ARCON/RAMSES: Current Status and Operational Risk D. Forkel-Wirth, G. Segura Milan, D. Perrin, S. Roesler; H. and Hz. Vincke, P. Vojtyla, M. Widorski (DGS,

Slides:



Advertisements
Similar presentations
SESAME Radiation Safety and PSS Phase I : Microtron + Booster Morteza Mansouri on behalf of Safety group TAC SESAME TAC 2013 : Morteza Mansouri.
Advertisements

André Augustinus 15 March 2003 DCS Workshop Safety Interlocks.
EDMS November th LHC Radiation Day RAMSES Induced Activity Monitors 5 th LHC Radiation Day CERN - 29 November 2005 RAMSES Induced Activity.
Radiation Protection aspects of the Switch-Yard operation V. Donate, G. Dumont, Joachim Vollaire on behalf of DGS-RP.
André Augustinus 16 June 2003 DCS Workshop Safety.
Commissioning the access system M. Gruwé Machine checkout workshop November 8 th 2007.
RAMSES & ARCON Radiation Monitoring for the Environment and Safety Basics and Overview M. Widorski, DGS/RP EDMS
LHC UPS Systems and Configurations: Changes during the LS1 V. Chareyre / EN-EL LHC Beam Operation Committee 11 February 2014 EDMS No /02/2014.
RAMSES Project Technical AspectsDPerrin RSOC September 17, 2003 RAMSES Project Status report - Technical aspects RAMSES Project Status report - Technical.
13 Oct 2005 ICALEPCS RAMSES: The LHC RAdiation Monitoring System for the Environment and Safety G. Segura CERN on behalf of the RAMSES team.
Information about system status Piquet backup call Supervision of fire alarm systems Control room backup Computer support for HCI’s/terminals Confirmation.
ST Technical Committee 15th October LHC Ventilation Control System migration D. Blanc ST-CV.
Luisa Ulrici and Luca Bruno, on behalf of DGS/RP
Tomasz Ladzinski GS/ASE. LASS Annual Maintenance & Tests General Principles Each winter shutdown preventive maintenance of EIS takes place. It is followed.
ATC/ABOC Days 21-23/1/2008 Heinz Vincke for SC-RP 1.
Remote manipulations / diagnostics in radioactive areas and handling of radioactive material Workshop, Geneva, Switzerland 6 th May 2013 THE REPLACEMENT.
Christophe Delamare EDMS Accelerator Consolidation Workshop GS/ASE activities.
CV activities on LHC complex during the long shutdown Serge Deleval Thanks to M. Nonis, Y. Body, G. Peon, S. Moccia, M. Obrecht Chamonix 2011.
An automated diagnostic system to streamline DSM project maintenance Johan du Plessis 15 August 2012.
Radiation Protection LS1 - Collaboration with CERN Technical Groups - Lessons learnt Stephane Bally (CERN), Sandro Di Vincenzo (CERN) Indico
Consolidation of access systems for the injector Complex ATOP days 4-6 March 2009 P. Ninin & R, Nunes in behalf of the PS and SPS access project teams…
Joint ILC/CLIC Safety document ► Incentive for this document:  Share effort to define a coherent safety protocol for future linear colliders.  Insure.
CERN Safety Alarm Monitoring Presented by Luigi Scibile ST division / MO group.
André Augustinus 16 September 2002 Safety issues.
Workshop on the Use of Ethernet as a Fieldbus CERN, 28 September 2001 Use of Ethernet in the control systems of the cooling and ventilation infrastructure.
RAMSES PROGRAMME F. SZONCSO CERN – DGS/DI 31 st March 2014 CERN – GREECE INDUSTRY day1.
LHC Access System August 2006 LHC Access System – Status and Planning August 2006 Elena Manola-Poggioli Eva Sanchez-Corral TS-CSE on behalf of the LHC.
MG - IEFC meeting 22/01/20101 Linac 3 shielding S. Gilardoni, M. Giovannozzi, S. Baird, R. Brown, S. Damjanovic, T. Otto, M. Widorski, Acknowledgements:
CLIC Implementation Studies Ph. Lebrun & J. Osborne CERN CLIC Collaboration Meeting addressing the Work Packages CERN, 3-4 November 2011.
Christophe Mugnier, on behalf AB/PO Group ATC-ABOC days, 23 January 2008 AB/PO equipment review and Stand-by service description for the power converter.
Access zones and Training Steve Hutchins BE-ASR IEFC workshop 7/3/2012.
1 1. Some recent views ( ) 2 Linac tunnel
ST/MAforLHC April 2003Sixth ST workshop1 Summary of ST/MA deliverables for LHC Luigi Scibile for the ST/MA group.
