1 Integration of collimators in the dispersion suppressors Status of 11 T cryo- assembly integration Dec 17, 2013

Slides:



Advertisements
Similar presentations
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
Advertisements

19th – 20th of September 2007Cryogenic Expert Meeting at GSI, Jan Patrick Meier1/11 Cryogenic Experts Meeting at GSI, 2007 The SIS 100 Cryogenic Jumper.
MICE RF and Coupling Coil Module Outstanding Issues Steve Virostek Lawrence Berkeley National Laboratory MICE Collaboration Meeting October 26, 2004.
ColUSM #51 30 th January, 2015 D. Duarte Ramos, C. Mucher, L. Gentini, T. Sahner, H. Prin, R. Wawrowski, Q. Deliege, V. Baglin, F. Savary.
LHC HARDWARE COMMISSIONING REVIEW May 2005 CRYOGENIC VACUUM SYSTEM Paul Cruikshank for AT/VAC.
A. Perin, CERN, TE-CRG, 26 May Review of the cryogenic by-pass for the LHC DS collimators 26 May 2011 Modifications to the DFBs, DSLC and cryogenic.
4m Undulator Design Concepts Amanda J Brummitt CCLRC RAL On behalf of the HeLiCal Collaboration.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
CEA DSM Irfu - Bernard GASTINEAU - R3B Technical Board Meeting -April 4, Reactions with Relativistic Radioactive ions Beams GSI Large Acceptance.
F. Savary on behalf of the WP11 team Input from V. Baglin, D. Ramos.
MICE Collaboration Meeting March 29 - April 1, CERN MICE alignment, tolerances and supports Tuesday March 30 Room Edgar Black/IIT March17-
CRYO PIPING & INTER-MODULE CONNECTIONS Yun He, Daniel Sabol, Joe Conway External Review of MLC Daniel Sabol, MLC External Review 10/3/2012.
1 Presented at ColUSM by D. Ramos on behalf of the Cold Collimator Feasibility Study Working Group Longitudinal.
Laurent Tavian Thanks to contribution and helpful discussions with M. Jimenez, V. Parma, F. Bertinelli, J.Ph. Tock, R. van weelderen, S. Claudet, A. Perin,
ZQNA Electrostatic Quadrupoles for ELENA Transfer Lines 1.Conceptual design 2.Performance 3.Engineering details 4.Interfaces 5.Production planning D. Barna,
Alignment and assembling of the cryomodule Yun He, James Sears, Matthias Liepe MLC external review October 03, 2012.
REVIEW OF THE CRYOGENIC BY-PASS FOR THE LHC DS COLLIMATORS ELECTRICAL CIRCUIT MODIFICATION, INCLUDING OPERATIONAL CONSIDERATIONS PRESENTED BY A. SIEMKO.
Status of vacuum & interconnections of the CLIC main linac modules C. Garion TE/VSC TBMWG, 9 th November 2009.
CRYOGENICS AND POWERING
MQXF Cold-mass Assembly and Cryostating H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia 4 th Joint HiLumi LHC-LARP Annual Meeting November 17-21, 2014.
H. Prin, F. Savary, D. Duarte Ramos, L. Grand- Clement, C. Mucher, A. Temporal.
SCU Layout Concept - Minimal Segmentation Joel Fuerst (ANL) SCU 3-Lab Review Meeting Dec. 16, 2014.
FP 420 Connection Cryostat Design and Integration Keith Potter, Jaak Lippmaa, Guido Ryckwaert, Benoit Florin, Thierry Renaglia, Thierry Colombet, Shrikant.
1 Hi-Lumi WP3 meeting Update on the Q1 to D1 cryostat Jan 28, 2014  Outline  Cryostat cross section options  Elliptical interconnect.
SCU Segmented Cryostat Concept M. Leitner, S. Prestemon, D. Arbelaez, S. Myers September 2 nd, 2014.
12th HL-LHC Parameter and Layout Committee meeting.
C. Garion Presentation Outline  Overview of the inner triplet interconnections  Q1/Q2, Q2/Q3 interconnections  General view  Working conditions  Compensation.
9/17/07IRENG071 Cryogenic System for the ILC IR Magnets QD0 and QF1 K. C. Wu - BNL.
MICE Prototype Coupling Coil Fabrication Update Allan DeMello Lawrence Berkeley National Laboratory MICE CM38 - Napa California February 25, 2014 February.
Plan for test station Marta Bajko For the Technical Review of FReSCa2 June 2015 Saclay Paris.
Special interventions Status of production and QC Nicolas Bourcey TE-MSC-MDT Fourth LHC Splice Review November 2013.
Vacuum, Surfaces & Coatings Group Technology Department 22 nd January 2015 C. Garion2 Beam Line Interconnection: snapshot of present design principles.
The integration of 420 m detectors into the LHC
Mike Struik / LHC-CRI INSTRUMENTATION FEEDTHROUGH SYSTEM FOR LHC MACHINE ARC QUADRUPOLE MAGNETS. 123rd LHC Vacuum Design Meeting 19 April 1999.
Integration options for collimators in the DS zones V.Parma, CERN, TE-MSC With contributions/input from: V.Baglin, A. Bertarelli, M.Karppinen, H.Prin,
Can we change a magnet without warming-up a full arc ? Serge Claudet, With help from P. Cruikshank & J-P. Tock (Chamonix Jan’10)
HL-LHC 11 T Dipole for DS Collimation 8 th to10 th December, 2014 D. Duarte Ramos, C. Mucher, L. Gentini, T. Sahner, H. Prin, R. Wawrowski, F. Savary,
Date 2007/Sept./12-14 EDR kick-off-meeting Global Design Effort 1 Cryomodule Interface definition N. Ohuchi.
SPL cryomodule specification meeting, CERN 19th October 2010 SPL cryomodule specification: Goals of the meeting SPL cryomodule specification: Goals of.
CW Cryomodules for Project X Yuriy Orlov, Tom Nicol, and Tom Peterson Cryomodules for Project X, 14 June 2013Page 1.
LHC Beampipes Ray Veness / AT-VAC FP XII 08Beam Vacuum- R.Veness.
A. Perin TE-CRG, 06 April LMC 08 April 2009 Consolidations related to pressure protection on DFBs and DSLs A. Perin, TE-CRG.
ColUSM #63 18 th September, 2015 D. Ramos, C. Mucher, L. Gentini, H. Prin, Q. Deliege, A. Bastard, J. Hrivnak.
Bruno Vullierme Sept LHC-CC09 - 3rd LHC Crab Cavity Workshop Slide 1 CRAB CAVITY INTEGRATION CRYOGENICS INSTALLATION.
Workshop on cryogenic & vacuum sectorisation of the SPL Vacuum Sectorisation Paul Cruikshank, CERN Technology Department (TE) Vacuum Surfaces & Coatings.
ILC : Type IV Cryomodule Design Meeting Main cryogenic issues, L. Tavian, AT-ACR C ryostat issues, V.Parma, AT-CRI CERN, January 2006.
Inner Triplet Review 1 H. Prin AT/MEL Activities on the triplets at CERN Reception and Acceptance Triplet String Assembly in Building 181 Handling and.
Inner Triplet Review 1 H. Prin AT/MEL Activities on the triplets at CERN Reception and Acceptance Triplet String Assembly in Building 181 Handling and.
1 Status of the 11T cryo-assembly design and integration Presented at ColUSM #34, February 21, 2014
Cryostats for superconducting magnets
ALIGNMENT OF THE NEW TRIPLETS
SPL RF coupler: integration aspects
D. Ramos, H. Prin, M. Moretti, C. Eymin, A. Temporal, V. Parma, S
Cold mass design, assembly plans and QA/QC at CERN
Roadmap for triplet cryostats
Internal review of IR2 LEP cryostats (WP11/WP5) Close out session
HFM Test Station Main Cryostat
Cryostat procurement, status and plan, QA/QC
Status of design and production of LEP connection cryostat
A. Vande Craen, C. Eymin, M. Moretti, D. Ramos CERN
Cryo-assembly design D. Ramos, V. Parma, C. Mucher, H. Prin, M. Souchet, J. Hrivnak, M. Moretti, L. Mora, F. Savary, L. Gentini Review of the 11T Dipoles.
Challenges of vacuum chambers with adjustable gap for SC undulators
Status of cryostat integration and conceptual design
The 11T cryo-assembly: summary of design and integration aspects
Design of Distribution Feedbox at LHC P7
Cryostats Some ideas for the new Q1 to Q3 Hi-Lumi WP3 meeting
Magnetic shielding and thermal shielding
Status of QQXF cryostat
Simplified Procedure Draft
J. Fleiter, S. C. Hopkins, A. Ballarino
Presentation transcript:

1 Integration of collimators in the dispersion suppressors Status of 11 T cryo- assembly integration Dec 17, 2013

Outline  (Today’s) “Rules of the game” (Some say design constrains, functional specifications, interfaces, etc...)  11 T + Collimator cryostat concept  What’s next 2

Full interchangeability with a standard dipole (no changes to neighbouring cryomagnets) 3 K2 QRL side M2 V2 W Y M1 M3 E C’ V1 K1 X N  No changes to cryo, electrical or mechanical interfaces (different jack’s position is inevitable)  mm long, interc. included  Inside the 11 T cryostat:  X-line remains straight  He II free cross section: 60 cm 2  Pressure drop of He II circuit: 4.3 kPa/m (50 mm smooth pipe)  Pressures and temperatures acording to LHC-Q-ES-0001 (edms 90032)

Operation and maintenance  Mechanical decoupling from cryostat and collimator for removal and alignment of collimator without warming up the arc  bellows between collimator tank and cryostat, independent supports to the floor, compatible integration  One collimator design fits beam 1 and beam 2  Minimise exposure to residual radiation  simplify removal/installation of collimator, ex. quick CF flanges, pre- aligned collimator support system, “rapid” electrical and hydraulic connections (but not remote handling), permanent bakeout insulation  Ports for “RF-ball” test of new sectors  Transport constraints: Stay in the “shadow” of the existing arc cryostat 4

