GLAST LAT ProjectMonthly Review, March 30, 2005 4.1.7 DAQ & FSWV2 1 GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S 4.1.7.

Slides:



Advertisements
Similar presentations
GLAST LAT ProjectMonthly Review, Aug-1, DAQ & FSWV1 1 GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S
Advertisements

GLAST LAT ProjectNovember 3, 2005 I&T Phase 0 IRR/TRR 1 GLAST Large Area Telescope: Integration and Test Phase 0 IRR/TRR November 3-4, 2005 Introduction.
GLAST LAT ProjectMonthly Status Meeting Jan 26, Project Status January 26, 2006 Gamma-ray Large Area Space Telescope Lowell A. Klaisner Project.
GLAST LAT ProjectSIU MRR DAQ & FSWV1 1 GLAST Large Area Telescope: G. Haller SLAC (650) Gamma-ray Large Area Space.
GLAST LAT Project I&T Integration Kickoff Meeting 03/09/04 Online 1 GLAST Large Area Telescope: I&T Integration Kickoff Meeting EGSE Hardware March 9th,
GLAST LAT ProjectMonthly Review, September 1, Tracker SubsystemR. Johnson 1 GLAST Large Area Telescope: Tracker, W.B.S August Status Meeting.
GLAST Calorimeter LAT F2F Meeting 17 Mar 2005 Naval Research Lab Washington DC W Neil Johnson 1 Subsystem Mgrs F2F Meeting Calorimeter Subsystem 17 Mar.
Tower Electronics Module and Tower Power Supply EM Tower Electronics Module (TEM) before coating/staking TEM & TPS assembly Close to 60 TEM & TPS assemblies.
GLAST LAT ProjectMonthly Status Meeting, June 30, Cost/Schedule Reports for 4.1 LAT Presentation Presentation May 2005 Month End Gamma-ray Large.
GLAST LAT ProjectNovember 04, 2005 Phase 0 TRR 1 GLAST Large Area Telescope: Integration and Test -Electrical Test- Phase 0 TRR Key Requirements Documents.
1 GLAST LAT ProjectMechanical Systems Mechanical Systems Mechanical / Thermal Hardware July 2005 Status Marc Campell, Subsystem Manager.
GLAST LAT ProjectMonthly Status Review – Sept. 1, 2005 GLAST Large Area Telescope: Performance & Safety Assurance Joseph Cullinan SLAC Performance & Safety.
GLAST LAT ProjectDOE Rebaseline Review, February 13, GLAST Large Area Telescope: Lowell A. Klaisner Stanford Linear Accelerator Center Chief Engineer.
GLAST LAT Project4.1.7 G. Haller V21 GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S Face-to-Face Nov 04 Mike Huffer/Gunther.
GLAST June 8, 2000, P. Roger Williamson, BFP - 1 Balloon Flight Planning Roger Williamson June 8, 2000.
GLAST LAT Project4.1.7 G. Haller V21 GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S September Status
GLAST LAT Project Quarterly Review, Aug. 14, 2001 Gunther Haller1 GLAST Large Area Telescope: Electronics, DAQ & Flight Software Gunther Haller Stanford.
GLAST LAT ProjectF2F, June 15, 2005 GLAST Large Area Telescope: Performance & Safety Assurance Joseph Cullinan SLAC Performance & Safety Assurance Manager.
GLAST LAT Project Technical/Cost/Schedule Review 09/01/ Integration and Test 1 GLAST Large Area Telescope: I & T Input to Monthly Technical/Cost/Schedule.
GLAST LAT ProjectNovember 3, 2005 I&T Phase 0 IRR/TRR 1 GLAST Large Area Telescope: Integration and Test Phase 0 IRR/TRR November 3-4, 2005 Introduction.
GLAST LAT Project4.1.7 July 17, 03 LAT Meeting G. Haller V41 GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S LAT.
GLAST LAT Project Technical/Cost/Schedule Review 03/30/ Integration and Test 1 GLAST Large Area Telescope: I & T Input to Monthly Technical/Cost/Schedule.
GLAST LAT ProjectF-to-F, June 15, DAQ & FSWV1 1 GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S Face-To-Face.
GLAST LAT ProjectSubsystem Managers Meeting May 12, GLAST Large Area Telescope: Lowell A. Klaisner Stanford Linear Accelerator Center Project Manager.
ISOC Peer Review - March 2, 2004 Section GLAST Large Area Telescope ISOC Peer Review Test Bed Terry Schalk GLAST Flight Software
GLAST LAT Project November 18, 2004 I&T Two Tower IRR 1 GLAST Large Area Telescope: I&T Integration Readiness Review Integration, Facility, Configuration.
GLAST LAT ProjectLAT Planning Meeting July 17 th and 18 th Integration and Test 1 GLAST Large Area Telescope: I & T Input to LAT Planning Meeting.
GLAST LAT ProjectNovember 18, 2004 I&T Two Tower IRR 1 GLAST Large Area Telescope: Integration and Test One and Two Tower Integration Readiness Review.
GLAST LAT ProjectEnv Test Planning, 3-4 May 2005 LAT Environmental Test PDR 1 LAT Environmental Test Planning and Design Review 3-4 May 2005 LAT EGSE and.
GLAST LAT ProjectF-to-F, March, DAQ & FSWV1 1 GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S Face-To-Face.
