CTIO: DECam Installation, Commissioning, & Operations Oct 2011 1 DES Collab Meeting Philadelphia R. Chris Smith CTIO/NOAO.

Slides:



Advertisements
Similar presentations
WIYN Planning Meeting, February 28, 2013 Wisconsin, Indiana Yale, NOAO 0.9m Half Degree Imager – First Light.
Advertisements

DECam Community Pipeline Review Closeout Presentation DES Council of Directors’ Review August 30-31, 2010 NCSA, Urbana IL.
Magellan Associate Director Report Personnel Observing Statistics Telescope Operations.
System-wide issues Before we get to the telescope System integration and verification at the telescope Operations Maintenance and support.
Darcy Bibb Oceanit Mentor: Tony Bartnicki Advisor: Curt Leonard Home Institution: Maui Community College Integration of a Small Telescope System for Space.
Moblas 8 Return to Operations 16 th International Laser Ranging Instrumentation Workshop Poznan, Poland October 16, 2008 Scott Wetzel, Howard Donovan,
Week 7 ASR plus a little CHANGE & INNOVATION
The KPNO 4m “Mayall” Telescope Arjun Dey (NOAO). National Optical Astronomy Observatory Mission: provide the best ground-based astronomical capabilities.
PreCam: Lessons Learned, version 0 Kyler Kuehn
Commissioning the NOAO Data Management System Howard H. Lanning, Rob Seaman, Chris Smith (National Optical Astronomy Observatory, Data Products Program)
Magellan f/5 Planning and Status Andrew Szentgyorgyi Magellan SAC Meeting Pasadena/17 Mar 2012.
Implementing 2007 NRC Portals of the Universe Report Chandra X-ray Center 25 April 2012 Implementing Portals of the Universe, April
Hunt for Molecules, Paris, 2005-Sep-20 Software Development for ALMA Robert LUCAS IRAM Grenoble France.
Mark Bowen Acting Theme Leader – Technologies for Radio Astronomy CSIRO Astronomy and Space Science 14 October 2010 Australia Telescope Users Committee.
ALMA Operations and the North American ALMA Science Center Al Wootten NRAO.
August 2 and 3, 2010 Project Cost, Schedule, Risk and Contingency Jay Elias.
Tim Abbott DECam & CTIO. Tim Abbott DECam & CTIO DECam will greatly expand and extend wide field imaging capability at CTIO.
Telescope Integration and Tests Tuesday Afternoon.
Dark Energy Probes with DES (focus on cosmology) Seokcheon Lee (KIAS) Feb Section : Survey Science III.
Magellan F/5 System Status A.Szentgyorgyi / Ann Arbor 25 Sept 2005.
John Peoples for the DES Collaboration BIRP Review August 12, 2004 Tucson1 DES Management  Survey Organization  Survey Deliverables  Proposed funding.
PDS Geosciences Node Page 1 Archiving Mars Mission Data Sets with the Planetary Data System Report to MEPAG Edward A. Guinness Dept. of Earth and Planetary.
Topics Covered Phase 1: Preliminary investigation Phase 1: Preliminary investigation Phase 2: Feasibility Study Phase 2: Feasibility Study Phase 3: System.
CTIO and the Dark Energy Camera Prepared for the CD-1 Director’s Review Tuesday, July 25, 2006 Fermilab Alistair R. Walker.
SSC SI Data Processing Pipeline Plans Tom Stephens USRA Information Systems Development Manager SSSC Meeting – Sept 29, 2009.
Dark Energy Survey (DES) (Presenter: Douglas Tucker) DES is observing (Aug. 15 th – Feb. 15 th ) Year 2 Operations Collaboration Meeting in Sussex, UK,
3.1.1 Optics, Optical Corrector, Mechanical Systems M. Johns, C. Claver.
What the Data Products Program Offers Users Todd Boroson Dick Shaw Presentation to NOAO Users Committee October 23, 2003.
1 The DES Calibrations Effort Douglas L. Tucker (DES Calibrations Scientist) DES NSF/DOE Review, 8-9 June 2009 The DES Calibrations Effort has connections.
Ray Plante for the DES Collaboration BIRP Meeting August 12, 2004 Tucson Fermilab, U Illinois, U Chicago, LBNL, CTIO/NOAO DES Data Management Ray Plante.
