M. Gilchriese Mechanics Labor and Disk Sectors US Pixel Meeting November 2001.

Slides:



Advertisements
Similar presentations
M. Gilchriese US ATLAS Pixel Meeting July 18-19, 2002 UC Santa Cruz.
Advertisements

Liquid H 2 Absorber Production Contents (1)MICE Absorber Status (2)MICE Absorber Modification (3)Plan/Schedule (4)Summary MICE CM-23 in HARBIN Shigeru.
Engineering Division 1 HFT Middle Support Cylinder Eric Anderssen, LBNL.
ATLAS Frame PRR 1 W.O. Miller Feb US ATLAS Pixel Detector Global Supports PRR W.O. Miller, R. Smith, W.K. Miller, R. Baer HYTEC G. Gilchriese, E.
ATLAS Pixel Detector February 2003 N. Hartman LBNL 1 Pixel Support Tube PRR: Assembly, Production, Schedule February 2003.
M. Gilchriese Evaporative Cooling Tests of Pixel Disk Sectors June 2000 E. Anderssen, M. Gilchriese, F. Goozen, F. McCormack, J. Taylor, T. Weber, J. Wirth.
Update on Be Wall Cavity Steve Virostek Lawrence Berkeley National Lab MTA RF Workshop November 15, 2010.
Stephen Milton Undulator System 20 April, 2006 LCLS Undulator System Update S. Milton, ANL FAC, April 20 th, 2006.
ATLAS Pixel Detector July 2003 ETC ‘04 E. Anderssen LBNL BPSS and Service Panels Santa Cruz, CA E Anderssen LBNL.
October 24, 2000Milestones, Funding of USCMS S&C Matthias Kasemann1 US CMS Software and Computing Milestones and Funding Profiles Matthias Kasemann Fermilab.
Engineering Division 1 Mechanical and Integration CD0 Walkthru, 19-Dec, 2007 Eric Anderssen, LBNL.
1 IBL Integration Activities & Future plans  Overall FEA on Geneva (in convergence with Seattle)  News from IST Composite Design  Integration.
July 10, 2003M. Garcia-Sciveres -- Module Assembly & Test1 WBS (& W.B.S & Services) Pixel Module Assembly & Test 1.Technical Status.
Electrical Integration WBS Eric J. Mannel Columbia University Electronics Project Engineer VTX and FVTX.
Seog Oh/ Duke University/September, 2003 TRT Workshop/ Peniscola, Spain Duke TRT Progress.
M. Gilchriese Status Report Sectors, Rings, Frame December 2002.
SLHC Pixel Layout Studies S. Dardin, M. Garcia-Sciveres, M. Gilchriese, N. Hartman LBNL November 4, 2008.
Ron Madaras, LBL U.S. Pixel Meeting, SCIPP, July 9-10, 2003 Patch Panel 1 (PP1) Brief Review Cost and Effort Estimate.
ATLAS Pixel Detector July 2001 Cooling Services Connections N. Hartman LBNL Cooling Connections Status Report October 11, 2001 N. Hartman, E. Anderssen,
DOE/NSF Review of the U.S. ATLAS Construction Project June 3-4, 2002 WBS 1.1 Silicon Subsystem Abe Seiden UC Santa Cruz.
L. Greiner 1IPHC meeting – May 7, 2012 STAR HFT Plans for the next year A short report on HFT/PXL plans for post May 2012 TPC – Time Projection Chamber.
Evaporative Heater Design, qualification and planning M.Olcese PRR SCT off-detector cooling PRR SCT off-detector cooling March March 2005.
Tariq J. Solaija, NCP Forward RPC EDR, Tariq Solaija Forward RPC EDR The Standard RPC for low  regions Tariq J. Solaija National Centre for.
ATLAS Pixel Detector Project N. Hartman LBNL 1 Alexis Smith Intern Progress Report Neal Hartman, March 25, 2003.
M. Gilchriese - November 12, 1998 Status Report on Outer Support Frame W. Miller Hytec, Inc E. Anderssen, D. Bintinger, M. Gilchriese LBNL.
Silicon Meeting July 10, 2003 Module and Stave Production Status James Fast Fermilab.
1 US Pixel Mechanics Role Global support structureIntermediate support structureLocal support structure Stave SectorDisk Barrel x (9-11) x5 x (22,40,56)
U.S. Deliverables Cost and Schedule Summary M. G. D. Gilchriese U.S. ATLAS Review Revised Version November 29, 2000.
M. Gilchriese Module Assembly and Attachment at LBNL M. Gilchriese for F. Goozen April 2000.
M. Gilchriese Overview of Production Plan for Pixel Global Support and Disk Support Rings M. G. D. Gilchriese Lawrence Berkeley National Laboratory February.
Ronald Lipton PMG June Layer 0 Status 48 modules, 96 SVX4 readout chips 6-fold symmetry 8 module types different in sensor and analog cable length.
M. Gilchriese - April 2001 Disk Sector Status. M. Gilchriese - April Technical Status Three prototypes to current dimensions(8-sector disks) except.
M. Gilchriese Sectors, Rings, Frame Assembly and Installation July 18.
ATLAS Pixel Detector February 2002 Cooling Services Connections N. Hartman LBNL Cooling Connections Status Report: LBNL Effort February, 2002 N. Hartman,