GLAST Calorimeter SLAC LAT Meeting 17Jul 2003 Naval Research Lab Washington DC wnjohnson 1 SLAC Meeting Calorimeter Subsystem 17 July 2003 W. N. Johnson.
GLAST LAT ProjectOct DAQ & FSWV3 1 GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S Analysis of cPCI Backplane.
GLAST LAT ProjectTower Power Supply Review Sept 22, 2003 Gunther HallerPart 2, Version 4 1 GLAST Large Area Telescope: Electronics, Data Acquisition &
GLAST LAT ProjectDOE/NASA Status Review, March 30 & 31, DAQ & FSWV8 1 GLAST Large Area Telescope: Gunther Haller SLAC LAT Chief Electronics.
GLAST LAT ProjectPDU/GASU MRR, February 3, DAQ & FSWV1 1 GLAST Large Area Telescope: B. Estey, G. Haller SLAC xxxx LAT Quality Engineer
GLAST LAT ProjectGASU TRR, July, DAQ & FSWV1 1 GLAST Large Area Telescope: Presented by G. Haller SLAC (650)
GLAST LAT Project PDU/GASU MRR 4 February 2005 PART 2 / 1 GLAST Large Area Telescope: B. Estey, Production SLAC (650)
EGSE CENTRIC PLAN FOR TWO TOWER TESTS IN ACCORDANCE WITH MEETING HELD 02 MAR 2005 REVISED 22 MAR 2005.
Linac Marx Modulator Update Trevor Butler 10/29/2014.
GLAST Large Area Telescope:
GLAST LAT ProjectMonthly Review, March 30, DAQ & FSWV1 1 GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S
GLAST LAT ProjectEGSE Peer Design Review, August 17, S. WilliamsEGSE Overview Electrical Ground Support Equipment Overview Scott Williams Stanford.
GLAST LAT Project4.1.7 G. Haller V11 GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S Monthly Status Gunther.
DAQ Development P. Roger Williamson Hansen Experimental Physics Laboratory Stanford University GLAST Collaboration Meeting GSFC February 10, 1999.
GLAST LAT Project – Cost and Schedule ReviewJanuary 27, 2004 AntiCoincidence Detector 1 GLAST Large Area Telescope: Cost/Schedule Review January 27, 2005.
GLAST LAT Project Technical/Cost/Schedule Review 04/26/ Integration and Test 1 GLAST Large Area Telescope: I & T Input to Monthly Technical/Cost/Schedule.
GLAST LAT ProjectMonthly Status Review – June 30, 2005 GLAST Large Area Telescope: Performance & Safety Assurance Joseph Cullinan SLAC Performance & Safety.
GLAST LAT ProjectMonthly Review, May 24, DAQ & FSWV2 1 GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S
GLAST LAT Project LAT System Engineering 1 GLAST Large Area Telescope: LAT System Engineering Pat Hascall SLAC System Engineering Manager
GLAST LAT ProjectMonthly Review, May 24, DAQ & FSWV1 1 GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S
GLAST LAT Project LAT System Engineering 1 GLAST Large Area Telescope: LAT System Engineering Pat Hascall SLAC System Engineering Manager
GLAST LAT Project4.1.7 G. Haller V2 1 GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S April Status Gunther.
GLAST LAT ProjectMonthly Review, June 30, DAQ & FSWV2 1 GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S
GLAST LAT ProjectCAL Peer Design Review, Mar 17-18, 2003 W. N. Johnson Naval Research Lab Washington DC GLAST Large Area Telescope Calorimeter Subsystem.
GLAST LAT ProjectMonthly Status Review – Nov 3, 2005 GLAST Large Area Telescope: Performance & Safety Assurance Joseph Cullinan SLAC Performance & Safety.
GLAST LAT Project4.1.7 G. Haller V31 GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S Monthly Status Gunther.
1 GLAST LAT ProjectMechanical Systems Mechanical Systems September 2003 GSFC Status Marc Campell, Subsystem Manager.
GLAST LAT ProjectGLAST Flight Software, 7 February 2003 FSW Development Plan 1 GLAST Large Area Telescope: Instrument Flight Software Development Plan.
GLAST LAT ProjectFace to Face, 14 April 2004 LAT System Engineering 1 GLAST Large Area Telescope: EGSE and Interface Verification Pat Hascall SLAC System.
GLAST Large Area Telescope Instrument to Spacecraft Interface Simulator (ISIS) Test Readiness Review 15 December 2004 Jana Thayer Eric Hansen Stanford.
GLAST Large Area Telescope LAT Flight Software System Checkout TRR Test Environment Sergio Maldonado FSW Test Team Lead Stanford Linear Accelerator Center.
GLAST LAT ProjectDOE/NASA Peer Critical Design Review, March 19-20, 2003 D. Nelson 1 GLAST Large Area Telescope: Electronics, Data Acquisition & Instrument.
GLAST LAT ProjectSLAC Internal Review, April 16-18, 2002 LAT-PR Electronics and Flight Software WBS GLAST Large Area Telescope: Electronics,
GLAST LAT ProjectMonthly Review, Sept 27, DAQ & FSWV1 1 GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S
Bill Raynor Naval Research Lab
GLAST Large Area Telescope:
GLAST Large Area Telescope:
Mechanical Integration
GLAST Large Area Telescope:
Introduction and Overview
Presentation transcript:

GLAST LAT ProjectMonthly Review, March 30, DAQ & FSWV2 1 GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S April Monthly Review Gunther Haller (650) Gamma-ray Large Area Space Telescope

GLAST LAT ProjectMonthly Review, March 30, DAQ & FSWV2 2 TEM/TPS Status & Schedule Status –Qual unit at NRL used for FM CAL testing in TV –A & B at I&T on tower A and B –1 & 2 to SLAC 5/9, to I&T 5/19 MOSFET’s were not tinned before assembly on TPS, devices were replaced Conformal Coating materail had expired, after tests extended expiration date –Rest of module: 2/week thereafter 6/27 last delivery to SLAC per schedule –Probably will exchange TPS on Tower A/B once sufficient TEM/TPS are at SLAC –Changed from original design Low voltage: some resistors were changed and one cap added per supply circuit to eliminate oscillation: fixed problem Bias voltage: caps were exchanged to improve phase-margin and stabilize supply. Resulted in large phase-margin Unrelated to that, have seen low-level ripple of supply at specific loads and specific voltages. Cause is time-constant of charge redistribution on series pumping capacitors. No plan to change, is a feature.

GLAST LAT ProjectMonthly Review, March 30, DAQ & FSWV2 3 PDU Status and Schedule Schedule for proto-flight –Delay at vendor –Now 5/4/05: unit assembled, pre-coat, to be sent to SLAC for testing –Back to Aeroflex on 5/11 for coating/staking –Back to SLAC 6/6 for environmental testing (Vib/TV/EMI) –Ready 6/20 Schedule for Flight Unit –6/10/05 Precoat PDU assembly ready for electrical test –7/10/05 Complete assembly ready for environmental test –7/20/05 Flight PDU to I&T –If that is too late, use proto-flight Tester –Analog mux card for TV test, fabricated, assembled –Vacuum feed-thru plate received, installed, in leak-testing –Vibration fixture fabricated