2 IMPACT - THE FIRE PERMIT = Hot Work Permit 3 Welcome ! This course is linked to the use of IMPACT, so it is assumed that: You know how to use IMPACT.
Review of the operation scenarios and required manning of the activities P. Schnizer and L. Serio.
ST Workshop 1 April 2003P. Vojtyla - TIS/IE1/10 Interaction of TIS and ST in Environmental Matters P. Vojtyla TIS – Integrated Safety and Environment.
 Overview of the run 2009 for CV  Major improvements in Water treatment - Demineralised water production - Cooling control  Major concerns for.
First radiological estimates for the HIRADMAT project H. Vincke and N. Conan 1.
Radiation Protection aspects for SHIP Doris Forkel-Wirth, Stefan Roesler, Helmut Vincke, Heinz Vincke CERN Radiation Protection Group 1 st SHIP workshop,
Review of the operation scenarios and required manning of the activities P. Schnizer and L. Serio.
Radiation Protection info update C. Adorisio (DGS/RP) 17 th LTEX Meeting
Session 2 of ATC/ABOC Days 2008 Doris Forkel-Wirth, SC-RP Pierre Bonnal, AB-SU 1.
Overview of the main events related to TS equipment during 2007 Definition Number and category of the events Events and measures taken for each machine.
Risk Analysis P. Cennini AB-ATB on behalf of the n_TOF Team  Procedure  Documents in preparation  Conclusions Second n_TOF External Panel Review, CERN,
EDMS Session 2 - Operation at high intensity of the CERN machines ATC/ABOC 21 January ARCON – RAMSES Bridge ATC/ABOC Days CERN – 21 to 23.
EUROnu Costing Workshop May 2011 Beta-Beam Costing Exercise Elena Wildner, CERN 25/05/11 1 EUROnu Costing Workshop, CERN May 2011.
AB/CO Review, Interlock team, 20 th September Interlock team – the AB/CO point of view M.Zerlauth, R.Harrison Powering Interlocks A common task.
1 Radiation Monitoring at CTF3 CTF3 Buildings – weak spots Radiation Monitoring system Monitoring results – First Lessons Idelette Floret, Thomas Otto,
SAFETY SERVICES PROVISION I. Bejar Alonso. Transfer Executive Safety Tasks from SC to Departments In application of the document “Safety policy at CERN”
CERN Jan 2006 Specific safety Issues for 2006 compared to 2004 P. Cennini AB Safety Requirement in case the Installation activities are going on.
Beam Instrumentation during LS1 Ray Veness on behalf of the BE/BI group.
EDMS July 2004 LHCb Experiment Area Meeting RAMSES at LHC point 8 LHCb Experiment Area Meeting 21 July 2004 RAMSES at LHC point 8 LHCb Experiment.
Proton-Driven Plasma Wakefield Acceleration CERN Project Structure Edda Gschwendtner, CERN Lisbon Meeting, 22 June 2012Edda Gschwendtner, CERN2.
Agenda 1 BOSS Meeting - 27/5/ : :10 Introduction and aims of the workshop 10‘ 09: :25 Priorities from OP for PSB and transfer lines 15'
External Data and DIP Oliver Holme 18 th January 2008.
Mu2e Mu2e Remote Handling Review Comparisons: Costs, Risks & Maintainability Ryan Schultz Deputy L3 Manager Target Station 3/3/2015.
MI Shielding Machine Protection Credit D. Capista March 7,2010.
CV works in the non- LHC accelerator complex during 2008 and plans for 2009 ATOP days 2009.
LIU-PSB Working Group meeting: 25/06/2015, Markus Zerlauth Consolidation of magnet interlocks in the PS complex – Warm magnet Interlock System (WIC) R.Mompo,
GIF++ implementation Adrian Fabich, Sylvain Girod, EN-MEF-LE Technical meeting with Supplier of Irradiator, 3 rd October 2013.
LS1 Day: The Injectors S. Baird EN/MEF Thanks to R Brown, N Gilbert, D McFarlane & V Chohan, IEFC workshop…. LS1 Day: The Injectors 1.
Artificial Intelligence In Power System Author Doshi Pratik H.Darakh Bharat P.
LS2 Safety Preparation Thomas Otto, LS2 Safety Support Officer for LHC
HEL – Safety aspects Christelle Gaignant
1v0.
Renovation of the 45-year old PS magnets
MERIT Review Meeting Cryogenics BNL, NY Dec. 12, 2005 Friedrich Haug
Experimental Areas – LS2 planning
Radiation Protection Handbook
Critical design review #1 for medium beta cavity cryomodules 3-4 APRIL SAFETY AND RAMI INPUTS - Franck Peauger OLIVIER KUSTER (INSTALLATION AND.
Presentation transcript:

ARCON/RAMSES: Current Status and Operational Risk D. Forkel-Wirth, G. Segura Milan, D. Perrin, S. Roesler; H. and Hz. Vincke, P. Vojtyla, M. Widorski (DGS, Safety Commission) Chamonix 27 th January

Table of Content Legal background Instrumentation Alarms, interlocks and their transmission RAMSES ▫ Reliability and availability ▫ Maintenance ▫ Operational risks ARCON ▫ ARCON versus RAMSES ▫ Interim solutions ▫ Operational risks RAMSES2light 22

Legal Background CERN has the legal obligation to protect the public and the persons working on site from any unjustified exposure to ionizing radiation. -> monitoring of ▫ ambient dose equivalent rates (in- and outside of CERN perimeter) ▫ releases of radioactivity by air, gases and effluents allows preventive assessment of radiological risks and the optimization of individual and collective doses -> fixed installed radiation monitoring systems: ▫ ARCON (Area Controller, since 1988 – LEP era, CERN in-house development) ▫ RAMSES (Radiation Monitoring System for Environment and Safety, since 2007 – LHC era, industry standard based technology) (in total ~ 800 monitors, data acquisition and storage, alarms and interlocks) 33

ARCON/RAMSES at CERN 4 LHC: RAMSES CTF3: RAMSES CNGS: RAMSES ARCON: LHC injectors ISOLDE, n-TOF, AD, Experimental areas

Monitors for Protection of Environment ARCON and RAMSES use the same/similar type of monitors 55 Wind Monitoring USA VGM - VAS Ventilation Monitoring RWM - RWS Water Monitoring station EPIC ERC Stray radiation Monitoring

Operational Radiation Protection Monitors ARCON and RAMSES use the same/similar type of monitors 66 REM counter Gas filled, high pressure ionization chamber Air filled ionisation chamber Beam-on: to protect workers in areas adjacent to accelerator tunnels and experiments against prompt radiation (mainly neutrons, E < some GeV) Alarm function Beam-off: to protect workers during maintenance and repair against radiation fields caused by decay of radionuclides (mainly gammas, E < 2.7 MeV) No alarm function

Operational Radiation Protection Monitors Special monitors 77 Hand&Foot monitor Site Gate Monitor Radiation Alarm Unit (RAMSES) Monitoring station SGM already prepared for connection to access system RAMSES: reading of radiation levels directly available ≠ ARCON

Alarm Levels for Designated Areas 88 not applicable Beam-On: accessible areas are shielded towards beam areas -> classification as Supervised Radiation Area or Simple Controlled Radiation Area is sufficient Monitors in designated areas (accessible during beam on): uniform alarm and interlock levels Radiation measurement: typical sampling time: s  extrapolation to 3600 s  above limit: alarm