Vacuum  Room temperature (bakeable) collimator vacuum operated and maintainded independently from cold beam vacuum  sector valves on both lines  Beam screens (K-line cooling) with same reliability and performance as rest or the arcs (no helium to beam vacuum welds, testing, etc.)  No demountable vacuum tight joints in cryogenic system  Ensure pressure safety of each new beam vacuum “subsectors”  rupture disks on SSS ports  Ensure pressure safety of insulation vacuum (DN 200’s)  Respect current RF-impedance requirements: ex. shielded sector valves, shielded bellows, max 15º taper angle 5

Thermo-mechanical  Busbar flexibility must take into account adjacent magnets  Temperature offset between cold mass and beam screen during transient  Temperature variation between two cold masses during transient  Cold to warm transitions on the beam lines 6

Standard interfaces + fixed length → why the collimator must be in the middle 7 New end covers may be made to route the bus bars in a way to provide enough space for the collimator (no interchangeability between cold masses). Standard interfaces Additional module needed to create a standard interconnect interface and thermal compensation. Interference with W sleeve (ok if collimator on the other side). Not possible to fit netiher the collimator nor sector valves between standard bus bar lines. New routing needed to make vertical space for the collimator

Basic concept  Independently cryostated and handled cold masses, linked through two short transfer lines  Transfer lines with expansion joints mechanically decouple cryostats A and B  Splice and piping interfonnect in the tunnel, all other work prior to installation  Can use the existing TCLD collimator design with modified the supports 8 Collimator Lines M, E, N, K, C’ Reinforced jacks to widstand vacuum forces Cold mass ACold mass B Line X Independently supported collimator Busbar splice and interconnect done in the tunnel Flexible S-shaped busbar stabiliser Busbar lyra

Mechanical alignment decoupled with expansion joints  No cold support adjustment  Conventional alignment procedure with adjustment on cryostat jacks and displaced fiducials 9 Universal expansion joint

Access for in-situ repair  Once the collimator removed, the vacuum vessel cover can slide open  In-situ access for repair of «fragile» components:  Expansion joints  Flexible hoses  Diode  Instrumentation feedthrough (IFS)  Current leads (?) 10 Collimator Cold mass ACold mass B

Will it fit in mm? (Layout of beam line equipped with collimator)

Concept of 11 T cryo-assembly 12

13 Interconnect sleeve (rigid) Expansion joints or flexible hoses on all lines Expansion joints RF-shielded bellows

14 Diode ? Splices Line M (6 busbars + splools) Line N Line E Lines C’ and K (not shown) Collimator Line X C’ and K lines not shown

Elements defining the design in the transverse plane  Line X insulation  RF-shield module of gate valve 15 N E M X QRL sideTransport side

Main features  Seen by neighbouting magnets as standard dipole: Staightforward replacement in case of major problem  Can be cold tested as a single unit in a dipole test bench and split in two for handling and transport  Standard alignment procedures  Completely independent operation of collimator and cryogenic systems  Access for some in-situ repairs  Simplified construction  Non-compromised functionality wrt existing arcs  Passed a first iteration with simplified CAD model  Minimised impact on the collimator design (assuming 800 mm long TCLD) 16

The short term “to do list”  Cold bore diameter?  Are M1 and M2 busbars needed?  Do we need spools?  Routing the busbars inside the cold mass end covers is the next challenge  Re-design components that can be optimised in length  Detail pipe dimensions and routing  Can we pull the line N cable? Can the line N splice be avoided?  Do we need diodes? One unit enough for both cold masses?  Trim powering? (Use line N? Compatibility with DFBA?)  Cold tests done prior to beam screen installation?  Determine position of supports for compatibility with special SSS cryostating tool and dipole anchors  Do we need to shield the collimator from busbar magnetic field as in the QTC? (stainless or carbon steel covers?)  Do we need more DN200’s on adjacent magnets?  Draft and approve interface specification 17 June 2014? yes Start busbar routing as if we do Just started 50 mm, as the other magnets, standard beamscreens

Steps towards “valid for installation” cryostats  Mockup of the bypass subassembly (asap!)  Validate integration of all components  Measure fabrication tolerances  Test alignement flexibility  Train personnel on assembly procedures  Exercise installation, alignment and removal of collimator  Simulate repair interventions  Develop tooling  Feedback for design improvements  Iterate on drawings, specifications, tooling design  Fabricate and cold test full scale prototype (i.e. 2 cold masses)  Fabricate series ? ?

Final remarks  Making it all fit in mm is not yet guaranteed -> let’s optimise all we can  One should aim for a design at least as robust as existing arc cryostats, demonstrated by testing  Let’s stick to common practices as much as we can  We need only 2 units for IR2 but more may follow: industrialisation and standardisation of the design are justified from the beginning  Good designs require time for testing and re-iteration, let’s give ourselves the chance to do it by answering open questions as soon as possible! 19

20