GLAST LAT ProjectMonthly Review, March 30, DAQ & FSWV2 4 GASU Status and Schedule Status –First delay from parts kitting –Then delay at vendor (bottle-neck with PDU/GASU/PCI connector assembly tests) Schedule for proto-flight –5/31: unit assembled, pre-coat, ready for test at SLAC –6/7: back to Aeroflex for coat/stake –6/29: unit fully assembled, ready for environmental test Schedule for Flight Unit –7/10/05 Precoat GASU assembly ready for electrical test –8/1/05 Complete assembly ready for environmental test –8/10/05 Flight GASU to I&T Tester –Tester in design/debug –Harness for TV in assembly –Received TV IO vacuum feed-thru

GLAST LAT ProjectMonthly Review, March 30, DAQ & FSWV2 5 GASU testing support –Automated stray voltage and S/T/M (not shown) –GASU firmware signed off –Functional tests –Trigger Pattern Generator Simulates all trigger signals (primary and redundant) Arbitrary time simulation Interfaces to LATTE GASU tester… TPG External test-box GASU Function generator P/S

GLAST LAT ProjectMonthly Review, March 30, DAQ & FSWV2 6 SIU/EPU Status and Schedule Status –Parts kitted –Board had to be refabricated due to coupon failures (fab now at DDI and Tyco for risk/schedule mitigation) –Send 5 SIB boards and connectors to Aeroflex 10 days ago –Will send 5 back-plane boards this week –Then next round of connector assembly will be done. Schedule –Delay from original schedule because of above –Estimate 2 weeks delay from dates below –6/1/05 Precoat cCPI boards ready for electrical test –7/28/05 Complete assembly ready for environmental test –8/19/05 First Flight SIU/EPU to I&T –8/24/05 Second flight SIU/EPU to I&T –8/27/05 Third flight SIU/EPU to I&T –8/30/05 Fourth flight SIU/EPU to I&T –9/2/05 Last flight SIU/EPU to I&T Tester –In design

GLAST LAT ProjectMonthly Review, March 30, DAQ & FSWV2 7 Harness Harness in assembly Received several types of cable assemblies –Bottle-neck is TEM-GASU cable since potting needed to be added. Vendor is waiting for material and supplemental PO. (Latter was just placed) Hardware/LAT-Harness/lat-harness.htmhttp://www-glast.slac.stanford.edu/Elec_DAQ/DAQ- Hardware/LAT-Harness/lat-harness.htm

GLAST LAT ProjectMonthly Review, March 30, DAQ & FSWV2 8 EGSE

GLAST LAT ProjectMonthly Review, March 30, DAQ & FSWV2 9 2-Tower Support Flight-like architecture with EM parts Complete (accepted by I & T) BPU P/S (Supplied by I & T) GASU TEMs External Test Box PDU To External Crate Shield penetration

GLAST LAT ProjectMonthly Review, March 30, DAQ & FSWV2 10 Thermo-testing support Electronics provides: –Feedback code –Platform to execute feedback code –LAT thermo-related monitoring –Power management (conditioning, monitoring and cabling) Architecture is basically same as 2-tower test… –Except… Power management –PDU, GASU and SIU in hand Test-stand being assembled (cables, Rack etc…) –Feed-back code written (and somewhat debugged) Ad hoc committee formed to coordinate this test… –Rich Baun (chairman) –Marc Campell –Jana Thayer (for electronics)

GLAST LAT ProjectMonthly Review, March 30, DAQ & FSWV2 11 VSC (status) Client Interfacing Hardware LAT functional hardware interfaces Software LAT/VSC Cable Interface Summary

GLAST LAT ProjectMonthly Review, March 30, DAQ & FSWV2 12 Client Interfaces (status) Design has been “reviewed” by all relevant clients: –FSW and FSW/test –I & T –ISOC New revision of documentation… –Additional, concrete detail Moving from a design document to reference document –FSW/test is now actually coding against committed code –FSW/test schedule is not currently impacted by complete (prototype) VSC delivery