1 DECam in Chile Intro to Dark Energy Survey & DECam Project Status of arrivals in Chile Instrument checkout in Chile Schedule for first light.
Tim Abbott DECam & CTIO. Tim Abbott DECam & CTIO: CTIO’s preparations Active Optics –33-pad system, LUT driven, updated every.
N. RadziwillEVLA Advisory Committee Meeting May 8-9, 2006 NRAO End to End (e2e) Operations Division Nicole M. Radziwill.
Tim Abbott DECam & CTIO. Tim Abbott DECam & CTIO DECam will greatly expand and extend wide field imaging capability at CTIO.
Mountaintop Software for the Dark Energy Camera Jon Thaler 1, T. Abbott 2, I. Karliner 1, T. Qian 1, K. Honscheid 3, W. Merritt 4, L. Buckley-Geer 4 1.
WFC3 SMOV Report for TIPS 16 July 2009 John MacKenty This presentation contains material that is embargoed until after the SM4 ERO press conference. Images/spectra.
Frazer OwenNSF EVLA Mid-Project Review May 11-12, Transition to EVLA
Brenna Flaugher, PMG, April 6, 2007 DECam Funding Need Profile (Dec 06) (then yr $, Overhead included) This gave a technically driven schedule resulting.
CHARA Collaboration Year-Five Science Review 2008 Nightly Reports and Remote Observations By ~ PJ Sallave - Goldfinger.
Mu2e Mu2e Remote Handling Review Comparisons: Costs, Risks & Maintainability Ryan Schultz Deputy L3 Manager Target Station 3/3/2015.
Tim Abbott & Brenna Flaugher, CTIO Integration Meeting 1 The DECam Project Closeout, Action Items Hexapod Optical Lenses CCD Readout Filters Shutter 2008.
Conventional Facilities integration: Approach and Issues Daniel Piso Fernández WP Leader (WP13 Conventional Facilities Integration Support) November 5,
Software Design and Development Development Methodoligies Computing Science.
1 DEPLOYMENT AND OPERATIONS MODULE 23 ECM SPECIALIST COURSE 1 Copyright AIIM.
Alistair Walker - DECam Instrument Scientist Tim Abbott – Blanco Telescope Scientist CTIO/NOAO DES Collaboration Meeting Oct The Blanco Telescope.
1 Progress for July 19, 2011 Preparations for Fill. –4 protection valves were attached: 2 on Z-shaped tubes, 2 on the tank –Herman’s new CTIO engineering.
F/8 Repair and recommissioning status and near term forward look Ron Probst, Roberto Tighe 06 Nov 2012.
DECam in Overview Alistair Walker Version 3 December Ver 4 Updates Jan
Commissioning Alistair Walker NOAO/CTIO 9/30/ DES Collaboration Meeting October
Updates on projects 472, 470, 443, 462, 442, 471, 480, 483, 484 Tim Abbott Changes since 9 July are in blue.
The Blanco Environmental Control System Alistair R. Walker November
LSST Commissioning Overview and Data Plan Charles (Chuck) Claver Beth Willman LSST System Scientist LSST Deputy Director SAC Meeting.
Blanco Telescope and DECam Alistair Walker ACTR meeting 22 March 2013
Technical resources schedule
CTIO Weather Station renewal
Telescope Assembly, Integration and Verification (AIV) WBS 04C. 14 J
Blanco F/8 Status AURA Observatory Council, Tucson, 3/2013.
Blanco Environmental Control System
E450AJ BOOMLIFT for DECAM Tasks
LSST Commissioning Overview and Data Plan Charles (Chuck) Claver Beth Willman LSST System Scientist LSST Deputy Director SAC Meeting.
Alistair Walker Version 3 December
CTIO Weather Station renewal
ETS For ACTR 9the April 2015 R.Tighe april 2011 april /04/2015
DECam Filter/Shutter Installation and Filters Installation
COSMOS Status David Sprayberry, Sean Points & Jay Elias
Blanco Telescope and DECam Alistair Walker ACTR meeting 22 March ver 2
DOE: Transition from MIE to Early Operations Kevin Reil LSST Camera Commissioning Lead LSST Commissioning Plan Review January 24-26, 2017.
Management Breakout: MREFC Budget Summary Victor L
LGS Project Meeting December 21, 2006 Agenda SWIFT update - A. Bouchez
Polarized 3He target installation
Presentation transcript:

CTIO: DECam Installation, Commissioning, & Operations Oct DES Collab Meeting Philadelphia R. Chris Smith CTIO/NOAO

Contents 1.STATUS 2.INSTALLATION 3.COMMISSIONING 4.OPERATIONS Oct 2011 DES Collab Meeting Philadelphia 2

Status – Facility Improvements Blanco primary radial supports –No breakages after 2 years, & x10 improvement in movement Primary mirror successfully realuminzed Oct 2011 DES Collab Meeting Philadelphia 3

Re-Aluminization of M1 DES Collab Meeting Philadelphia 4 Post-shutdown measurements very close to nominal value of pure Al ! Oct 2011

Console room upgrade: Before DES Collab Meeting Philadelphia 5 Oct 2011

Console room upgrade: After DES Collab Meeting Philadelphia 6 After Oct 2011

ALSO: Computer Room Before After Oct 2011 DES Collab Meeting Philadelphia 7

Cooling Plant Oct 2011 DES Collab Meeting Philadelphia 8 New 40 Ton Chiller installed –Was 30 Ton+10 Ton, now 40 Ton+30 Ton –Gives headroom for future dome cooling project Glycol contaminant –Pulled out leaking part –Removed oil from system

DECam Cooling System Design and implementation Oct 2011 DES Collab Meeting Philadelphia 9

DECal System: New White Spot New white spot (left) installed in dome Illumination system pending shipping from TAMU Oct 2011 DES Collab Meeting Philadelphia 10

G-floor Prep G-floor = DECam cage & optics prep area –New crane installed for cage and optics assembly Oct 2011 DES Collab Meeting Philadelphia 11

G-floor Prep G-floor = DECam cage & optics prep area –Next step: Clean(ish) work tent for optics integration Oct 2011 DES Collab Meeting Philadelphia 12

Facility Improvements Blanco UPS and generator improvements Telescope Control System –Basic Performance Demonstrated; issues identified with tuning –Software tests in Sep/Oct/Nov –Impact of extra weight of DECam+Counterweight under re-evaluation Oct 2011 DES Collab Meeting Philadelphia 13

Blanco Improvements Instrument Maintenance Facility (ex Coudé room) on telescope Main Floor Clean Room in use, with added humidity Oct 2011 DES Collab Meeting Philadelphia 14

Community Workshop Highly successful workshop –42 attendees from many institutions –Talks online –Purpose: provide information on capabilities of DECam & how community can use DES data –Program: informational talks, invited plenary science talks, short project talks, and breakout sessions –Organizing Cmte: D.James (chair), Walker, Allen, Norman, & Weintraub Oct 2011 DES Collab Meeting Philadelphia 15

CTIO Director’s Installation Reviews Integration & Installation review = April 2011 –External committee charged to review procedures & safety of integration & installation Installation & Safety review = Oct 2011 –Revisit installation procedures, recommendations of I&I review, and in particular look at safety to personnel & instrument Oct 2011 DES Collab Meeting Philadelphia 16

Installation Phases Phase 1: Pre-Shutdown (Oct – Jan): –Work on cooling systems –Work on imager –Fabrication of counterweight components, platforms, & cart –Assembly of Cage & Optics Phase 2: Shutdown (Jan – Apr) –Telescope disassembly –Top-end Change –Telescope reassembly & tuning Phase 3: Post-Shutdown/Commissioning (Apr – Aug) –Re-commission telescope (tuning, f/8) –Install imager –Commission imager Oct 2011 DES Collab Meeting Philadelphia 17

Shutdown – gross phases Remove f/8 cell and stow Install platform mounts & plates Telescope to zenith Measure current telescope alignment Remove & stow primary mirror Remove old cage Install new cage (cage, hexapod, corrector) Reinstall primary mirror Preliminary optical alignment Rebalance telescope Tune TCS Check out f/8 → Image quality checks with SBIG cameras?? Install remaining DECam components at NW station → Commissioning DES Collab Meeting Philadelphia 18 Oct 2011

