LHC machine status Mike Lamont for the LHC team. 75 ns50 ns 2011 – recap Increase number of bunches Reduce beam size from injectors Squeeze further Increase.

Slides:



Advertisements
Similar presentations
LHC Beam Operations Past, Present and Future Maria Kuhn on behalf of the LHC team Moriond QCD 2013.
Advertisements

Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
(n)QPS LHC status and plans LHC Status and Plans Mike Lamont for the LHC team 1.
(n)QPS LHC status LHC: past, present and future Mike Lamont for the LHC team
Status of the LHC Mike Lamont for the LHC team. The LHC Very big Very cold Very high energy 2.
LHCC 3rd June 2015 Mike Lamont for the LHC team
Sat/Sun 26/27 th March Sat 18h20: Stable beams. Fill #1653. Sun 10h02: Stable beams continued. vdM scans. Length calibrations. 16h59: Beam dump. Delivered.
MD#2 News & Plan Tue – Wed (19. – 20.6.) DayTimeMDEiCMP Tue06: GeV  4 TeV: Ramp for chromaticity - missed A 08:00Ramp down 10: GeV: Large.
LHC beam operation past, present, future Mike Lamont for the LHC team.
Lot’s of time lost due to cryo problem in IR8. Major impact, therefore review of MD program… Start discussion here, please let us know your input. Will.
LHC progress with beam & plans. Of note since last time Transverse damper Beta beating in the ramp Collimation set-up at 450 GeV & validation LBDS – systematic.
LHC Accelerator Prospects Mike Lamont for the LHC team “LHC: the status, the projections for this year, and the possibilities for the near and far future..
CONTENT: Beam characteristics and parameters Filling schemes Operational settings OP procedure and COLL setting Planning Shift breakdown To define the.
:00: Prepared new fill B1: Q X =0.293, Q Y =0.269; lifetime = 25h ✔ B2: Q X =0.297, Q Y =0.267; lifetime = 5h ✗ Strong 50Hz and 100hz lines.
Friday to Saturday 02:00: Machine closed. 09:00: Cryogenics all OK. Preparing pre-cycle. 10:00: Pre-cycle started. 11:30: Pre-cycle finished. 14:00: Beam.
LHC progress Report LHCC Wednesday 23 rd March 2011.
Evian 2014 historical perspective run 1: 2010: L peak >10 32 cm -2 s -1  2x10 32 cm -2 s : produce >1 fb -1  delivered.
Machine development - results and plans – critical results, what’s to be done? R. Assmann 15/07/2011 R. Assmann for the LHC MD coordination team (R. Assmann,
Tuesday 17 th April 04:00 Prepare second fill for v/d Meer scans. 06:22 Stable beams, v/d Meer scans for Alice and LHCb. 13:20 End v/d Meer scans.Dump.
Status of the LHC Mike Lamont for the LHC team. LS1 - descent into the underworld again.
09:25 Operator dump fill #2178, integrated lumi 107/108/18 nb-1. Trip of RQ4.R6 (fire heaters discharged) just after the beam dump but the QPS gave no.
Draft MD Planning Thu (3.11.) DayTimeMDMP Thu05:00 Ramp down, cycle 07: GeV: Injection stability and losses – check steering constraints, define.
Collimator settings for 2012 R. Bruce, R. Assmann for the collimation team
Cryo back at 17:30 Beam back at 19:00 IR2 aperture until ~03:00 Since then no beam from the SPS:  Connector problem on MKD  Connector eroded, needs to.