Alarm Philosophy Two different philosophies: Either beam interlock on alarms or operator action following an audible/visual signal. Interlocks are preferred above operator action by RP. Choice is mainly made due to required and available reliability level and weighted according impact on machine operation. Transmission of radiation protection alarms PS complex: Radiation Alarm Repeater Panels –> visual and audible alarm to operators, no ARCON interlock on LINAC, Booster of PS beam, RAMSES interlocks in operation at CTF3, action OP and RP SPS complex: LASER system -> ARCON interlock on SPS beam, action OP and RP LHC: LASER system + visual and audible alarm (to be implemented), no RAMSES interlock on LHC beam (with exception of RF commissioning), Action OP and RP 99

Alarm Philosophy Transmission of alarms from site gate monitors: alarms to be transferred to TCR via RAMSES and ARCON; action OP and RP Transmission of environmental alarms (pH and temperature) to TCR; action IE, OP and CV No transmission of radiological environmental “alarms=action level”*) to other systems than ARCON or RAMSES; action IE and RP No technical alarms of RAMSES or ARCON are transmitted to TCR**) for the time being (for historical reasons) *) DGS-IE + BFSP: environmental radiation monitoring does not require alarm function **) with exception of pH and temperature  10

RAMSES Radiation Monitoring System for the Environment and Safety  Designed to cover all CERN installations  2002: RAMSES limited to LHC due to budget restrictions  Presently monitoring system for LHC, CNGS and CTF3  Developed, installed and maintained by an industrial contractor  State-of-the-art integrated decentralised monitoring system, designed to fulfil SIL 2 level for the basic monitoring, alarming and interlock functions.  Standard system for new projects (LINAC4); or extension of existing installations (HiRadMat)

RAMSES Reliability and Availability Compliant to applicable international standards for radiation protection instrumentation (ISO) IEC closely used as reference - Functional safety lifecycle - Project Management Plan - Hazard Analysis - Safety Integrity Levels assigned to safety functions Decentralised radiation monitoring system Each detector-alarm unit operates autonomously, back-up with batteries, unit continues to operate even if rest of the RAMSES system fails Safety integrity level (SIL) 2 for radiation alarms and interlocks

RAMSES Maintenance Preventive maintenance: Systematic, regular control of operational reliability for each single equipment item (every 2 weeks to once a year) Performed by contractor and DGS-RP, DGS-IE 2009: Hardware and software updates have been implemented in Annual maintenance completed Corrective maintenance (TCR not yet involved): During working hours: performed by 1 st intervention line (DGS/RP-IL) During non-working hours: RP on-call service and DGS/RP-IL on a best effort basis Contractor Hot Line (24H/24H, 7d/7d) Contractor 8 – 48 hours to solve problem on site

RAMSES - Operational Risk RAMSES statistics: 3 false alarms in 2009 (1 hardware failure at LHC-3, 2 at CTF3 – cured by replacement of faulty equipment) No false interlock signal in 2009 in LHC 99 %* data availability in database (* Present checking limit) Areas are sufficiently well covered with monitor stations, provisions are made to increase redundancy even more

RAMSES data : i.e. LHC restart in 2009 RAMSES ready for CNGS 2006 and LHC 2008

ARCON CERN development in the 80’s for LEP VME Bus (CPU 68040) OS9 (Operating system) MIL1553 (field bus) / Ethernet TCP/IP Up to 64 counting inputs (current pulses) Still about 380 channels on ARCON To be phased out and replaced by RAMSES system:  ARCON-RAMSES interface (to replace HPSLZ18 server)  RAMSES2light (RAMSES for injectors)  RAMSES2 (RAMSES for rest of CERN facilities, i.e. ISOLDE, n-TOF, AD and experimental halls)

ARCON versus RAMSES  17 ARCONRAMSES Developed80 th for LEP2000 th for LHC StandardCERN standardIndustrial standard SIL< SILSIL2 for alarms and interlocks Size~ 380 monitors~ 400 monitors Detectors SystemGrouped (several monitors on one ARCON station) Autonomously operating monitors, grouped into smaller entities Worst risk in case of failure - RP Several channels fail in case of ARCON failure -> whole area without radiation monitoring Single channel fails -> radiation monitoring ensured by remaining channels Supervision / Software partHP server, proprietary software no longer supported PCview SCADA solution, OPC client/server technology same type of detectors – different electronics