Shutdown part 1/3 Telescope disassembly Jan 2012 Work day: 08:30 – 16:30, 1hr for lunch, 5 day week. The usual shutdown crew Throughout the shutdown: –Foreman –Beginning of day/shift meetings –End of day/shift meetings –Short report distrib by after every end of day/shift meeting. NamePosition Gale BrehmerHead TelOps Jorge BrionesMountain mechanic Eduardo AguirreMountain mechanic (Pachon) Gerardo GomezMountain mechanic (Pachon) Dario GuajardoMountain mechanic Esteban ParkesElectronico (jefe) Javier RojasElectronico David RojasElectronico Andrés MontaneMechanical engineer Freddy MuñozMechanical engineer Patricio SchurterMechanical engineer Fabian CollaoMechanic (ETS, jefe) Victor RobledoMechanic (ETS) Victor PintoMechanic (ETS) Juan OrregoMechanic (ETS) Cristian DiazMechanic (ETS) Roberto TigheOptical Engineer

Shutdown part 2/3 Top end change 23 Jan – 7 Feb –Additional telescope staff from Tucson coming down to help speed things up Two shifts: 1.08:30 – 16:30, 1 hr for lunch. 2.14:30 – 22:30, 1 hr for lunch. → 14 hour day, 2 hour overlap between shifts. Two shifts: Team Gringo & Team Chileno –4 on top ring, 1 on lower platform, 1 crane operator –Also: lookout, foreman, safety engineer.

Shutdown part 3/3 Telescope reassembly & shakedown 8 Feb – 16 April, 08:30 – 16:30, 1 hr for lunch, 5 day week. Dress telescope (run feeds) Reinstall M1 & align Install modified Cass cage Rebalance telescope Tune servos Verify f/8 handling Team: –As part 1, plus… –4 Arizonans, 4 for “Dress telescope” –TCS support for tuning

22 Commissioning Strategy Phase 1 - F/8 mirror optical alignment and test Phase 2 – DECam optical corrector tests using the SBIG cameras Then there is a month of installation and checking out of DECam and other cage contents Phase 3 – Full DECam System tests, on the sky Science Verification - JULY/AUGUST 2012 Observations - SEPTEMBER 2012 Oct 2011 DES Collab Meeting Philadelphia

Commissioning Schedule NoPhaseActivityTime (w)Elapsed (m) 1ONEF/8 commissioning ObservingObserve F/810.5Contingency 3TWOOptics tests - SBIGs ObservingObserve with F/821.25Contingency 5InstallationInstall Imager InstallationFunctional tests THREEDECam Tests (A) ObservingObserve with F/823.25Contingency 9THREEDECam Tests (B) ObservingF/814.00Contingency 11ObservingScience Verification24.6 Oct 2011 DES Collab Meeting Philadelphia 23

Science Verification Community science verification time –How it works Two several night programs from experienced teams, selected by special TAC Chosen for both science impact and for exercising the equipment The teams sign up for rapid data reduction and publication Proprietary time set to zero to encourage this! –Why? Allows community to access real DECam data early, to help them plan their own programs This model was successful with NEWFIRM DES verification time –Do a mini-survey using DES protocols 24 Oct 2011 DES Collab Meeting Philadelphia

Schedule Caveats Shutdown depends on –Optics delivery & alignment verification –Counterweight design and implementation –TCS tuning tests and plans f/8 observing = contingency –Plan to schedule any community observations flexibly, via remote or service observing, so that we can adapt to schedule changes –Additional contingency needed for TCS tuning Sub-optimal season = weather –May need additional time due to change in commissioning season –June/July/August is worst weather for Cerro Tololo The SV time will actually be scheduled as science verification / engineering. The following engineering blocks will be written as engineering / science verification. –SV includes both Community & DES time for testing Survey commencement also depends on Community Pipeline deliverable Oct 2011 DES Collab Meeting Philadelphia 25

DECam+DES Operations DES Scheduling –DES commitment: 105 nights/yr for 5 years Baseline is Sep-Dec, occupying ~70% of time, plus Jan/Feb half nights Result: about 1 week/month for community time in Sep-Dec –Bottom line: “A” semesters almost normal community use, “B” = DES, limited community time Oct 2011 DES Collab Meeting Philadelphia 26

The Beginning 27 Oct 2011 DES Collab Meeting Philadelphia

Backup slides On Commissioning From Alistair’s talk in Portsmouth Pending updates in current round of revisions Oct 2011 DES Collab Meeting Philadelphia 28

