How to improve operational efficiency ? [R. Alemany] [CERN AB/OP] [Engineer In Charge of LHC] Beam Commissioning Workshop, Evian Jan 2010.

Slides:



Advertisements
Similar presentations
Jan Uythoven, AB/BTLHCCWG, 3 May 2006 Page GeV Commissioning Machine Protection Needs to be commissioned to: Prevent damage with the used, higher.
Advertisements

6 th April 2010 MP3 weekly summary – issues and follow-up 0v1 M. Zerlauth for the MP3-CCC shift crew.
MP3 report – week 17 19/4/2010 – 25/04/ interventions MP3/QPS team in CCC Monday Morning Meeting : 26th of April 2010.
Handshake over DIP 10/08/20091R. Alemany - BE/OP/LHC.
8:16 SB 25ns dumped by RF; integrated lumi 0.6 nb-1. 9:14 BIC problem in TI8 and CMS recovering their tracker 10:09 Abort gap cleaning commissioning. 16:29.
LHC Beam Operation WorkshopM. ZerlauthDecember 2010 Thanks to : CERN Machine Protection Panel, EICs, et al 1v0 Do we understand everything about MP system.
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
Tuesday 10 th April - morning Access for:  point 3 Jerome Landaro TCSG one jaw didn't move  point 5 Qps expert on RPMBB.UJ56.RCBXH1.R5  point 6 TCDQ.
NQPS trips due to EMC transients 30/06/20111ZCh, TE-MPE-TM Z.Charifoulline - # nQPS.BS signals in A12 & A34 # statistics over.
Session th January 2010 R.Schmidt TE/MPE Hardware Commissioning 2010 and beyond R.Schmidt.
02/09/2010 Access conditions for test of the RB.A23 at 17:30. Splice mapping. Complete machine closed by ~18:00.Problems in getting TI2 ready for injection.
Operational tools Laurette Ponce BE-OP 1. 2 Powering tests and Safety 23 July 2009  After the 19 th September, a re-enforcement of access control during.
Introduction to availability modelling in ELMAS Arto Niemi.
1 Second LHC Splice Review Copper Stabilizer Continuity Measurement possible QC tool for consolidated splices H. Thiesen 28 November 2011 K. Brodzinski,
“we believe the reason why the first bunch is more intense than the following 3 is that it's on that one that the SPS RF loops are locked” Philippe & Django.
:00: Prepared new fill B1: Q X =0.293, Q Y =0.269; lifetime = 25h ✔ B2: Q X =0.297, Q Y =0.267; lifetime = 5h ✗ Strong 50Hz and 100hz lines.
1 Interlock logic for LHC injection: intensity limitations Jörg Wenninger AB-OP-SPS Outcome of the join Machine-Experiments Workshop on Machine Protection.
Friday March 4 th LHC morning report the short story: from a global point of view we had basically only one access !!!
LHC Status Mo Morning 20-June Bernhard Holzer, Gianluigi Arduini et al 7 runs The Week.
IDE DCS development overview Ewa Stanecka, ID Week, CERN
Handshake with the experiments 04/09/20091 R. Alemany (BE/OP/LHC) LHC Experiments Handshake.
1 Operational availability Optimizing LHC L. Ponce With the (un)intentiona lcontribution of all OP crew.
RBAC Content: LHC Operational Mode Piquet Roles RBAC Strict LHC Operational mode and CMW Acknowledgements: Pierre C., Wojtek S., Stephen P., Lars J., Verena.
Monday h34: beam (1020b) lost after 10 Hz RF trim. Fill h56: XPOC to be reset by expert. 08h18: Masked QPS_STATE SIS interlocks for RB.A12.
LHC Machine Checkout & Dry Runs Strategy Acknowledgements: R.Alemany, R.Giachino M. Albert LHC Beam Operation Workshop June 2014.
Power Converters and DC cablesSlide 1/.. LHC - HC review Hugues THIESEN – AB/PO Thursday, 12 May 2005 Water cooled cables warm bus bars power converter.
1 Commissioning and Early Operation – View from Machine Protection Jan Uythoven (AB/BT) Thanks to the members of the MPWG.
BCWG - 16/11/20102 Content WHY do we need a HW Commissioning campaign? WHAT are we going to do? HOW are we going to do it? ElQA QPS Powering Tests Planning.
NQPS commissioning …a long way to go. Topics nQPS component overview Enhancements in Firmware Commissioning diagram Detailed task list Summary.
09:25 Operator dump fill #2178, integrated lumi 107/108/18 nb-1. Trip of RQ4.R6 (fire heaters discharged) just after the beam dump but the QPS gave no.
MP3 List of main Issues during March 2010 MP3 - Team.
Last night Lhc closed 15:00 Beam on Ti 8 /Ti2 Prepulse check synchronisation ok with LHCb /RF 17:00 Open Point 4 PC’s and RF 19:00 LBDS energy tracking.
[R. Alemany] [CERN AB/OP] [Engineer In Charge of LHC] HWC Workshop ( ) Consolidation and major changes that have impact on the powering circuits.
From yesterday LHC status Wednesday 26 th Welcome Verena back on shift 07:08 Access in PM85 for piquet EPC (O.Fournier).  Fuse on RD2.R8 circuit.
1 Machine considerations and constraints for the Safe Injection Flag and Safe Beam Flag Jörg Wenninger AB-OP-SPS Introduction to ‘injection flags’ Machine.
AB/CO Review, Interlock team, 20 th September Interlock team – the AB/CO point of view M.Zerlauth, R.Harrison Powering Interlocks A common task.
MP3 report – week /05/2010 – 09/05/ actions MP3/QPS team in CCC LMC: 12 th of May 2010.
LHC progress Sunday 3rd May 2015 Coordination: Mike Lamont, Wolfgang Hofle.
Conclusions on UPS powering test and procedure I. Romera Acknowledgements: V. Chareyre, M. Zerlauth 86 th MPP meeting –
Outline of 2014/2015 plans V. Kain, M. Lamont, J. Wenninger 6/18/2013Optics Measurement and Correction Review
Tuesday 26 th April – morning shift 08:00 Great news, cryo is back! Unluckily it was followed by many other problems, one after the other one. So, spent.
Training LHC Powering - Markus Zerlauth Powering Interlocks Markus Zerlauth AB/CO/MI.
Linac2 and Linac3 D. Küchler for the linac team. Planning first preparative meeting for the start-up of Linac2 in June 2013 –this early kick-off useful.
Summary of the technical stop activities on collimators (w17, 2012) O. Aberle – 07/05/12.
04h36: Cryo problem in arc 81. Access. 09h14: Injection.  TI8 injection collimator setup.  Testing new sequence.  New version of vacuum application.
07:00 Dump fil #2219, 123 pb -1 delivered. Trim TDI parking position to +/- 55 mm in the collimator BP trimmed the temperature kicker limit to 62 degrees.
TE-MPE-CP, RD, 28-Sep Problems with QPS DAQ Systems During LHC Operation, 1 st Results from 2010 CNRAD Tests R. Denz TE-MPE-CP.
MPE Workshop 14/12/2010 Post Mortem Project Status and Plans Arkadiusz Gorzawski (on behalf of the PMA team)
Tuesday 3 rd October STABLE BEAMS until 12:25 when we switched to ADJUST for a EOF test for Tobias  dump B2 first and then B1.  Dump at EOF test because.
LHC status Friday 11 th September 2015 Coordination: Mike Lamont, Jorg Wenninger.
Operation of a 6 BCHF collider: do we fit the expectations?
LHC Beam Commissioning Meeting V. Kain & R. Alemany
Machine operation and daily maintenance management in SOLEIL
DRY RUNS 2015 Status and program of the Dry Runs in 2015
Saturday Coordinators weekend: Mike Lamont, Eva Barbara Holzer
-9:00: Test IP transverse adjustment (CMS) and optics verification.
J. Uythoven for the MPE-MI & MS Teams
Tuesday Fill lost #1855 at 7:28 due to the trip of RQX.R1. This was traced to a software bug in the FGC… The Class 51 (LHC_PC) FGC software has been upgraded.
A/N 26 16:00 Access finished problem with the BLM test. one crate is failing the beam permit test. Fixed. Access required in sector 78 for QPS to fix a.
Monday 11/07: Recovery Plenty of accesses.
02/08/ :35: Lost access chain in point 2 (PX24 PAD)  Dump after ~14.5 hours ~100 nb-1.
Thursday morning – optics correction
Fri 29/7 – Sat 30/7 09:00 End of fill 1990, PC trip RCBXV3.R1 (likely SEU on QPS). Integrated Luminosity: 41 pb-1. Access for MKI2 main switch replacement.
Tuesday 28th September Fill 1375 ongoing 09:00 Move in Roman Pots
Tuesday 22 November 2011.
Assumption for a given sector
Friday Morning 7:30 injection for fill 2908
Thursday
Monday 26th September 7:30 Beam dump, QSP on RQX.R1, lost cryo in ITR1, 91 pb-1. Cryo recovery, needed about 1.5 h. Setting of TI2 collimators to 5 sigma.
Friday 15th February - morning
Presentation transcript:

How to improve operational efficiency ? [R. Alemany] [CERN AB/OP] [Engineer In Charge of LHC] Beam Commissioning Workshop, Evian Jan 2010

I. Machine availability/unavailability Source: e-logbook from the 20 th of November to 16 th of December 2009

Machine not available 40% What can be optimized

Machine not available 40% Precycle side effects (18%): Non correct settings Power converter problems (some occasions access needed) QPS problems: Not possible to reset with power cycle  intervention tunnel needed Trips due to U_RES drifts up > 0 mV Noise induced by RBHI in TI2 trips nQPS RQTD, RQTF trips in the whole machine because Q-feedback left over. Circuits mostly affected: 600 A Dry runs (but we need the full monty)

Machine not available 40% Precycle side effects (18%): Non correct settings Power converter problems (some occasions access needed) QPS problems: Not possible to reset with power cycle  intervention tunnel needed Trips due to U_RES drifts up > 0 mV Noise induced by RBHI in TI2 trips nQPS RQTD, RQTF trips in the whole machine because Q-feedback left over. Circuits mostly affected: 600 A We need a PVSS method (Sequencer task) that resets U_RES drift once per day Thresholds increased from 300 µV to 500 µV in S12, but is this enough? We systematically switch off TI2. Once wrong thresholds loaded Remote reset is available for all sectors but for some reasons not always works, why? Can it be fixed?