U.S. Deliverables Cost and Schedule Summary M. G. D. Gilchriese Revised Version December 18, 2000.
ATLAS PIXEL SYSTEM OVERVIEW M. Gilchriese Lawrence Berkeley National Laboratory March 11, 1999.
Nov. 8, 2001M. Garcia-Sciveres -- PP0 & Service Panels1 PP0 & Service Panels 1.Introduction 2.Technical Status 3.Goals for 2002.
November 04 Jason Tarrant CCLRC1 SCT EC Interconnects l Progress of SCT EC Interconnects »Services (Required for Disc Insertion 2004 / Integration 2005)
ATLAS Pixel Detector Cooling Connections Testing and Development: Progress Report April 26, 2001 N. Hartman, E. Anderssen, M. Gilchriese, F. Goozen, T.
M. Gilchriese U.S. Pixel Mechanics Overview M. G. D. Gilchriese Lawrence Berkeley National Laboratory April 2000.
M. Gilchriese Disk Sector Production Pixel Local Supports Production Readiness Review.
UCSC August 12, 2008 U.S. Upgrade R&D Meeting: Strip Detector  Seiden.
DOE/NSF Review of U.S. ATLAS /March 2001 WBS Pixel Overview and WBS Pixel Mechanics M. G. D. Gilchriese Lawrence Berkeley Laboratory.
ATLAS 1 Beam Pipe Support Structure (BPSS) Interface and Assembly Final Design Review, April 2003 E. Anderssen, N. Hartman LBNL.
ATLAS 1 Beam Pipe Support Structure (BPSS) Services Interface and Assembly Final Design Review, April 2003 E. Anderssen, N. Hartman, A Smith, LBNL S. Coelli,
D. Greenfield CLRC1 End-cap Engineering Status Report Debbie Greenfield, RAL UK-V 30 October 2002.
1 FVTX Detector Assembly Stephen Pate New Mexico State University (FVTX Assembly Management WBS 1.7) Stephen Pate, NMSU – FVTX Review – 16-Nov-2009.
Brenna Flaugher Sept. 24 th Lehman Review1 Run IIB Silicon Upgrade: Cost and Schedule Lehman Review Sept. 24, 2002 Brenna Flaugher Run IIB Silicon Project.
D. Greenfield CLRC1 UK-V End-cap Engineering 15 July 2003 Debbie Greenfield, RAL.
M. Gilchriese Items from Talks U.S. Pixel Meeting Santa Cruz July 2003.
M. Gilchriese Stave Prototype Status Summary July 5, 2006.
ATLAS Pixel Detector July 2003 SC Pixel Meeting N. Hartman LBNL 1 Pixel Support Tube WBS Santa Cruz Cost Workshop July 9, 2003.
M. Gilchriese Disk Sector Status E. Anderssen, M. Gilchriese, F. Goozen, N. Hartman, T. Johnson, J. Wirth October 11, 2001.
M. Gilchriese - December 2000 Disk Sector Status E. Anderssen, M. Gilchriese, F. Goozen, N. Hartman, T. Johnson, F. McCormack, J. Wirth and D. Uken Lawrence.
December 1999 Frame and Assembly Planning Status E. Anderssen, D. Bintinger, M. Gilchriese and F. Goozen LBNL W. Miller Hytec, Inc.
ATLAS Pixel Detector September 2002 N. Hartman LBNL 1 Pixel Support Tube: Cost and Production Schedule September 2002.
Walter Sondheim 6/9/20081 DOE – Review of VTX upgrade detector for PHENIX Mechanics: Walter Sondheim - LANL.
M. Gilchriese Work Plan W. Miller iTi M. Cepeda, S. Dardin, M. Gilchriese, C. Haber, R. Post LBNL February 6, 2007.
ATLAS Pixel Detector Pixel Support Tube Interfaces Pixel Support Tube PRR CERN, Geneve E. Anderssen, LBNL.
M. Gilchriese Towards Fabrication of a Mechanical Prototype Stave.
ATLAS Pixel Detector December 2001 Cooling Services Connections N. Hartman LBNL Cooling Connections Status Report: LBNL Effort December, 2001 N. Hartman,
Steinar Stapnes, LHCC June The ATLAS inner detector TRT endcap A+B TRT endcap C TRT barrel SCT barrel SCT endcap Pixels uWhole ID sits inside bore.
1 Disk Sectors Integrated support and cooling for disk modules. Each sector has 6 modules Number of sectors is 2x9+4x8=50. Fabrication of all sectors in.
USCMS Pixel PMG, Nov 29, Mechanics Status Disks, ½ Service Cylinders Installation USCMS FPIX FNAL PMG Joe Howell Bruno Gobbi Nov. 29, 2006.
M. Gilchriese - February 2001 Disk Sector Status E. Anderssen, M. Gilchriese, F. Goozen, N. Hartman, T. Johnson, F. McCormack, J. Taylor, T. Weber, J.
M. Gilchriese Upgrade Stave Mechanics(Only) Status September 16, 2006.
21 Mar 2007ALICE - Paul Dauncey1 ALICE CR07: Installation and Commissioning Paul Dauncey Material from: L. Leistam: “ALICE Status” W. Riegler: “Commissioning.
Resource Loaded Schedule and Budget Profile
Jim Fast Pacific Northwest National Laboratory
10/month is the present production rate 2 FTE + sporadic contributions
Presentation transcript:

M. Gilchriese Mechanics Labor and Disk Sectors US Pixel Meeting November 2001

M. Gilchriese 2 Pixel Mechanics - I Pixel Support Tube Global Support Frame/Pixel Mounts Disk sectors and support ring Services

M. Gilchriese 3 Service and Beampipe Support Carbon-fiber tube Glass-fiber tubes Support points and flanges Carbon-fiber tube Glass-fiber tubes Support points and flanges This slides into support tube Patch Panel 1(PP1) Pixel Mechanics - II Not shown are PP2 and contributions to overall integration, final assembly and installation.

M. Gilchriese 4 FY02 Design/Fab Team Engineers, designers, students, technical staff. Additional designer time budgeted currently for support tube,service panel, beam pipe support...

M. Gilchriese 5 Tasks in FY02 Disk sectors - in production but some tooling to be finalized, finish production by end of FY02 Complete coolant fitting design, fabricate for sectors. Disk support rings - preproduction just starting, finish production by end FY02 Global support frame - design nearly complete, PRR in Feb. ‘02, half production in FY02, remainder in FY03 Disk assembly, insertion into frame. Prototype complete, final design can wait until early FY03?. Same for dry assembly of frame elements. PST and related design - just beginning final design for some aspects, remainder still in conceptual phase. Many interfaces. PST prototypes - design for foot-long sections, heaters, thermal tests leading up to FDR in June ‘02 PST production design to follow prototype phase, including heaters Beam pipe support design by beam pipe FDR in Feb. 02 Service panel design, including prototype, in ‘02. Integrated with beam pipe support. PP1 design and possibly prototype. PP2 responsibilities moving to Europe.