Interim Solution for ARCON  18 ARCONInterim Solution SIL< SIL Size~ 380 monitorsMaintains all existing ARCON channels DetectorsDetectors (spares missing)Spare detectors available to some extent or may be taken from experimental areas – in case of need SystemGrouped (several monitors on one ARCON station) ARCON remains operating surveillance system Worst risk in case of failure - RP Several channels fail in case of ARCON failure -> whole area without radiation monitoring Electronic spare parts (from LEP) are tested and operational in case of need Supervision / Software part HP server, in-house developed software ARCON-RAMSES bridge (eliminates HP server and proprietary software)

Interim Solution for ARCON  ARCON-RAMSES Interface (to replace MIL 1553, HPSLZ18 Server) Interface completed, Supervision part completed,  Final reception of the RAMSES based supervision system for all ARCON was scheduled for end 2009  1 st quarter 2010 due to a technical problem identified with OPC server software.  Back-up for LHC injector chain ARCON: Electronic spare parts are tested and available Spare detectors still critical  To be taken from experimental areas (according to a predefined list), new spare detectors will be bought within the RAMSES II light project Improved reliability of ARCON network link  ARCON network star points are secured by UPS Improved battery and power supply surveillance  Installed on all ARCON  19

ARCON-RAMSES Interface Completion 1 st quarter 2010 Moniteurs provenant zones autres All connected by the existing CERN TCP/IP infrastructure (Etherne t).

Operational Risk - ARCON  21 Problem of supervision server (outdated system (HP server) to communicate with continuously up-dated modern software systems (Operation) for data and alarm transmission – to be cured by ARCON RAMSES bridge Failure of an entire ARCON system will result in the loss of radiation monitoring for a whole area -> beam stop and replacement of ARCON Monitor failures -> spare monitors to be installed (worst case: from experimental areas ) Final solution: RAMSES2light RAMSES2 Worst case scenarios: 1) faulty ARCON equipment – similar to a broken magnet, septa or power supply -> beam stop Replacement of an entire ARCON: 1- 3 days 2) ARCON software (for equipment control): Difficult to maintain, common weak point to all ARCONs

Operational Risk - ARCON  22  Basic guideline defined in SR16 (Safety Rule 16, BE/OP)  Specific action and information for PS Complex available to operators on:  Specific action and information for SPS Complex defined in technical note EDMS To be added to OP shut-down lectures – see FOM 19/1/2010

 23 Operational Risk - ARCON PS complex number of monitors to be increased -> consolidation

 24 Operational Risk - ARCON SPS complex PAXTA40: (monitor in SPS interlock system) Function: stray radiation monitor to protect personnel in the ECA4 cavern at floor level during SPS operation. Procedure to be followed in case of failure or unavailability of monitor:  SPS operation to be stopped  Inform RP on the monitor problem (phone: or 74848).  ECA4 floor to be cleared and closed.  If not possible to block access to floor level of ECA4 only, the whole ECA4 area to be cleared and closed at the surface.  Operation may continue – after clearance by DSO, RSO and RP (beam permit sheet? ) Example (EDMS ) – RP part only, DSO actions to be included SPS complex: underground installation –> less impact of ARCON failures when compared to PS complex

RAMSES 2 Light Project Replacement and consolidation of ARCON by RAMSES for the entire LHC injector chain Project passed Finance Committee in March 2009 (extension of existing RAMSES contract) Project includes ARCON replacement, consolidation, new projects (LINAC4, HiRadMat) and spares Contract amendment and related order signed in December 2009 (after having solved EMC problems) Two phase project – depends on accessibility of areas during accelerators operation: Commissioning and acceptance tests of instrumentation in accessible areas  October 2010 Full commissioning and acceptance tests by the end of shutdown period

Conclusion RAMSES (LHC) has proven to be reliable (SIL2 level) Provisions had been made to increase RAMSES redundancy even more Actions had been taken to secure injectors for LHC run 2010 ARCON (injectors) to be replaced by RAMSES2light latest until end of shut-down 2010/11 RAMSES2light replaces and consolidates existing monitoring system at the LHC injectors Technical alarms from RAMSES and ARCON to be transferred to TCR Radiation alarms from site gate monitors to be transferred to TCR  26