATION RENEWABLES PORTFOLIO STANDARD.
NATURAL GAS MARKET OUTLOOK Natural Gas Outlook Import share of natural gas supply declines as domestic supply grows Shale gas has been the primary.
® Investor Meetings June 7-8, 2010 PG&E Corporation.
The Market Outlook for Natural Gas: The Wyoming Natural Gas Pipeline Authority’s Perspective Wyoming Geological Association Conference Prepared: July 26,
Energy Production and Use in California Source: California Energy Commission
Wyoming Pipeline Authority August 24, 2004 Mark C. MoenchJohn R. Smith Vice President and General Counsel Director, Regulatory and Governmental Affairs.
Public Transit Department Bus and Fuel Procurement Strategy AzTA/ADOT Transit Conference April 2013.
E.ON on the Romanian Energy Market ZF Power Summit Bucharest, February 27, 2013 Frank Hajdinjak CEO E.ON România.
Montana Ambassadors Helena, Montana February 25, 2011.
Energy and Economy Transition California’s energy system to a highly efficient, renewables-based system and electrify transportation.
The Value of Electric Transmission NASUCA Mid-Year Meeting June 25, 2012.
Laura Doll Deputy Executive Director, CPUC October 18, 2006 Platt’s CA Power Market Forum C ALIFORNIA P UBLIC U TILITIES C OMMISSION Fulfilling Resource.
The Evolving Roles and Responsibilities of Gas Utilities In Today’s Markets Presented by: Hank Linginfelter Executive Vice President, Utility Operations.
Energy Action Plan “Report Card” and the AB32 “Umbrella” CFEE ROUNDTABLE CONFERENCE ON ENERGY Julie Fitch California Public Utilities Commission Director.
Citizens’ Academy Kathy Viehe GRU Interim General Manager November 12, 2014.
Renewables Portfolio Standard: Progress and Perspectives Aaron J. Johnson Director, Renewable Energy Policy & Strategy February 1, 2011.
Energy Action Plan Natural Gas Update California Public Utilities Commission California Energy Commission Randy Roesser December 8,
National Petroleum Council Study Balancing Natural Gas Policy: Fueling the Demands of a Growing Economy September 2003.
Winter Past, Winter Future Role of LNG in New England Prepared for: New Hampshire Energy Summit Concord, NH October 5, Joe Dalton Director, Government.
National Governors’ Association April 5, 2001 James Mahoney PG&E National Energy Group and any other company referenced herein which uses the PG&E name.
1 Combined Heat and Power (CHP) Settlement Overview Power Association of Northern California Luncheon, November 9, 2010 Frank Lindh General Counsel California.
1 Review of CPUC Role with the Public Interest Energy Research (PIER) Program on Natural Gas Briefing for California Senate Energy, Utilities and Communications.
The Market Outlook for Natural Gas: The Wyoming Natural Gas Pipeline Authority’s Perspective.
CALIFORNIA ENERGY COMMISSION NATURAL GAS ASSESSMENT: SHORT AND LONG TERM Briefing to the Legislature Assembly Utilities and Commerce Committee January.
California Energy Commission California’s Natural Gas Context Supply/Demand Outlook and Concerns for this Winter Joseph Desmond Chairman California Energy.
California’s Proposed DR Cost-Effectiveness Framework January 30, 2008.
March 30, 2012 Wholesale Generation Interconnection Process Photovoltaic Program Power Purchase Agreements Request for Offers.
Renewable & Alternative Power Senate Energy, Utilities & Communications Committee Stuart R. Hemphill Director, Renewable and Alternative Power Southern.
1 Sunrise Powerlink Project Update Orange County Business Council March 10, 2009.
DR issues in California discussed last year in March Historical DR in California: some background issues –Twenty years of programs/tariffs I/C and AC cycling.
1 Is there LNG in California’s Future? “LNG: When East Meets West” Zeus Development Conference Long Beach, CA by David Maul Manager, Natural Gas Office.
CPUC Public Agenda 3247 Thursday, January 21, 2010, 10:00 a.m. 505 Van Ness Ave, San Francisco Commissioners: Michael R. Peevey Dian M. Grueneich John.
Natural Gas and Energy Reform Legislation Steve Crout Managing Director, Government Affairs American Gas Association.
Southern California Edison The San Onofre Nuclear Generating Station April 14, 2011.
California Energy Commission Retail Electric Rate Projections: Revised Cases 2015 Integrated Energy Policy Report California Energy Commission December.
1 California Energy Commission April 27, 2015 Valerie Winn Chief, State Agency Relations Contingency Planning and Diablo Canyon Power Plant.
California Energy Commission Natural Gas Outlook IEPR Commissioner Workshop on 2015 Natural Gas Outlook Report Monday, September 21, 2015 Anthony Dixon.
Aliso Canyon Reliability Briefing to the Porter Ranch Community Advisory Committee Edward Randolph, Energy Division Director, California Public Utilities.
California Energy Action Plan July 17, Energy Action Plan Natural Gas Actions Status Report David Maul California Energy Commission Staff And Richard.
California Gas System Overview
Alternative Rate Structure Paul Smith Vice President, Rates Duke Energy Ohio June 20, 2006.
CEC Workshop January 24, 2003 January 24, 2003 Chris Price Market Development Wild Goose Storage Inc.
California Energy Action Plan December 7, 2004 Energy Report: 2004 and 2005 Overview December 7, 2004.
Entrega Gas Pipeline Project Wyoming Natural Gas Pipeline Authority - August 24, 2004.
CEC Public Workshop Order Instituting Informational and Rulemaking Proceeding (08-DR-01) March 3, 2008.
- DISCOVER THE DIFFERENCE - Florida’s Natural Energy - DISCOVER THE DIFFERENCE -
CEC Load Management Standards Workshop March 3, Update on the CPUC’s Demand Response and Advanced Metering Proceedings Bruce Kaneshiro Energy Division.
1 Bret Lane, Chief Operating Officer, SoCalGas LOCAL ENERGY RELIABILITY IN SUMMER 2016 SOCALGAS ® ACTIONS April 8, 2016.
Community Choice Aggregation Demonstration Project Marin County Base Case Feasibility Analyses Overview April 5, 2005.
Aliso Canyon’s Impact on Electric Reliability Technical Analysis and Action Plan Joint Agency Workshop April 8, 2016 California Energy Commission California.
Joint Energy Auction Implementation Proposal of PG&E, SCE and SDG&E California Public Utilities Commission Workshop – November 1, 2006.
Transmission Pricing Options
California Energy Solutions Group
CPUC Rate Proceedings Relevant for TOU
Presentation transcript:

California Public Utilities Commission Regulation and Natural Gas Infrastructure Richard Myers CPUC Energy Division May 14, 2009

2 CPUC Jurisdiction is Extensive but Does Not Cover All CA Infrastructure CPUC-regulated utilities deliver natural gas supplies to over 10 million customers in California Over 100,000 miles of pipelines and over 200 billion cubic feet (Bcf) of storage capacity Roughly Bcf/d of deliveries on utility systems, or about 80% of total California consumption Another 20% of demand is supplied directly off interstate pipeline systems or from California production CPUC also regulates storage providers CPUC does not regulate CA or out-of-state natural gas producers or interstate pipelines

3 CPUC Policy on Natural Gas Infrastructure and Capacity Allow gas utilities to gain better access to new sources of supply, develop a diverse supply portfolio, and have adequate storage capacity for core procurement requirements Ensure adequate, diverse utility natural gas pipeline and storage infrastructure for utilities and consumers  Assure delivery of supplies with high degree of certainty, especially for core customers  Minimize transmission constraints  Provide access to diverse portfolio of supplies  Reduce the likelihood of price spikes  Allow more gas to be stored when prices are low  Allow customers to match supplies with requirements Suppliers and pipelines should have fair access to utility transmission systems

4 CPUC Encourages or Requires New Infrastructure via Various Means Market mechanisms, e.g. independent storage expansion CPUC orders following litigation/settlement, e.g. SoCalGas storage expansion per Biennial Cost Allocation Proceeding (BCAP) Cost of service regulation, e.g. distribution pipeline additions Requests for transmission capacity expansion, e.g. per the Gas Supply Rulemaking and Firm Access Rights framework Delivery reliability guidelines, e.g.  Core and noncore reliability standards  Overall slack capacity standards

5 Recent and Pending CPUC Actions on Infrastructure & Capacity Rights PG&E contracts for interstate pipeline capacity rights on Ruby Lodi Gas Storage’s Kirby Hills capacity expansion PG&E RFO process for incremental core storage capacity PG&E Gas Accord local transmission projects SoCalGas storage expansion approved in Biennial Cost Allocation Proceeding (BCAP) Gill Ranch/PG&E Gas Storage proposal for new storage facility Sacramento Natural Gas Storage proposal for new storage facility Wild Goose Storage capacity expansions Interstate pipeline consultation process for core procurement interstate rights

