Overview of LCLS-II Cryomodule Plans

Slides:



Advertisements
Similar presentations
SRF Cryomodule Assembly Facility Plans Tug Arkan AAC, May 10-12, 2005.
Advertisements

ANL HWR Cryomodule Status Update 27 January 2015 Zachary Conway On behalf of the ANL Linac Development Group Argonne National Laboratory Physics Division.
LCLS-II Cryomodules Production Plans at Fermilab
RF Unit Test Facility at NML & CM1 Test Plan Bob Kephart Fermilab IWLC-10 October 20, 2010.
SRF_BizPlan_31Oct2010_Rev_14 Production Preparations at JLAB JLab SRF Team EDMS – PLM DESY TeamCenter Meeting at SLAC 31 MAR 2014.
ORNL is managed by UT-Battelle for the US Department of Energy Commissioning and Operation of the Horizontal Test Apparatus at SNS Presented at: CEC/ICMC.
Alignment and assembling of the cryomodule Yun He, James Sears, Matthias Liepe MLC external review October 03, 2012.
Dr. Michael Peiniger Superconducting RF activities at RI Research Instruments with a focus on EXFEL cavity production.
An SRF Single Cavity Horizontal Test Facility Tom Peterson, Fermilab May 10, 2005.
ILCTA_NML Progress at Fermilab Jerry Leibfritz September 10, 2007.
R&D Status and Plan on The Cryostat N. Ohuchi, K. Tsuchiya, A. Terashima, H. Hisamatsu, M. Masuzawa, T. Okamura, H. Hayano 1.STF-Cryostat Design 2.Construction.
ESS cavities interfaces
SCU Layout Concept - Minimal Segmentation Joel Fuerst (ANL) SCU 3-Lab Review Meeting Dec. 16, 2014.
Internal Cryomodule Instrumentation ERL Main Linac Cryomodule 10/10/2015 Peter Quigley, MLC Design Review.
IHEP 1.3 GHz Cryomodule and Cryogenics IHEP Cryogenic group 2nd Workshop of the IHEP 1.3 GHz SRF R&D Project Dec 2 nd, 2009.
SCU Segmented Cryostat Concept M. Leitner, S. Prestemon, D. Arbelaez, S. Myers September 2 nd, 2014.
FNAL Cavities for S1 Global Jim Kerby ALCPG 09. FNAL Deliverables Discussed in meetings 15/16 July and 10/11 Sept, and Webex and s 9/30/20092FNAL.
Detail discussion of S1 Global at STF H. Hayano (KEK) GDE Mar 3-6, 2008.
Type IV Cryomodule Proposal (T4CM) Don Mitchell, 16 JAN 2006.
Cryomodule Development at Fermilab Don Mitchell Representing the SRF engineering community at Fermilab April 20, 2009 Tsukuba, Japan TILC09.
Americas Region: T4CM Status and Plans H. Carter TD SRF Dev. Dept. July 14, 2006.
Harry Carter – LCFOA Meeting 5/1/06 1 LCFOA Technical Briefings: Cryomodules H. Carter Fermilab Technical Division.
Americas Main Linac Cavity and Cryomodule WBS X.9 Resource Proposal.
Date 2007/Oct./23 FNAL-GDE-Meeting Global Design Effort 1 Cryomodule Interface Definition (FNAL-GDE-Meeting) N. Ohuchi.
Project X RD&D Plan Cryogenics Arkadiy Klebaner AAC Meeting February 3, 2009.
FNAL efforts on LHC Crab Cavity R&D (Proposals for R&D sub-tasks, resources and schedule) Nikolay Solyak.
An Overview of the ILC Cryogenic System Tom Peterson, Fermilab LCFOA at SLAC 1 May 2006.
Accelerator/ Medium Beta Cavities Paolo Michelato INFN Milano - LASA April 21, 2015.
Shrikant_Pattalwar TTC 2015 Dec 1, 2015 SLAC 1 Horizontal Tests in a Vertical Cryostat Shrikant Pattalwar STFC Daresbury Laboratory UK.
Alignment and assembling of the cryomodule Yun He, James Sears, Matthias Liepe.