LHC Machine Operational Status and Plans LHCC, 22nd September 2010 Steve Myers (On behalf of the LHC team and international collaborators)
Progress with Beam Report to LMC, Machine Coordination W10: Mike Lamont – Ralph Assmann Thanks to other machine coordinators, EIC’s, operators,
28/01/2013LHC 8:30 meeting Summary of Week 4 pPb physics Machine Coordination: Mike Lamont & Jan Uythoven Ion coordination: John Jowett.
Monday 19 th March 07:33 Lost (another) beam in the squeeze, beyond 2 m, B2 hits 1/3 resonance. 08:30 Start (another) ramp  Try to correct coupling and.
Tue 23/8 – Wed 24/8 09:00 Start 90 m optics run – Preparation and verification of the collimation functions – Re-generation of functions for Transverse.
Mike Lamont An attempt at synthesis Acknowledgements all round
Ralph Assmann, Giulia Papotti, Frank Zimmermann 25 August 2011
MD Planning Fri – Sat (26. – 27.8.)
Wednesday 8.9 External crossing angles:
1st LHC MD Period Started
Wednesday :06 Dump fill 3533: interlock BPMS in IP6
Cryo Problem MD Planning Tue (1.11.) C B Day Time MD MP Tue 01:00
Day :00-11:30: Optics at 3.5 TeV Optics re-measured with AC-dipole. Excellent reproducibility. Small emittance increase from AC-dipole. Collapsed.
LHC Machine Status report
Machine Coordinators: G. Arduini, J. Wenninger
The LHC - Status Is COLD Is almost fully commissioned
Saturday 21st April 00:33 Interlock during ramp on BLM HV
MD Report 24 June 2012 Machine coordinators: Barbara Holzer, Mike Lamont MD Coordinators: Ralph Assmann, Giulia Papotti, Frank Zimmermann MD#2 News & Plan.
Friday 07:00 Power glitch on the EDF network. Point 8 affected.
LHC status Benoit Salvant (Beams department, Accelerator and Beam Physics group) for the LHC complex teams With many thanks for their inputs to J. Boyd,
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Fill 1410 revisited Peak luminosity 1.4e32 Beam current 2.68/2.65 e13
LHC Morning Meeting - G. Arduini
Mike Lamont 4th HERA and the LHC workshop 26th May 2008
Summary of Week 16 G. Arduini, J. Wenninger
Mon 22/8 – Tue 23/8 00:07 stable beams #2040. Initial luminosities: 2.1x1033 cm-2s-1 18:00 Programmed dump. End of physics #2040. ~83 pb-1 in ~18 hours.
Scrubbing progress - 10/12/2012
J. Uythoven, W. Venturini Delsolaro, CERN, Geneva
Week 35 – Technical Stop and Restart
MD#2 News & Plan Tue – Wed (19. – 20.6.)
04-05/08/2010 End of physics at ~11:00 after 18.5 hours ~120 nb-1.
LHC Beam Operations Past, Present and Future
Saturday 7th May Sat – Sun night
Summary Thursday h21: Stable beams fill #1303.
Summary of week 19 Machine Coordinators: G. Arduini, M. Lamont Main aim: Luminosity production.
Aims for the week Recover from technical stop and precycle at 10A/s
MD#2 News & Plan Tue – Wed (19. – 20.6.)
MD Planning Fri – Sat (1. – 2.7.)
Wednesday h10: Programmed dump. 07h54: Injection. 200b.
Saturday :42 stable beams fill 3541
Monday :15 fill 3523 dumped by BPMs IP6
Summary Tuesday h23: Machine closed. Precycle started.
Fri :52 Stable beams fill #2536
Another Immortal Fill….
Tuesday 6th April 8:00 Injection studies 16:00 RF studies
Saturday 29th October Friday during IP2 1 m squeeze test
Presentation transcript:

LHC machine status Mike Lamont for the LHC team

75 ns50 ns 2011 – recap Increase number of bunches Reduce beam size from injectors Squeeze further Increase bunch intensity Initial commissioning Initial commissioning Scrubbing 21/3/2012

2011 Another remarkable year It was nearly always a battle… Remarkably no real show stoppers Successfully took on: – Total intensity – Bunch spacing – Bunch intensity – Emittance – Beta* & aperture 21/3/2012

Of note Operational robustness – Precycle, injection, 450 GeV, ramp & squeeze & collisions routine Machine protection – Unpinned by superb performance of machine protection and associated systems – Rigorous machine protection follow-up, qualification and monitoring Routine collimation of 110 MJ LHC beams without a single quench from stored beams. 21/3/2012

Beam from injectors 21/3/2012 Excellent performance – years in the preparation Best in 2011 with 50 ns: ~1.45 x ppb ~2.3 microns into collision Design with 25 ns: 1.15 x ppb Normalized emittance 3.75 microns

IR1 and IR5 aperture at 3.5 TeV 2011’s “platinum mine” We got 4-6 sigmas more than the expected 14 sigma Triplet aperture compatible with a well-aligned machine, a well centred orbit and a ~ design mechanical aperture Stefano Redaelli 21/3/2012 ~600 m ~3 cm CMS Addition margin allowed squeeze to beta* = 1 m – big success – 3.3e33 cm -2 s -1

Operation efficiency Overall efficiency – Pretty good considering that this is the LHC – Overall time in stable beams 34% Premature dumps – 50% of all STABLE BEAMS fills lasted less than 3 hours 34% 21/3/2012

SEE failures during 2011 operation Systems hit: QPS, Cryogenics, Power converters, Collimation, Interlock systems, UPS, Access UJ14/16 most critical 72 21/3/2012 Markus Brugger

Vacuum 21/3/2012 LSS2 CMS Unexpected pressure rise (10 -6 mbar) observed in LSS2 & LSS8 and close to CMS: – bad RF contact (x-rays inspection) Interventions done in 2 & 8 & CMS to resolve RF finger issues – shouldn't be a problem in Vincent Baglin

Injection collimators beam screen heating 21/3/2012

Concerted program of investigations, simulations, tests with beam … Tobias Baer

Christmas stop The big 5: Cryogenics, Cooling and Ventilation, Electricity, Vacuum, Magnets and protection Plus many, many other activities Huge amount of work performed to ensure a reliable operation in 2012: – Maintenance, consolidation, upgrades… No major concerns during the break From the machine side a duration of 13 weeks (from beam ON to beam OFF) is realistic (no margin but no shortcuts) 21/3/2012 Katy Foraz

R2E 2012 ~30-50 dump events expected… Mitigation actions over Xmas: 21/3/2012 Relocation Point 1: Fire detectors Points 4 & 6: cryogenics CPUs relocated from UX to UL Point 5: Civil engineering (ducts in UL557, vault along 20 m) UPS relocated from UJ56 to UL557 PIC relocated from UJ56 to USC55 Point 8: Ethernet racks (startpoint) (from US85 to UL86) WIC & timing racks (from US85 to UA83) QURCb & rack EYQ (from US85 level 2 to US85 level 0) Shielding Point 1: RBs/UJs Anne Laure Perrot

2011 to 2012 Well organized, productive Xmas technical stop – Lot of R2E related work – Plus consolidation and improvements of many systems Vacuum consolidation to address successfully diagnosed causes of instabilities in 2011 Injection collimators issues diagnosed and understood - spare in preparation - fingers crossed in the meantime Cool-down of machine exactly on schedule - cryogenics demonstrating full mastery… Very smooth hardware commissioning including careful quench-less commissioning of main circuits to 4 TeV Well oiled Machine checkout final tests and preparation for beam 21/3/2012

2012 strategy 4 TeV 50 ns p-Pb: 3.5 TeV or 4 TeV β*=0.6m→0.7m→0.9m ∫Ldt = fb -1 L peak = cm -2 s -1 SPS N p = SPS ε= 2 μm Pile-Up=26-35 ∫Ldt = 5 fb -1 in June? β*=(0.6,0.6,0.6,3)m TCP gap=2.2mm LHCb ∫Ldt=1.5 fb -1 SEE dumps=30-50 nb -1 ∫Ldt = nb -1 21/3/2012 Rogelio Tomas

Collimator settings 2012 Collimation hierarchy has to be respected in order to achieve satisfactory protection and cleaning. Aperture plus tight settings allows us to squeeze even further.. 21/3/2012 σ TCP 74.3 TCSG 76.3 TCLA 78.3 TCSG 67.1 TCDQ 67.6 TCT9.0 Aperture : tight settings Roderik Bruce

