Muon g-2 Installation Schedule All Experimenters Meeting June 16, 2014 Aria Soha Muon g-2 I&I Manager.

Slides:



Advertisements
Similar presentations
Tagger and Vacuum Chamber Assembly Procedure. Outline. Assembly procedure for tagger and vacuum chamber. Support stands. Alignment.
Advertisements

April 21, 2010 Barbara C. Jordan Elementary School Update Presented by.
Zebulun Krahn Advisor: Curtis Meyer Technician: Gary Wilkin Carnegie Mellon University Straw Tubes and Hall D December 11-13, 2003 GlueX Collaboration.
The Preassembling Installation Survey & Alignment Accelerator Center of IHEP Qu Huamin 2006 / 4 / 27.
TPC meeting, NBI, 2-3 September 2002Børge Svane Nielsen, NBI1 Status of laser system TPC meeting, Copenhagen, 2-3 September 2002 Børge Svane Nielsen, Jørn.
TPC meeting, CERN, 7-8 October 2003Børge Svane Nielsen, NBI1 Status of laser system TPC meeting, CERN, 7-8 October 2003 Børge Svane Nielsen, Niels Lindegaard,
LED Signs Installation By LED Craft Inc. P20mm Full Color LED Sign : 32” high x 90” wide Lit Box Sign: 18” high x 90” wide
Unit 42 Floor Framing Floor Unit Resting on Sill Plates • Floor Unit Resting on Cripple Walls • Posts and Beams • Floor Joists • Subfloor • Floor Underlayment.
Muon g-2 Muon g-2 Experiment Quarterly Report Aria Soha All Experimenter’s Meeting March 2, 2015.
Screw Lift Prepared by : Areen abu kishek Amjad Haj Yousef Julia Thaher Heba Asmar Mohammed Qasrawi Presented To : Eng. Jad Mouqadi.
J. H. ChrzanowskiNSTX TF Flag Joint Design Review1 NSTX TF Flag Joint Design Review Fabrication and Assembly April 10, 2003 By: James H. Chrzanowski.
Step IV Infrastructure update STFC Tim Hayler Eddie Holtom Norbert Collomb Graham Stokes 14 th December 2011 MICO170 meeting 1Tim Hayler.
Jo Beth Folger MMF Site and October 14, Conventional Facilities – MMF Presentation Outline Facility Design.
Tagger and Vacuum Chamber Design. Outline. Design considerations. Stresses and deformations. Mechanical assembly.
GLAST LAT ProjectLAT Mgr’s Meeting LAT Planning Meeting Mechanical/Thermal Systems March 17, 2005 Marc Campell.
TAGGER MAGNET DESIGN Presented by Tim Whitlatch Hall D Tagger Magnet Design Review July 10,
Door Details in Masonry. Masonry Construction u Detailer needs to understand –how a door is installed –space available (Masonry Opening) u Masonry Opening.
B ASEPLATES S LIDE S HOW. Anchor Bolts are positioned and placed in the concrete before it cures. Plastic caps are placed over the anchor bolts to protect.
ILC Main Linac Superconducting Cryogen Free Splittable Quadrupole Progress Report V. Kashikhin for Superconducting Magnet Team.
1 Cryostat assembly, integration and commissioning procedures M.Olcese Version: 07 May 2008.
LBT Q Engineering Review PSPI: PEPSI installation preparation, includes all of the pier modifications.
18 June 20031Integration Review B. Schmidt Outline: Filter design and basic concept to ensure seismic stability Filter Installation and the required tooling.
Unit 91 Week 13 Jon Gutierrez, Chris Sauer, Simon Radomski, Chat Huynh, Jeff Burton, & Robert Platt November 12, 2008 Prototype Review Week 2.
Update on alignment kit and stave 250 frame M.Gibson (RAL) 1.
Office of Science Coupling Coil Status S. Gourlay August 1, 2012.
‘Market Leaders in Rendered Building Products’ The Poly-Tek Cabin.
Visit Gangway FromLHBIEP__0181 by Andre Coin ~ 2600 GANGWAY POSITION.
HOME IMPROVEMENT Project Monsters Second Status Report Reporting period: Feb 15-April 10, 2005 Project Manager: Hakki Isik Team members: Chad Harms Yilmaz.
24 January 2014 LARP VTF Follow-up Meeting P. Kovach VTF 1 LARP Vertical Test Facility Vertical Dewar Design, Magnet Prep And Installation Paul Kovach.
Schedule and Work We are moving into a very intensive 4 months with a lot of work to be carried out Electrical services to the devices – after the South.
LBT Q Engineering Review PSPI: PEPSI installation preparation, includes all of the pier modifications.
CLIC Permanent Magnet Quadrupole update 1 st December 2010 Mechanical Engineering status N. Collomb1.
G. Barber Sci-Fi Tracker Progress Ral 28 Oct Progress On The Design Of The Full Tracker Contents:- Recap of New Station Layout Version 2.5 Version.
Shear Problem Defined There are no bolts on the inboard side of the coil structure to account for shear forces. Bottom Line: friction alone will not prevent.
Step IV Construction North Side Walls and End Walls May 2015 Stephen Plate, Brookhaven National Laboratory.
 YE+4 disks = 2 Nos. (12 Sectors each)  Support Structures = 2Nos.  AISI 1045 steel bar = 1 No. for checking dimension of 680 mm (0/-0.5)  Fasteners.
Fundamentals of Structural Detailing
Safe Spot ME 4182 Prototype Review #1 March 29, 2006 J.J. Couvillion - Drew Bartlett - Manish Patel - Nick Roberts - Elisha Mellitz.
Unit 91 Week 14 Jon Gutierrez, Chris Sauer, Simon Radomski, Chat Huynh, Jeff Burton, & Robert Platt November 19, 2008 Prototype Review Week 3.
Design Review RSXS - EndStation Review on Vacuum Chamber Stand and Supports Location Beamline Roll-up Endstation.
CERN adb Chamber Support Structure Installation MUON SYSTEM INTEGRATION MEETING - Status of Production of support panels - Things to be settled.
Muon Trigger Status Report Eric James Trigger Commissioning Workshop 8/17/00.
PRY Base - Contents l PRY Support/Base/Platform in the MICE Hall l Requirements l Environment l Design l Structural Integrity l Preparation l Installation.
G.Barber/Peter Cooke: Mechanical Design Update Imperial 22 July Mechanical Update for Tracker workshop Contents:- New Station Layout Light Guide.
1 SVT Status Update Yuri Gotra CLAS12 Silicon Vertex Tracker TCB Meeting March 13, 2015.
Booster L12/Noker-L13/Absorber Update PIP Update Talk August 15, 2012 Salah Chaurize.
February 14, Comprehensive Review B. Schmidt Outline: Status and overview of activities: –Platforms and staircases –Muon Filters and beam plugs.
1 BROOKHAVEN SCIENCE ASSOCIATES Accelerator Systems Installation F. Willeke, ASD Director 6 th ASAC October 22-23, 2009.
SiD MDI Issues Tom Markiewicz/SLAC Beijing ACFA/GDE Meeting 05 February 2007.
MUON Project Overview Action Items from September meeting New Action Items Update to the List of Worries Update of plans for the next 6 months.
Presented by Mike Johnson
Tuesday 9 th January Project Status Report Project Achievements Project Schedule Issues Finance Summary Risk Register Photos.
SC2004 Exhibit Status. Proposed Schedule Exhibit ships from SLAC 7/22 Arrive Fermilab 7/29 Fermilab Quantum Universe display opens 10/1 Ship date to SC2004.
Dan Cheng 8/27/2015 MQXFS1 Observations and Feedback from the Assembly Processes, Part II.
Section 2 Safety, Tools and Equipment, Shop Practices Unit 6: Fasteners.
Warm Vessel Leveling Islands (Piers)
Mezzanine Update.
Present status of the flux return yoke design
BSS Prep work at CERN and Acceptance of Parts
Far Detector Activities Late 2017 – Early 2018
Introduction Jason Tarrant – Integration Engineering Step IV Removal
DESIGNING & HANGING A PROFESSIONAL ART EXHIBITION
DESIGNING & HANGING A PROFESSIONAL ART EXHIBITION
171-SH SH Box with Pre-Installed 101⁄2" Pigtail Popular 4" square boxes and switch boxes Pre-installed 101⁄2" insulated grounding.
BASEPLATES SLIDE SHOW.
GLAST Large Area Telescope:
“Fold-and-Go” Legends: Overall Status:  
STEEL PLATES.
Fixed Support Design & Testing
Muon Installation Status
Presentation transcript:

Muon g-2 Installation Schedule All Experimenters Meeting June 16, 2014 Aria Soha Muon g-2 I&I Manager

Outline Ring Installation Schedule Progress to date Vacuum Chamber Sequencing Overall Schedule Summary Pictures 2 Aria Soha Muon g-2

Short-Term Ring Installation Schedule 3 Aria Soha Muon g-2 Link to Live Web DocumentLive Web Document

4 Aria Soha Muon g-2 Progress to date & near-term TaskScheduled timeActual time Anchor angle bracket dams2 days1 week(Power Outages interferred) Base plate hole drilling2 weeks3 weeks(Power Outages interferred) Disassemble Prototype1 day2 days Electrical Panels on South wall5 weeks epoxy threaded rod2 days Fasten steel angle to the floor to create a dam1 day2 days Grout Cures24 hours Grout Round 21 week2 days Grout, Round 11 week2 days Iron stability Measurements (Capacitec) Measure Yoke-ear spacing1 day Paint Base plates1 week1 day Prep Bottom Yokes3 days Reference Bottom Yoke A1 day 5 days Reference Bottom Yoke C & B1 day Reference Bottom Yoke D & E1 day Reference Bottom Yoke F & G1 day Reference Bottom Yoke H & I1 day Reference Bottom Yoke J & K1 day Reference Bottom Yoke L1 day Set elevation and level base plates2 days1 day Set elevation and level base plates2 days Set Jack Stands to elevation1 day Install Bottom Yoke A2 days1 day Align Bottom Yoke A1 day Move C, D, E Bottom Yokes from ME71 dayDelayed due to asphalting

Vacuum Chamber Sequencing 5 Aria Soha Muon g-2 Link to Live Web DocumentLive Web Document

Installation is progressing well Cross coordination between WBS categories is planned and well in hand. Pictures…. 6 Aria Soha Muon g-2 Summary

Delivery of Steel to MC-1 7 Aria Soha Muon g-2

Base Plate Installation 8 Aria Soha Muon g-2

Grouting 9 Aria Soha Muon g-2

Student Involvement 10 Aria Soha Muon g-2

First Yoke Placed! 11 Aria Soha Muon g-2

Current Status 12 Aria Soha Muon g-2 Aligning Bottom Yoke A Electrical Panels being installed on South wall Angle Brackets installation

Current Status 13 Aria Soha Muon g-2