Detail plan of S1-Global H. Hayano (KEK),
Date 2007/Sept./12-14 EDR kick-off-meeting Global Design Effort 1 Cryomodule Interface definition N. Ohuchi.
SPL cryomodule specification meeting, CERN 19th October 2010 SPL cryomodule specification: Goals of the meeting SPL cryomodule specification: Goals of.
FNAL Cryomodule Assembly and Installation Plans Tug Arkan LCLS-II Production Cryomodule Final Design Review May 12-14, 2015.
NML - RF Unit Test Facility Jerry Leibfritz Fermilab.
PIP-II Cryogenics Arkadiy Klebaner and Jay Theilacker PIP-II Collaboration Meeting 9 November 2015.
LCLS-II Cryomodules Production at Fermilab Tug Arkan, 7/17/2014.
Cryomodule Assembly Facility (CAF) at Fermilab Tug Arkan (FNAL) FNAL-LBNL joint meeting on SRF Cavities and Cryomodules March 15, 2012.
LCLS-II Prototype Cryomodule Vacuum Vessel and HGRP Tom Peterson 4 December 2014 Design Review.
26 April, 2016 LCLS II Cryomodules and Cryoplant, Joe Preble LCLS-II Overview JLAB Organization for LCLS-II JLAB responsibilities & Schedule and Status.
CW Cryomodules for Project X Yuriy Orlov, Tom Nicol, and Tom Peterson Cryomodules for Project X, 14 June 2013Page 1.
Ralf Eichhorn CLASSE, Cornell University. I will not talk about: Cavities (Nick and Sam did this) HOM absorbers (did that yesterday) Power couplers (see.
FNAL Cryomodule Assembly and Installation Plans Tug Arkan May 22, 2015.
Jefferson Lab Cryomodule Cost and Optimization. Based Jlab energy upgrade Cryomodule design and produced to increase the energy gain of CEBAF to 12 GeV.
SRF Collaboration Shekhar Mishra Fermilab. Overview Charge: Does the laboratory make effective use of collaboration and existing SRF capabilities at other.
LCLS-II Cryomodule Design
Development of Cryo-Module Test Stand (CMTS) for Fermi Lab (R.L.Suthar, Head,CDM, BARC) Cryo-Module Test stand (CMTS) is a very sophisticated equipment.
Cryomodule Interconnect Installation Issues A Comparison of XFEL to LCLSII Karen Fant 7/29/2015.
Cryomodule Safety Approvals Jay Theilacker LCLS-II Production Cryomodule Final Design Review May 12-14, 2015.
JLAB Cryomodule Assembly Facilities Visit Report Tug Arkan, Yuriy Orlov March 26, 2012.
ESS Cryomodule Status Meeting – Introduction | | Christine Darve Introduction to Cryomodules for the ESS 2013 January, 9 th Christine Darve.
Prototype Cryomodule FDR Ken Premo 21 – 22 January 2015 High Power Coupler Design.
LCLS-II Technical Requirements
RF Systems and Controls for the LERF CM Tests
LCLS-II For LCLS-II Cryomodule Testing at JLab
CERN – Zanon discussions
Field Emission Minimization for LCLS-II
Cryomodule test stand at ESS site
WP5 Elliptical cavities
LERF as Cryomodule Testing Facility Set-Up and Installation Logistics
FRIB Cryogenic Support
at STFC Daresbury laboratory
Evolving an ILC focused SCRF Facility from the XFEL Infrastructure
IHEP Cryomodule Status
SNS PPU Cryomodule Instrumentation
Cryomodule Assembly Plan
Cryomodules Challenges for PERLE
SNS PPU Cryomodule Instrumentation
SNS PPU Cryomodule Design Overview
SNS PPU CRYOMODULE PDR Cleanroom Assembly Katherine Wilson
Presentation transcript:

Overview of LCLS-II Cryomodule Plans E. Daly for LCLS-II Cryomodule Collaboration AWLC Meeting 14 May 2014

Acknowledgements Special Thanks – T. Peterson, T. Arkan, A. McEwen, G. Neil JLab, FNAL and SLAC colleagues XFEL Project Team at DESY & CEA/Saclay E. Daly, AWLC, 14MAY2014

Outline Overview of LCLS-II Collaboration Design Highlights Prototypes Production Strategy CM Production Preparations Summary E. Daly, AWLC, 14MAY2014

LCLS-II Project Collaboration 50% of cryomodules: 1.3 GHz Cryomodules: 3.9 GHz Cryomodule engineering/design Helium distribution Cryoplant selection/design Processing for high-Q LLRF design Undulators e- gun & associated injector systems Undulator Vacuum Chamber Also supports FNAL w/ SCRF cleaning facility Undulator R&D: vertical polarization R&D planning, prototype support processing for high-Q e- gun option E. Daly, AWLC, 14MAY2014

Cryomodules for LCLS-II (CDR) Cryomodule (CM) Parameters value Cavity operating temperature (K) 2 Number of 9-cell cavities per cryomodule (1.3 GHz) 8 Total installed cryomodules (1.3 GHz) 35 Number of 3.9-GHz cavities per 3.9 GHz CM 4 ( 8, TBC) Total installed 3.9 GHz cryomodules 3 ( 2, TBC) Number of installed 1.3 GHz cryomodules in L0 1 Number installed 1.3 GHz cryomodules in L1 Number of installed 3.9-GHz cryomodules as linearizer Number of installed cryomodules in L2 12 Number of installed cryomodules in L3 20 Courtesy of T. Peterson, SRF Weekly Mtg, DEC 2013 E. Daly, AWLC, 14MAY2014

Cryomodule Collaboration Fermilab is leading the cryomodule design effort Extensive experience with TESLA-style CM design and assembly Basis is 3-D model & drawings of similar Type-IV CM Jefferson Lab and Cornell are partners in design review, costing, and production Cornell and JLab both have valuable CW CM design experience Jefferson Lab sharing half the 1.3 GHz production Recent 12 GeV Upgrade production experience Argonne Lab is also participating in cryostat design Beginning with system flow analyses and pipe size verification Experienced SRF and cryogenic personnel at ANL may be available for other collaborative tasks Courtesy of T. Peterson, SRF Weekly Mtg, DEC 2013 E. Daly, AWLC, 14MAY2014

1.3 GHz CM Modifications for LCLS-II Design Specification – Qo > 2.7 x 10 10 @ 16 MV/m, < 100 W per CM at 2K High Qo Team has intense focus (see A. Grasselino’s AWLC May 2014 talk) Design Points - TESLA Type 3+, XFEL, and Type 4 CM designs Modifications for CW heat loads Larger chimney pipe from helium vessel to 2-phase pipe Larger 2-phase pipe (4 inch OD) Closed-ended 2-phase pipe Separate 2 K liquid levels in each cryomodule 2 K JT valve on each cryomodule End lever tuner and helium vessel design for minimal df/dP Details in Y. Pischalnikov’s AWLC May 2014 talk Double-layer inner magnetic shield SC Magnet – splits in half for installation outside cleanroom Two cool-down ports in each helium vessel for uniform cool-down of bimetal joints No 5 K thermal shield But retain 5 K intercepts on input coupler Input coupler for ~10 kW CW Details in N. Solyak’s AWLC May 2014 talk Courtesy of T. Peterson, SRF Weekly Mtg, DEC 2013 E. Daly, AWLC, 14MAY2014

LCLS-II CM Schematic Courtesy of T. Peterson Note : Slope of 2-phase helium in pipe due to tunnel slope (6 cm over 13 m), need single connection to 300 mm pipe Courtesy of T. Peterson E. Daly, AWLC, 14MAY2014

Prototype 1.3 GHz CM Description Each lab produces a prototype CM Main Objectives for Prototypes Establish working collaboration for production with Jlab – each lab produces a prototype cryomodule, then provides production cryomodules Demonstrate CW operation of 8 high-Q cavities in a cryomodule Prototype cryomodule planned for use in LCLS-II New cryostat design and procurement with Type 3+ spacing Use existing cavities in prototype CMs Incorporate High-Q0 surface process development in a logical way Peripherals New He vessel Slight modifications to HOM coupler End-lever tuner RF power couplers, modify TTF couplers or procure new ones (more later) Do these developments once – the primary cryomodule design effort Courtesy of T. Peterson, SRF Weekly Mtg, DEC 2013 E. Daly, AWLC, 14MAY2014

LCLS-II Prototype Cryomodule Courtesy of T. Peterson, SRF Weekly Mtg, DEC 2013 8 cavities (End Tuner) + 1 “Splittable” SC Quad, 6 Current Leads ~50A -JT Valve -Splittable Quad -BPM -Gate Valve E. Daly, AWLC, 14MAY2014