Courtesy of Reiner And I would like to repeat that the EMC problem between the RBHI in TI2 and the nQPS of S12 should not be forgotten.

Precycle side effects (18%): Non correct settings Power converter problems (some occasions access needed) QPS problems: Not possible to reset with power cycle  intervention tunnel needed Trips due to U_RES drifts up > 0 mV Noise induced by RBHI in TI2 trips nQPS RQTD, RQTF trips in the whole machine because Q-feedback left over. Circuits mostly affected: 600 A Machine not available 40% Avoid to left over Q-Feedback action after an unscheduled dump → Q/Q'-FB dependence on beam presence flag (BPF): automatic FB 'on → off' if BPF 'on → off' FB 'off → on' only if 'BPF == true‘ (without forgetting that sometimes we may want to switch off the feedback when beam is in)

Machine not available 40% QPS specific (10%), examples: Access to increase thresholds on global bus bar detection Access to reset circuits that cannot be rested from CCC Access to replace heater discharge power supply S34 Experiments (~ 3%): ATLAS lost patrol (2 hours) ATLAS up to 20 minutes to analyze PM and give back injection permit SYSTEMATICALLY ALICE problems to give the injection permit (4 hours) Procedure to recover pretty simple, but only one person new it... Difficult to find in the middle of the night  Better trained shifts crews in the experiments. Unacceptable when beam dump not produced by ATLAS and safe beam. With unsafe beam we should discuss. Other experiments by far more fast. Systematic verification of heaters power supplies. Automatic tasks in the QPS system with corresponding alarms.

Machine not available 40% Miscellaneous (~ 5%): Emergency access A combination of precycle problems + cryo lost + access needed One of the major down time reasons is related to having to remove the power permit to access the machine, even the UAs. Why? Because this implies switching off the PC and then having to recycle with all the unwanted side effects. This procedure is very expensive for operations. Can we do something about, like declaring PHASE I (injection current) for all the machine except the RB which will be OFF when accessing UAs? CHAMONIX should answer

Machine available 60% Source: e-logbook from the 20 th of November to 16 th of December 2009 What is this 60%?

Machine available 60% Out of the 60%, 50% beam in the machine, the other 50% was: Preparation for injection: set up transfer lines, MKI soft start, handshakes, LBDS/BIC arming, etc Solve problems (most of them mentioned in Brennan’s talk) Understand the dump (PM) The first thing to do is to solve those problems PERCENTAGE OF BEAM IN THE MACHINE DURING THE 26 DAYS  ~30 % Thanks to Chris R.

Machine available 60% The big majority of problems are solved within few minutes. What is important in this case is the number of times the problem gets repeated. If the problem repeats systematically this is an indication of control tools not adequate, procedures not adequate, training insufficient. There are problems that we can afford to have them with safe beam, if they happen one or two times, but even at this low rate the may constitute an important issue when working with unsafe beam. There are problems that they are not problems by themselves but because of the collateral damage they produce: powering-access interlock  locks all PCs

Machine available 60% Most of the problems mentioned by Brennan have a rather easy and straight forward technical solution  controls problems (FESA servers, proxies, etc) (Wojtek’s talk)  BG’s talk Rigorous use of mode, automatize actions as a function of beam mode changes (fill number changes, handshake, etc)

Machine available 60% Sequencer: a review took place the first week of Jan and a list of requirements with priorities exists. Within the requirement list emphasis is given to prepare the sequencer for unsafe beam operation. From Sequencer Review

Machine available 60% Jorg’s talk

Machine available 60% BLMs issues found in 2009 being addressed/solved + lot of work on reliability/monitoring of the healthiness of the system + over-injection problem under study Etc, etc Christos’ talk

Machine available 60% But there are other problems that require a careful thinking, mainly the ones which solution has to be in place before unsafe beam operation: Injection mechanism: improve software tools to assure correct injection (IQC, injection sequencer, LHC sequencer), check entry conditions before injecting, clean-up the system after injection to be ready for next step, procedures/sequences + of course W. Bartmann’s presentation

Machine available 60% Beam dump analysis: XPOC still work to be done here, as well as Post Mortem: Jorg’s talk (MPS Summary )

Machine available 60% System specific problems: we have to make sure they are addressed and solved. This needs follow up: beam commissioning meeting, dry runs. Procedural problems: need a major debate, but what Brennan proposes is already a good start. Operational discipline/training

Conclusion If we manage to solve the solvable problems which make the machine unavailable we can recover % of the down time. If we manage to solve the problems which prevents us of having beam in the machine when the machine is available, we can recover ~15% of down time. The means to do this exist. But when trying to maximize the beam availability time we should not compromise safety. Unsafe beam operation will imply less flexibility, more checks before injection takes place, more time to analyze the beam dumps... Less beam presence in the machine