6 PG&E Capacity Rights on Ruby Pipeline In November 2008, CPUC approved PG&E contracts with proposed Ruby pipeline for long-term, firm capacity rights 250 million cubic feet per day (MMcfd) for core procurement, 125 MMcfd for electric generation department Allows significant access for the first time to Rockies supplies for PG&E Ruby construction will benefit not just PG&E but other northern CA consumers as well Expected 2011 operation date

7 Lodi Storage Expansion In March 2008, Lodi Gas Storage capacity expansion approved, second phase of Kirby Hills facility CPUC authorized increase in working storage inventory by 6.5 Bcf, and in injection and withdrawal capacity by 200 MMcfd

8 PG&E Requests for Offers of Incremental Core Storage In July 2006, CPUC authorized process under which PG&E’s core gas procurement department could obtain incremental storage capacity, beyond PG&E storage allocated to core customers PG&E Core Procurement Department obtained some additional capacity in 2007 from PG&E Storage and Lodi, with a two-year term that ended in March 2009 PG&E just filed a new request with CPUC to issue another RFO for new incremental storage, to replace some Baja Path capacity Pending before the CPUC

9 PG&E Local Transmission Projects In September 2007, CPUC approved latest PG&E Gas Accord settlement Pursuant to Gas Accord settlement, significant local transmission projects being constructed by PG&E in Sacramento and Fresno areas Includes areas that had experienced constraints

10 SoCal Gas BCAP Settlement Approval of Storage Expansion In Phase 1 of the current BCAP, the CPUC approved a settlement under which SoCalGas will expand storage inventory (7 Bcf) and injection capacity (145 MMcfd) over the period SoCalGas expected to file applications soon for authority to proceed with these storage expansions Phase 1 also allocated an adequate amount of SoCalGas storage capacity (79 Bcf) to SoCalGas and SDG&E core customers

11 Gill Ranch and PG&E Storage Project Proceeding pending before the CPUC In July 2008, PG&E and Gill Ranch Storage filed applications at CPUC for approval for a new storage facility near Fresno Gill Ranch to own 75% and PG&E to own 25% of facility 20 Bcf of inventory capacity, 650 MMcfd of injection and withdrawal capacity Has potential for additional Bcf of inventory Settlements with intervenors recently reached, which applicants say settle all non-CEQA issues Final decision anticipated in late 2009

12 Sacramento Natural Gas Storage (SNGS) Pending before the CPUC, SNGS requested approval in April 2007 of a new storage facility in Sacramento area 7.5 Bcf inventory, 100 MMcfd injection capacity and 200 MMcfd withdrawal capacity Project has been opposed by neighborhood group Draft Environmental Impact Report issued April 2009, stated that current location is not the environmentally superior alternative Other locations suggested as environmentally superior, based on safety considerations

13 Wild Goose Storage Capacity Expansions Following CPUC November 2008 finding that condemnation of small parcel of land would serve public interest, Wild Goose Storage will expand capacity up to certificated capacity of 29 Bcf (from 24 Bcf) and withdrawal capacity from 480 to 700 MMcfd In April 2009, Wild Goose filed application at CPUC for expansion beyond certificated capacity Proposes to increase inventory capacity from 29 to 50 Bcf, injection from 450 to 650 MMcfd, and withdrawal from 700 to 1200 MMcfd Wild Goose estimates the additional project could be completed in months following CPUC approval

14 Interstate Pipeline Capacity Consulting Process In 2004, CPUC approved a streamlined process under which gas utilities could develop portfolio of interstate pipeline capacity rights Utilities must maintain minimum level of interstate pipeline capacity rights, about their annual average core demand Utilities consult with Division of Ratepayer Advocates (DRA), The Utility Reform Network (TURN) and CPUC’s Energy Division If DRA and TURN concur with utility proposal, utility may request approval from Energy Division staff Since 2004 process implemented, staff has approved numerous interstate pipeline capacity contracts with natural gas utilities Utilities have developed a portfolio of contracts with varying terms and capacity amounts, rather than small number of large, long-term contracts

15 Other Recent Utility Expansions and Measures SoCalGas is increasing local transmission capacity in the Imperial Valley, formerly a “constrained” area, by 110 MMcfd (from 90 to 200 MMcfd) - should be complete this summer Upgrades completed on SDG&E system to allow deliveries of LNG supplies from Costa Azul LNG terminal (operational in May 2008) FAR transmission framework implemented October 2008 in southern California,  provides framework for determining location of capacity demand  assures LNG suppliers can gain firm access to SoCalGas/SDG&E transmission systems