Strategy – One Design, Two Production Lines Designs for Prototype and Production CMs (aim to satisfy PR and CM FRS) Identical Prototypes - utilize as much existing hardware as possible to reduce schedule risk and reduce overall cost while achieving the same performance as the production CMs Identical Production Designs - utilize as much of the DESY/XFEL design as practically possible to reduce schedule risk and reduce overall cost FNAL produces 16 CMs; JLab produces 17 CMs Identical Parts Received at Partner Labs Well-developed drawing packages, clear requirements and specifications Concurrent reviews within LCLS-II project Procurement activities – lead technical contacts at Jlab/FNAL/SLAC work together during all phases Identical Tooling Interfaces Interfaces between CM hardware and tooling are identical Avoid adding custom features to CM Adapt non-CM hardware interfaces to Lab-specific tooling Equivalent Processes yielding Equivalent Performance Recognize that some tools are different at each lab (e.g. HPR, vertical testing systems, vacuum leak checking equipment, etc.) Monitor key process variables in consistent fashion (e.g. samples to verify etch rates) E. Daly, AWLC, 14MAY2014

Leveraging XFEL’s Existing CM Experience XFEL Production - Four cavities per test stand Tunnel construction is underway Production of CMs is currently ramping up! Start operations in April 2017, see http://www.xfel.eu/project/construction_milestones/ CM ready for testing (can test 3 CMs at once) E. Daly, AWLC, 14MAY2014

Opportunity to Learn from CEA Colleagues Production of CMs is currently ramping up! E. Daly, AWLC, 14MAY2014

Leveraging FNAL’s ILC-style CM Production Development Cavity String Assembly Insertion of Cold Mass into Cryostat Assembly Cryomodule Ready for Transport On-site Cold Mass Assembly Courtesy of T. Arkan, FNAL E. Daly, AWLC, 14MAY2014

LCLS-II Cavity/Cryomodule Process at JLab Supplier Partners JLAB SRF Facility Cavity String Assembly & Leak Test Assemble Cavity String -Class 100 Clean Room Cavity /Helium Vessel Prep. & Test VTA RF Test in liquid Helium @ 2 K Cryomodule Test in “Test Cave” Cryomodule integrity @ 2 K Tuners - Range, Hysteresis, & Resolution/ Sensitivity Cavities for Gradient & Dynamic Heat Load Qo Cryomodule Assembly Instrumentation & Wiring Tuners, MLI– Multi Layer Insulation, Cryogenic Circuits , magnetic shielding, alignment Super Insulation Cabling & Shield Vacuum Vessel & Final Alignment Install Cryogenic Supply Interfaces Horizontal Test Preparation Pressure Test & Leak Check (vacuum) Receiving in SRF Inventory Mechanical Inspection CMM Cryomodule shipping to SLAC JLAB support for installation of first 3 Cryomodule Courtesy Chi-Chang Kao, SLAC Component FNAL JLAB SLAC Niobium X   Cavities HOM/FP Feed through Cavity Flanges - VTA Testing Cavity Flanges - HTB Testing Helium Vessels FPC- Fundamental Power Couplers x Cavity String Bellows Cavity String Hardware Magnet BPM- Beam Position Monitors, HOM Absorber Gate Valve 2-Phase Pipe Bellows End Lever Tuner Magnetic Shielding GRHP Sub-assembly Gas Return Header Pipe, Cryostat, Intercept, Thermal Shield, Multi-layer Insulation etc. Vacuum Vessel Instrumentation Interconnect Parts Shipping Frames / End Caps X = Lead Laboratory (as of 20Mar2014) Courtesy of A. McEwen, JLab Commissioning at SLAC Install Cryomodules in Accelerator, cool to 2 K Weld & certify leak tight , pressure test check Controls, Gradient & Dynamic Heat Load - Qo LCLS-II 1.3 GHz Cryomodule LCLS-II 1.3 GHz Dressed Cavity, Doped and Ready for VTA Testing E. Daly, AWLC, 14MAY2014 Contract# DE-AC05-06OR23177

SRF Facilities at JLab Start Ship E. Daly, AWLC, 14MAY2014

CM Production Preparations Adapt existing infrastructure and facilities to accommodate LCLS-II components, sub-assemblies, final assembly and testing Define processes required for component handling, assembly and testing Develop test plans – key activities are cavity qualification from vendors and cryomodule acceptance testing Employ SRF QA Tools used for 12 GeV 100 MV CW cryomodules (aka C100) production and SNS production E. Daly, AWLC, 14MAY2014