M. Gilchriese FY02-03 Personnel Project Base Anderssen, Goozen Hartman Dardin, Weber, Wirth Should be 2.5 FY02 Could be 1 for FY02, but should be 1 for FY03. Johnson 80hrs FY02 and 960 in FY03 For service panel soldering to be added. Hoeferkamp? Bartolo All personnel, not just design. As posted last week. Needs some modification after input today/tomorrow. HYTEC not shown - see Bill’s talk tomorrow.

M. Gilchriese 7 Design Milestones

M. Gilchriese Disk Sectors

M. Gilchriese 9 Disks Six disks. Eight sectors per disk. Total of 48 sectors.

M. Gilchriese 10 Disk Sector Concept Carbon-carbon faceplate 0.43 mm Aluminum tube Carbon-carbon faceplate 0.43 mm Carbon foam Carbon-carbon hard points Cyanate-ester film adhesive PEEK buttons CGL-7018

M. Gilchriese 11 Disk Sector Status PRR passed in July. In (pre)production. Assembly sequence at Some production fixtures to be made Most materials in hand(carbon-carbon, tubes, foam…) Reviewed costs this week with people doing work(Wirth et al) Remaining materials(adhesives, PEEK, pins, storage,….) –As posted last week 11K –Current estimate 12K Shop time –As posted last week 501 hours –Current estimate 501 hours Labor - covered previously and remains the same as posted. Mech tech shared with other items(eg. service panel prototypes, fittings) but costed totally here for convenience. Schedule. Complete by end FY02, assuming coolant fittings in time. Baseline date was 6/25/02. Three month delay projected.

M. Gilchriese Coolant Fittings

M. Gilchriese 13 Technical Status Summary Custom fittings for sectors - capillary inlet, U-tube(2 sectors operated in series) and outlet. Similar for staves. Connection at PP0, also custom fitting. Connection at PP1. Possibly commercial. US developments(see samples) –Variseal(plastic seals) - recently stopped –Al Luer-lok(syringe-like) - looks good, extensive test protocol for few prototypes to be complete in next week. Remaining issue - radiation length –Laser welding of aluminum fittings to aluminum sector tube samples demonstrated successfully on few parts. Remaining issues are welding on bent tubes(in progress) and yield(need more parts). Only one vendor successful so far. European developments –Cu-Ni part with Indium seal - looks good. Remaining issues are long term creep(under test), handling thin In(currently 200microns but will try In plated Cu) and making in aluminum(in progress). In general this has gone much more slowly than expected, now critical path item for sector construction. Schedule is very tight. Uncertainty about luer-lok vs Indium.

M. Gilchriese 14 Fittings Plan/Costs This is preliminary. Developing quickly. Prototypes/test samples and preproduction( ) –Basic assumption is $250 per connection pair to cover fittings and laser welding in prototype phase(will be much less in production). –Prototypes/test samples 20 pairs=5K –Preproduction sectors 8x2=16+4spares=20 pairs = 5K –Bend fixture for U-tube. $1000 for materials. 25 hours shop time –Tech labor covered by base program or part of sector fabrication. –Total prototype( ). $11K materials, 25 hours shop, 0.5 FTE base program tech labor. All in FY02. –Estimate posted last week had 26K materials, 80 hours shop and 520 hours project tech labor…so this will go down substantially Production( ) –For now have kept original estimate done by Neal Hartman –This assumes we do all of tubes and fittings beyond those directly on staves. This may not be so, could do some of the fitting fab in Europe but joining should be done here since tubes are integrated into service panels. –Total is about 35K, should be moved into FY02. Meeting this schedule will be very difficult.

M. Gilchriese 15 Potential Cost Reductions Design –Shift engineering design funding(0.5 FTE? In FY02 and FY03) for beam pipe support to outside pixel budget. –Reduce LBL designer time in FY02, delay production design of some items eg. service panels and PP1 until FY03, until have some experience with real electronics. Support patch panel design effort internally(Goozen) instead at lower level. Concentrate on support tube and beam pipe support in FY02 then switch partly to service panels, PP1. –Reduce/eliminate UNM EE time for PP1 and cable plant in FY02 and FY03. Design requires anyway frequent coordination with mechanical effort at LBL. –Reduce production engineering oversight for rings and frame from HYTEC. Would require more effort from LBNL physicists to save $. Sectors and Fittings –Not much. Tom Johnson to SCT work if fittings don’t arrive fast enough? Go fast.