GLAST LAT ProjectMonthly Review, March 30, DAQ & FSWV2 13 Hardware status All hardware delivered and on hand for four (4 ) VSCs –Subject to these caveats… S/C telemetry monitoring required more systran boards then initially envisioned (ordered, off-the-shelf delivery) –Have enough on hand to put together prototype –Will talk about more below… VSC/LAT Cable Interface –Will talk about more below… Neither of these shortages affect prototype use by FSW/Test Cabling for test-bed –defined –connectors delivered –queued for construction

GLAST LAT ProjectMonthly Review, March 30, DAQ & FSWV2 14 Prototype VSC under construction… Science Interface GPS receiver systran board (removed) SBC 1553 interface (removed) to GASU

GLAST LAT ProjectMonthly Review, March 30, DAQ & FSWV2 15 LAT functional hardware interface (status) Status includes hardware/firmware and driver software –1553 (done) –Discretes (done) –Science Interface (done) Remains to wrap for C++ interface (see package status)

GLAST LAT ProjectMonthly Review, March 30, DAQ & FSWV2 16 Package (software status) CCSDS (complete, committed) Handlers (complete committed) Network (complete, committed) Thread (complete, committed) Queues (complete) Scheduler (complete) List (complete) Proxy (50% complete, +1 week to completion) Drivers (00% complete, +2 weeks to completion)

GLAST LAT ProjectMonthly Review, March 30, DAQ & FSWV2 17 VSC/LAT cable Interface Adapts LAT cables to VSC (VME) from factor Provides signal conditioning for temperature sensors –LAT originated, S/C telemetry –Implementation is VSC PART II Consists of two boards: –Inside board (LAT signals within the shield) –Outside board (LAT signals outside the shield) Grossly underestimated degree that adding S/C telemetry would affect design of this interface –+4 weeks design effort (done), allocated zero Status: –Inside board Designed, out of layout at the end of week 1 week fabrication and load 1 week commission –Outside board one week behind inside board Prototype requires only inside board

GLAST LAT ProjectMonthly Review, March 30, DAQ & FSWV2 18 Mechanical Interface ABCDEABCDE VM ES C5 SY ST RA N I/O SCI ABCDEABCDE VM ES C5 SY ST RA N I/O SCI HRSHRS MINSMINS SECSSECS TTM 637 A B TC LK 1553 A B TC LK DISCI VSCIO850 JL124 JL125 JL138 JL145 JL121 JL122 MonP MonR M ON IT OR SCI EN CE A SI U SCI EN CE B VSCIO468 JL131 JL144 JL152 JL123 JL238 JL239 +Y -Y RA D GR ID M ON AC D M ON

GLAST LAT ProjectMonthly Review, March 30, DAQ & FSWV2 19 Issues Larger TPS ripple issue resolved, potentially have small ripple at certain loads/voltage settings AUSTIN EEPROM DPA problems –New lot delivery date 6/10, but no CSI yet, so not clear Qualification of cCPI press-fit connector assembly using solder process Need to work on closing open FPGA review items

GLAST LAT ProjectMonthly Review, March 30, DAQ & FSWV2 20 Level 3 Milestone Count

GLAST LAT ProjectMonthly Review, March 30, DAQ & FSWV2 21 Level 3 Milestone List

GLAST LAT ProjectMonthly Review, March 30, DAQ & FSWV2 22 Level 3 Milestone List

GLAST LAT ProjectMonthly Review, March 30, DAQ & FSWV2 23 Level 3 Milestone List

GLAST LAT ProjectMonthly Review, March 30, DAQ & FSWV2 24 Level 3 Milestone List

GLAST LAT ProjectMonthly Review, March 30, DAQ & FSWV2 25 Cost Report

GLAST LAT ProjectMonthly Review, March 30, DAQ & FSWV2 26 FTE Report (DOE/NASA-funded only)

GLAST LAT ProjectMonthly Review, March 30, DAQ & FSWV2 27 Comment to FTE Not budgeted –Amalia Russell 18 hrs Needed since Lupe (tech) went to more NASA certification classes –John Wray 35 hrs Added to help TEM/TPS safe-to-mate and CPT testing –Van Allen Clark 166 hrs Tech writer, still docs to modify (e.g. 2-TEM/TPS TV testing, etc –Shop Labor-Var. 352 hrs 24/7 need to watch TV chamber, night-shift/weekend