Bali Dream Gde Putra Paean Lee Lilith Shoemaker Loida Vasquez Sustainability, Buildings, and the Built Environment Spring 2014
Design Team Gde Putra ~ Sketchup Artist Visionary Lilith Shoemaker ~ Water & Waste Specialist Loida Vasquez ~ Solar Energy Master Paean Lee ~ Napkin Drawing Inspiration
Mission Environmental ~ Natural Building Social ~ Vastu Principles Financial ~ Cost Benefit Self Sustaining LEED (Leadership in Energy and Environmental Design) Guidelines Family of 4
Map & Climate
Top View 34 ft. 50 ft. 14 ft.
Front View Candi Bentar ~ Tower Gate
Southeast View Shading Trees Longan
West View Family Pavillion
North View Solar Panels
Northwest View Upper Ventilation Windows
Roof Design Create Maximum Circulation Hot Air
Inner North Wall Ventilation Cool Air
Inner Walls Entrance Meditation Room Kitchen Dining Room Master Bedroom Living Room Children’s Bedroom Office Space Courtyard Vastu Room Placements
Inner Entrance Bamboo Partition
$7000 $2300 $0 $1000 $3000 $50 $500 $2200 Adobe Walls Clay Roof Tiles Stone Foundation Authentic Wood Windows Parquet Wood Flooring Bamboo Entrance Wood Solar Pavillion Man power Building Materials Total: $16050 = $13.88 per ft 2
Water Logic
Water holding Options Purchased Cistern: $23,000 Site-made Fiber reinforced concrete: $ Labor
Water Storage Cistern Pump Pressure Tank PEX System (manifold) 50 gal Water Tank Submersible Pump Septic Garden Outlet Toilet Outlet Kitchen Shower & Sink Laundry
Off-Grid ish Solar Power System
kWh/m^2/day Denpasar, Indonesia JanFebMarAprilMayJune JulyAugSepOctNovDev Solar Irradiance
kWh per month needed 2. Chose lowest productive month kWh X 31 days = 150 kWh/month kWh/150 kWh (per panel) = 6.66 panels or 7 panels 5. Increase to 8 panels for good measure Solar Panel Array
If each panel outputs 250 watts, then… 250w X 8 panels = 2000 total watts If we choose a 24 V charge controller, then… 2000w/24V = or 90 amps 100 amp charge controller needed Charge Controller
1000 kWh/30 days = 33 kWh X 3 = 99 kWh 99 kWh = 99,000 wh 99,000wh/24V = 4,125 AH We need (4) 24V, 1100 AH forklift batteries Battery Bank 3 day back-up
Hourly Watt Usage Peek Hour Wattage Use
The maximum load at any given time is 3,500 watts An inverter has a 95% efficiency Therefore, 3,700 watts must be fed into the inverter in order for a 3,500-w output because 3,500/.95 = 3,685-w (2) 2,500 watt inverters = 5,000 watts DC to AC Inverter
8 (250-w) solar $1.50/watt = $3,000 1 (100 A) charge controller = $300 4 (1,100 AH) forklift batteries = $ 14,000 2 (2,500-w) Inverters = $3,000 Accessories (cables) = $ 4,000 Total Estimated Cost = $24,300 (40yr payoff) Estimated Cost Grid-Tied = $10,000 (17yr payoff) Estimated Expense
Cost Analysis ItemBali DreamConventional Building$16,050$40,000 Solar$24,300 ($10,000)$0 Water$3,000 (23,000)$0 Total $43,350$40,000 Yearly Water$0$120 Yearly Electricity$0$600 ROI5 years
“Naturalness is the basis of effectiveness.” ~ Maharishi Mahesh Yogi Thank you!