Infrastructure, Tooling & Facilities (JLab) Vertical Testing of Bare/Dressed Cavities Planned rate - 4 cavities per week Cavity String, Cold Mass and CM Assembly Tools Planned rate – 1 CM per month Horizontal Testing Bench – supports Qo R&D and production efforts Planned rate ~ 1 cavity per CM Cryomodule Testing Facility (CMTF) Planned rate – 1 CM per ~ 6 weeks E. Daly, AWLC, 14MAY2014

Cavity String Assembly in Clean Room (JLab) “Lollipop” supports for each cavity TBD for SC magnet and bpm Use mobile rail system rather than rail-in-floor used at DESY, CEA/Saclay and FNAL Transfer to CM assembly rails for cold mass assembly E. Daly, AWLC, 14MAY2014

JLab CMTF : Production “Bottleneck” HPRF system suitable for individual cavity testing or 8 cavities in short duration steady state TBD system for testing SC magnet Magnetic shielding encloses testing volume reducing external fields to ~50 mG Cryogenic capacity for testing individual cavities in CW mode End Caps – specific for LCLS-II CM testing Interface to CM piping and existing junction box using u-tubes E. Daly, AWLC, 14MAY2014

Facilities Improvements : Testing in CMTF End Cans Connects CM to CTF valve box via u-tubes Interfaces for valves, LL and diodes to monitor and control helium flow/inventory Provides reliefs for primary circuit, shield circuit and insulating vacuum space HPRF Procure 1.3 GHz 10 kW Solid-State Amplifiers (SSAs) & Circulators Modify Waveguide and Interlocks Run line power to SSA/Circulators Provide controls in CMTF Control Room LLRF RF Instrumentation (arc detectors, IR sensors, etc.) Software development Cryogenic Test Facility (CTF) Increase return side piping to reduce overall pressure drop from CMTF Improve recovery system (pumping, compression) to provide base pressure of 0.031 atm (23 torr) in the CM helium bath E. Daly, AWLC, 14MAY2014

Summary Goal for production of CMs at Jlab/FNAL is “identical design, identical parts, equivalent processes to yield equivalent performance” Infrastructure development supports this goal Overall Plan for Cryomodule Design & Production R&D / Design Modifications Complete FY14 Infrastructure / Tooling FY14/15 Prototype CMs (2 units) FY15 Start of Production 1.3 GHz CMs (33 units) FY16 Rates of 1 CM per 6 – 8 weeks in current plans Start of Installation at SLAC FY17 E. Daly, AWLC, 14MAY2014

Back Up Slides E. Daly, AWLC, 14MAY2014

Facilities Improvements: Assembly Tools (JLab) Main Cavity Tools Clean room tooling - small fixtures for coupler installation, flange alignment, VTA testing hardware* Cavity Handling Cages* Cavity Processing Tool Improvements (e.g. HPR, Heat Treatment Furnace, Horizontal EP) Two sets of carriages for cavity string Main Cold Mass and Cryomodule Assembly Tools Cold Mass Spreader Bar - Supports / Positions Cold Mass for cavity string attachment* Cold Mass Installation into Vacuum Tank Vacuum Tank Supports Spreader Bar - Lifts Cryomodule* Shipping Frame & End Caps* *Design exists, purchase copies E. Daly, AWLC, 14MAY2014

Vertical Test Area / Horizontal Test Bench (JLab) VTA Up to four test stands available for production acceptance testing capable of testing one cavity at a time Utilize same cavity hardware (test flanges, feedthroughs, etc.) provided by project to cavity suppliers Small modifications required to existing supports Ensure low magnetic field environment (“magnetic hygiene”) HTB Support High Qo R&D Plan to conduct five tests during production effort to provide feedback on cavity assembly process or for production development activities Modifications to top hat for XFEL-style FPC and small modifications to existing supports E. Daly, AWLC, 14MAY2014

Cold Mass / VV Assembly “Lollipop” supports for each cavity TBD for SC magnet and bpm Use two-rail system to transfer cavity string onto Return Pipe Use two-rail system to transfer cold mass into vacuum vessel Crane access in high-bay for shipping E. Daly, AWLC, 14MAY2014

CMTF Conceptual Layout JUNCTION BOX BAYONET BOX END CAP BAYONET U-TUBE CAVE DOOR (CLOSED) HEAT EXCHANGER End view of CM with bayonets connecting JB, HX and BB E. Daly, AWLC, 14MAY2014