1 Incident Summary A fatal incident occurred at the Amin (Nimr) Steam Pilot project site on Thursday 20th September, 2012 at an approximate time of 14:10.

Slides:



Advertisements
Similar presentations
Safety Absolutes Green Lake
Advertisements

Working Around/Under Loads
HSSE Policy Z Contractor HSSE Induction V2. HSSE Policy Z Contractor HSSE Induction V2.
Crane Operations Objective
Safe Job Analysis The objective of this procedure is to prevent accidents by operating a systematic procedure for: Identification of hazards associated.
Crane Safety, Subpart N
Crane and Hoist Training
Cranes, Hoists and Truck Hoists
1 Cranes Module 13. 2Objectives After this module you should be able to – identify the most common crane hazards – take the necessary steps to avoid those.
Safety : Cranes Introduction to Industrial Technology Spring 2014 Mr. Shubert 1.
Energy Supporting Energy 1 1 DROPS Forum 12 th April 2011 Ron Martin Corporate HSE Advisor.
1. 2 Safety work-stoppage PDO & its contractors have suffered THREE high potential incidents involving cold cutting in the last TWO months.
SHE Code 4: Safety and Safe Use of Work Equipment
Contractor Crane Topple Incident PRELIMINARY: INVESTIGATION ONGOING.
Scissor Lift Safety Training Working Safely on Scissor Lifts 29 CFR OSHA Scaffolding Safety Requirements.
Lifting Operations & Lifting Equipment. LOLER 98  Lifting Equipment must be of adequate strength & stability, as must the load itself  Lifting equipment.
Safety Induction to the Lift & Escalator Industry
MNM Fatal Falling Material Accident Falling Material Accident April 21, 2009 (Tennessee) April 21, 2009 (Tennessee) Sand & Gravel Operation Sand.
Safety Talk 21 / 1 Safety Talk 21 Cranes and their Safe Operation.
Electricity kills and injures people. Around 1000 electrical accidents at work are reported to HSE each year and about 25 people die of their injuries.
Gasunie is one of the biggest gas infrastructure companies in Europe. Within the company, we give safety the highest priority; it forms the basis of our.
Lifting Operations and Lifting Equipment Regulations (LOLER) 1998
SHE Requirements Clarification Meeting Date:17 November 2014 Compiled: Nompumelelo Kaule.
Always start a vehicle correctly
Working Around/Under Loads
Who is Responsible for Overhead Crane and Hoist Operations
Always use the correct lifting equipment
PDO Second Alert What happened:
PDO Safety Advice What happened?
PDO Second Alert What happened? Your learning from this incident..
Lifting & Rigging Continuing Education Fourth Quarter 2016
2.8 Mtr Belt Mtr Rope = 7.3 Mtr Broken
Injury: Fall from height
Comply with Safe Operating Procedures
Never place yourself in line of fire
2.8 Mtr Belt Mtr Rope = 7.3 Mtr Broken
Click anywhere to get started…
Safety is part of our culture at Halliburton
Do not work at height without fall protection
Always use the right means of access for working at heights jobs
LIFTING & HOISTING ENGAGEMENT PACK
Follow Management of Change for an activity which is not in permit
PDO Safety Advice Date: 11/08/2015 Injury: Amputated fingers
Always use the correct tools for the job
Always follow Night driving rules
Follow the rules to save a life
Check & avoid potential Pinch points
PDO Safety Advice What happened? Your learning from this incident..
LTI: Finger Crush Injury Hands off suspend loads “Use Tagline”
Always stay out of the line of fire
PDO Second Alert Date: Incident title: Fatality What happened?
If in doubt – stop the job
Safety Critical Devices can Save the Lives & Protect Asset
Crane operating with boom lowered and under Supervision
Ensure safety devices are working prior to starting work
Always keep your hands away from crush points (Line of Fire)
PDO Second Alert Date: Incident title: HiPo What happened?
PDO Second Alert Date: Incident title: MVI Rollover
Be aware of potential pinch points
Use only certified lifting equipment in good condition
PDO Safety Advice Date: 23/08/2015 Injury: Fractured fingers
Always keep your equipment maintained
PDO Second Alert What happened? Your learning from this incident..
Use the correct lifting device for the load
Keep away from “Line of Fire”
Only perform tasks under your responsibility
In the line of fire Disclaimer: this safety moment is designed to prevent similar incidents occurring. All guidance herein is provided in good faith and.
Cranes and Hoists Standard 29 CFR Part
Always position the crane boom correctly before slinging the casing
Apply 3 point contact while ascending/ descending for proper stability
Presentation transcript:

1 Incident Summary A fatal incident occurred at the Amin (Nimr) Steam Pilot project site on Thursday 20th September, 2012 at an approximate time of 14:10 hrs. The deceased is a 32 year old Indian helper working for Al Turki Enterprises (ATE), a PDO contractor. An ATE mechanical crew was using a 25 ton crane to lift pipe sleeves. During the lifting operation, the deceased went to fetch slings from the crane’s tool box located above the cranes battery. The contents of the box cannot be accessed from ground level so he stood on the outrigger and reached over. In doing so he placed himself in the arc path taken by the cranes counter weight which as it rotated, crushed the deceased against the toolbox. He immediately fell unconscious and was brought to STS camp clinic in Amal. The doctor gave him CPR but could not revive him and at 15:15 hrs he was declared dead. Fatal Crane Incident at Amin (Nimr) Steam Pilot Project 20/09/2012, FIM #

2 Events leading to the Incident There was no ‘Person In Charge’ or banksman controlling the crane operations There were Concurrent Operations leading to conflicting tasks in the area. 2 mechanical crews working on two separate PTWs in the same area The deceased walked into and within the cordoned off area. There were non adherences to the PTW requirements and deviations from the Lifting Operations Standards and Procedures (PR 1709): lifting plan was not followed; hazards were not reassessed when there was a change at the work site; crew members changed from one crew to another.

Learnings from Incident (LFI) 1.Ensure there is a proper lifting plan in place and it is followed at all times; 2.Ensure HEMP has been carried out; 3.Ensure the “Ten Questions For A Safe Lift” have been discussed and properly cascaded during the toolbox talk; (slide 6) 4.Ensure risks of concurrent operations are assessed and mitigated; 5.Ensure lifting operation personnel are competent and qualified; 6.Ensure a Person is In Charge (can be the Banksman) and wears a high visibility vest; 7. Never access a crane when it is either operating or about to operate; 8. Use steps to access heights, not an outrigger; 9. Always be aware of events around you and expect the unexpected; 10. Barricade the area and ensure only authorized personnel enter; 11. Crane drivers and banksman (signaller) must visually check all around the crane before operating. PDO Emergency Safety Advice for all crane operators Not complying with crane Operating Procedures and Standards can kill

Banksman / Signaler: The only person, who co-ordinates the lifting movements and maintains radio- and/or visual communication with crane operator and persons close to the load. Slinger / Rigger: The person, who inspects the rigging, selects rigging to suit the load, installs the equipment and connects/disconnects the load. Person in charge of the lifting (PIC) The person, who co-ordinates and controls all aspects of lifting operations on site. (The PIC and Banksman may be the same person). Responsibilities

To ensure continual improvement all Contract Managers are to review their HSE HEMP against the questions asked below: Confirm the following: Do you employ a competent PDO compliant banksmen used for all lifting operations? Do you employ trained and competent crane operators? Do you create and use lifting plans for all lifting operations? Do you adequately supervise lifting operations? Do you regularly audit your lifting operations to assure compliance? Do you have an effective maintenance and inspection schedule to keep the windows/mirrors clean and alarms working? Do your cranes have warning labeling to warn the unsuspecting of hazardous areas? Do you conduct relevant TBTs to staff involved in lifting operations? Have you conducted risk assessments of lifting operations and ensured the required controls are implemented and maintained? Have you created and introduced effective Job Safety Plans for lifting operations. Management Learnings

Ten Questions For A Safe Lift 1. Is everyone aware of and fully understands the lifting and hoisting procedures applicable to the lift? 2. Has everyone attended the toolbox talk? 3. Has a pre-use inspection of the Lifting Equipment been carried out and are the Lifting Accessories tagged or marked with: - Safe Working Load (SWL) - A unique identification number - A valid certification date 4. Are all safety devices working? 5. Does everyone know the Person-in-Charge of the lift? 6. Is everyone competent and aware of his or her tasks? 7. Is there a current Lift Plan and JHA and does everybody understand the job and precautions? 8. Does everyone know the environmental limits (e.g. maximum permissible wind speed) for the lift? 9. Is the lift area controlled and is everyone clear if the load falls or swings? 10. Are signaling methods and communication agreed and clear to you?

LSR 7 Never walk under a suspended load Every “routine” lift must have a generic lifting plan. Every “non-routine” lift must have specific lifting plan. Person In Charge shall ensure lift area is cordoned off during the lifting operations. No one should ever be under any working crane or suspended load.

Person In Charge (Banksman / Signaler)

9 Incident Details Contractor Name: ATE Incident Owner : OSD Time, Date, Place: hrs, 20th Sep at Amin ‘A’ Street Persons involved in the Incident: Mr. Jakhu Naran Maheshwari (ATE Emp. No ), Age – 32 working as a helper in ATE since 2009 Vehicles / equipment involved in the Incident: TE – 285, 25 Tons Mobile crane, Make Kato, NK 250EV, Year of manufacture – 2001 Injuries:1 Fatality Actual Severity Rating: Level 4 Potential Severity: Yellow Fatal Crane Incident at Amin (Nimr) Steam Pilot Project 20/09/2012, FIM #