How tight? 21/3/2012 Intermediate settings (2011): ~3.1 mm gap at primary collimator Tight settings (2012): ~2.2 mm gap at primary collimator Norway Iberian peninsula Roderik Bruce

2012 run configuration Energy – 4 TeV – Low number of quenches (as in 2011) assumed Bunch spacing - 50 ns Collimator settings – tight – As discussed – NB not yet proven operationally Atlas and CMS beta* - 60 cm – with 70 cm and 90 cm as fallbacks Alice and LHCb beta* - 3 m – Natural satellites versus main bunches in Alice 21/3/2012

Bunch spacing Performance from injectors Bunch spacing From Booster Protons per bunch (ppb) Emittance H&V [mm.mrad] 150 Single batch 1.1 x Single batch 1.2 x Single batch 1.45 x Double batch 1.6 x Double batch 1.2 x /3/2012

2012 LHC schedule Q1/Q2 Commissioning MD & TS Ramp-up Scrubbing 21/3/2012

2012 LHC schedule Q3/Q4 Special runs Proton-lead 21/3/2012 High beta* runs for ALFA and TOTEM Van der Meer scans

breakdown 21/3/2012 Days Machine check-out2 Commissioning with beam21 Machine development22 Technical stops20 Scrubbing (25 ns)3 Technical stop recovery6 Initial intensity ramp-up~21 Proton running~126 Special runs~8 Ion setup4 Ion run24 ~150 days

50 ns performance estimate 4 TeV, 50 ns, 1380 bunches, 1.6e11, 2.5 microns 150 days of proton physics (assuming similar efficiencies to 2011) Beta* [cm] CollimatorsPeak Lumi [cm- 2 s -1 ] Int. Lumi [fb -1 ] Pile-upIncrease in peak 90Intermediate5.1e – Tight6.2e – % 60Tight6.8e – % 21/3/2012

25 ns performance estimate 4 TeV, 25 ns, 1380 bunches, 1.6e11, 2.5 microns 140 days of proton physics (extra scrubbing required) Beta* [cm] CollimatorsPeak Lumi [cm- 2 s -1 ] Int. Lumi [fb -1 ] Pile-up 80Tight3.8e /3/2012 Conclusion: 25 ns not competitive with 50 ns

Present status 21/3/2012 DateMilestone Wed 14.03LHC ready for injection Beam 1 injected Thu 15.03Both beams captured, orbit and Q adjusted Optics measured and corrected at 450 GeV Fri 16.03Both beams at 4 TeV Sat 17.03Beam 1 squeezed to 0.6 m Sun 18.03Both beams squeezed to 0.6 m Separation and crossing angles on Mon 19.03Beam Instrumentation, Ramp & squeeze Aperture measurement Tues 20.03RF, injection Beam taken for the first time in 2012 a week ago

Optics measurement at 4 TeV 21/3/2012 Flat-top before squeeze Almost unbelievable reproducibility of magnetic machine

Aperture measurements at 450 GeV 21/3/2012 loss rate at the global bottleneck Q4R6 primary collimator Beam loss at collimator Using transverse damper to generate constant losses with single bunch Stefano Redaelli, Daniel Valuch

Initial commissioning (3 weeks) System commissioning Transverse damper RF Beam instrumentation Machine protection Feedbacks System commissioning Transverse damper RF Beam instrumentation Machine protection Feedbacks Optics meas. & correction Magnet model meas. & correction Aperture measurements Optics meas. & correction Magnet model meas. & correction Aperture measurements 21/3/2012 Progressing well - machine in good shape

Conclusions Good performance in 2011 from working on all available parameters Very definitely exploring the effects of high intensity beams – SEUs, beam induced heating, vacuum instabilities… – Operational efficiency suffering as a result Main gain in 2012 is use of tight collimator settings and reduced beta* – 5 to 6 x cm -2 s -1 and 15 fb -1 should be possible Hope for improved operational efficiency – R2E mitigation measures etc. – but partially countered by increased peak performance Commissioning progressing well - another long, interesting year in prospect… 21/3/2012