Pre-Commissioning All components tested and ready for end-end system tests Pre-Requisites for Phase 1 –PF cage installed & aligned –F/8 ready Pre-Requisites for Phase 2 –Hexapod functioning correctly –SBIG system ready Pre-Requisites for Phase 3 –All utilities installed and working –DECam passed functional tests –Data system ready Oct 2011 DES Collab Meeting Philadelphia 29

Phase 1 F/8 Verify correct operation of F/8 focus and tilt mechanisms Analyze optical performance with IMAN, make sky map Remove and re-install F/8, check all still OK Use the CTIO IR Imager (ISPI) for imaging tests Oct 2011 DES Collab Meeting Philadelphia 30

Phase 2: DECam Optics At Zenith –Focus at center of CCD –Evaluate and correct for tilt using radial cameras –Evaluate image symmetry, adjust x-y –Evaluate image quality Over Sky –Evaluate image quality over sky, built approximate LUT for top-end deflections –Focus stability –Image ghosts –Test our understanding of the effects of misalignment and defocus Oct 2011 DES Collab Meeting Philadelphia 31

Pre-Phase 3: DECam Installation Cabling, LN2 system, install if not already done, check DECam install Functional tests of DECam and its data system SISPI and all interfaces working, alarms work Air systems OK Initial reliability tests Install (and remove) filter, then install all filters Oct 2011 DES Collab Meeting Philadelphia 32

Phase 3: DECam Imager Commissioning Phase 3A –Monitoring & exercising activities –Daytime calibrations and CCD tests (some are every day, others less often) –Telescope & TCS tests – pointing, tracking –Focus – map, in-and-out, sky position, filter, temperature –Donut, Bcams, alignment –Autofocus –Crosstalk, ghosts, scattered light –Guiding –Calibrations – dome flats, star field flats, sky flats –Photometry, astrometry –Reliability, efficiency, user interface, tool evaluation Oct 2011 DES Collab Meeting Philadelphia 33

Phase 3 DECam Commissioning Phase 3B –Community protocols qualification - test DECam performance and reliability and the ability of the Community Pipeline to reduce the data. Deep dithered field. Long exposures, high background Low galactic latitude field, multiple filters Variable star density – e.g. large globular cluster or resolved nearby galaxy Establish optimal dither patterns etc –DES protocol qualification – Test DECam performance and reliability and the ability of the DESDM pipeline to reduce the data Test also analysis codes on real DES-like data Test ObsTac Test QuickReduce in the DES context etc Oct 2011 DES Collab Meeting Philadelphia 34

Staffing I CTIO instrument support scientists and technical staff will be trained, procedures will be developed and/or optimized. Operation and first-response support will pass from the DECam Project to CTIO. Technical backup from the DECam Project team will be very important, especially in the first year of operation. Both DES Collaboration and NOAO scientists & engineers will participate in commissioning – the scientists will be drawn from those with technical expertise relating to DECam, and/or astronomical experience Scientists –NOAO DECam Instrument Scientist heads up commissioning (1) –On-duty scientists, one will be Chief ( ~5-6 people, ~3 on night shift) –Work a day shift, a swing shift, or a night shift depending on tasks –Pipeline scientists – Tucson, NCSA (a few) –Analysis scientists – especially the DES science teams (many) Schedule – no more than 7 nights on… Oct 2011 DES Collab Meeting Philadelphia 35

Staffing II Engineering/technical support - CTIO –Telescope Operator (1) –Blanco Observer Support (1) –TELOPS staff (lead Gale Brehmer) – mechanical support (2) daytime, electronic support (2) swing shift on call –ETS staff (lead Tim Abbott) support for commissioning – 8-9 people covering all the technical specialties and who have been involved with the DECam Project. They are based in La Serena, on mountain when appropriate. Engineering/technical support leads – DECam –Vacuum/cryogenics H. Cease –Electronics T. Shaw, S. Chappa –Software K. Honsched, A. Elliott, L. Buckley-Geer –CCDs J. Estrada –Instrument integration T. Diehl –The final commissioning roster will be iterated given the experience of integration and installation. Oct 2011 DES Collab Meeting Philadelphia 36

Communications Daily meeting –Update engineering and analysis activities relevant for the short term –Prepare revised plan for the coming night –Review any changes to the longer range plan –Update any requirements met/missed Ad hoc meetings, using videocon, IP phone, Skype WWW tools to foster rapid dissemination of results SISPI provides logbook, image header information, alarms Oct 2011 DES Collab Meeting Philadelphia 37