Mohamed Al-Shaikh, BSc MSc CEng MIET Manager, Maintenance - GCCIA

Slides:



Advertisements
Similar presentations
Electricity Restructurings: The Legal Perspective Robert Lane CMS Cameron McKenna (London)
Advertisements

BI Marketing Analyst input into report marketing Report TitleElectricity in Swaziland Report Subtitle Country profile of power sector, market trends and.
Grid Issues Charles Davies Commercial Director, National Grid Company British Wind Energy Association April 2002.
Click to edit title Click to edit sub-title The European Network of Transmission System Operators Stockholm 14th of September 2009 Teun van Biert - Convener.
Albanian power market Sokol RAMADANI Chairman ERE- Albania 1 FEBRUARY 2012 Electricity market design and regulatory issues in Albania and South East Europe.
SAUDI ELECTRICITY COMPANY (SEC)
The Need for an Energy Grid in the Maldives
Planning challenges for RE Deployment North African perspective Addressing Variable Renewables in Long-Term Energy Planning (AVRIL) : 2-3 March 2015 Rim.
1 SOLAR AND ENERGY STORAGE FORUM 14 APRIL 2014 | DUBAI, UAE SOLAR AND ENERGY STORAGE FORUM 14 April | DUBAI, UAE Supported By:
“Investment in Transmission” Economics of Electricity Markets – IDEI Toulouse, 2-3 June 2005 Jon Carlton – Director of Network Strategy.
Power Supply Options for Connecticut’s Energy Future Connecticut Energy Advisory Board Scott Davido President, Northeast Region NRG Energy, Inc. December.
Towards Regional Independent Operators – a main driver for successful market integration.
Powering Africa – SAPP Strategies
E: W: E: W:
BUSINESS OPPORUNITIES IN SAUDI POWER SECTOR US-Saudi BUSINESS OPPORTUNITIES FORUM CHICAGO April 28-29, 2010 Ali Albarrak President &C E O Saudi Electricity.
TRANSACTION AND INDUSTRY REVIEW CONFERENCE NIGERIAN POWER SECTOR REFORM: AN OVERVIEW OF TCN AGREEMENTS.
Saudi Arabian Monetary Agency “SAMA”
. Juan de Fuca Cable. Safe Harbor Statement Included in this document is certain information which is “forward looking information” as defined by the.
THE TRES AMIGAS SUPERSTATION Southwest Renewable Energy Conference Santa Fe, NMSeptember 16 th 2010 UNITING THE NATION’S ELECTRIC POWER GRID.
Costs of Ancillary Services & Congestion Management Fedor Opadchiy Deputy Chairman of the Board.
1 Electrical Energy Transmission by High-voltage Direct Current (HVDC) and Prospects for an Electrical Market Mohamed Lakhdar HABIB and Rime BOUAROUDJ.
Electricity Network Connectivity Between the GCC Countries Presented By: Adnan I. Al-Mohaisen May 17, 2005.
Economic Development and Globalization Division Financing for Development Section.
RAO “UES of Russia” Action Plan on Reliability Improvement of Unified Power System of Russia August 29, 2005.
Grid Integration of Renewable in India - Challenges and Policy Responses Sanjay Garg General Manager General Manager PGCIL/ Ministry of Power.
Turkish Power System Overview March 2012
PJM © PJM Overview ARIPPA Valley Forge, PA November 8, 2007.
SARI/Energy Integration South Asia Regional Initiatives for Energy Integration (SARI/EI) Shanker Khagi USAID/Nepal March 7, 2013 Kathmandu, Nepal Supporting.
AFREPREN/FWD Cogen Centre Training Workshop on Cogeneration in Africa
Legal and Regulatory framework Regional Power Exchange Issues Apr 4, 2006 Kjell A Barmsnes
RENEWABLE ENERY & BIOMASS COGENERATION TRAINING – KENYA BY LEWIS B. MHANGO.
Impact of Liberalization of the Electricity Market on Energy Efficiency, Quality of Supply and Environmental Performance Eric BONNEVILLE ECI Webconference.
Contents Overview and latest topics in TEPCO
Sanjay Garg General Manager PGCIL/ Ministry of Power
Association of Energy Regulators for Eastern and Southern Africa EgyptEra Electricity Market and Regulators Status in COMESA General Assembly Meeting Lusaka,
Croatian Power System 1 The Electric Power System - Croatia -
18th APUA Congress Power Network Interconnections and Development of Regional Markets in Maghreb and Europe  Mr. Djebrouni Mohamed.
 Transmitting power at high voltage and in DC form instead of AC is a new technology proven to be economic and simple in operation which is HVDC transmission.
Cooperative Opportunity for Wind Development. State of Union speech  “it’s possible we could generate up to 20 percent of our electricity needs through.
Technical Advisory Group Tuesday 6 October 2009 Tony Pearson Network Planning Manager.
Updated 1/28/2011.
Developing Africa’s energy potential and integrating power supply systems for sustainable development in African countries (case of Niger)
OFFSHORE WIND ENERGY IN OUR POWER SYSTEMS CONCLUSIONS AND RECOMMENDATIONS FROM THE EUROPEAN CONCERTED ACTION FOR OFFSHORE WIND ENERGY DEPLOYMENT Luc Dewilde,
European Commission views on intra-day and balancing markets
World Bank Framework for Energy Trade in South East Europe David Kennedy World Bank.
ACCESS TO THE GRID Vaida Tamašauskaitė Power System Planning Division Power System Development Department Lietuvos energija AB Ryga, 3 July, 2006.
BritNed Investing in interconnection capacity Damian Bach France-UK-Ireland Stakeholder Group meeting 4 th July 2008, Sellindge, Kent.
BI Marketing Analyst input into report marketing Report TitleElectricity in Madagascar Report SubtitleCountry profile of power market trends and investment.
BI Marketing Analyst input into report marketing Report TitleElectricity in Texas Report Subtitle State profile of power sector, market trends and investment.
BI Marketing Analyst input into report marketing Report TitleElectricity in Namibia Report Subtitle Country profile of power sector, market trends and.
1 The Macroeconomics of Labor Market Outcomes in MENA over the 1990s: How Growth has Failed to Keep Pace With a Burgeoning Labor Market.
1 SYMPOSIUM: U G A N D A A F T E R I D I A M I N A N D M I L T O N O B O T E Hamburg, Germany 29 th September 2008 INVESTMENT OPPORTUNITIES IN POWER GENERATION.
EABC/EAC ENERGY CONFERENCE: 8-9TH JUNE, AVAILABLE BUSINESS OPPORTUNITIES IN THE ENERGY SECTOR By Eng. B.J. Mrindoko.
AFRICAN DEVELOPMENT BANK KENYA- SPAIN Multilateral Partnership Meeting Nairobi, 9 December 2013.
Guidelines on Transmission Tarification ERGEG Public Hearing 30. June 2005.
ERRA Workshop on Regulatory Monitoring of the Electricity Sector Almaty, Kazakhstan, January 31 – February 2, Improvement of market relations in.
This project has received funding from the European Union’s Horizon2020 research and Innovation programme under grant agreement No
Black Start Service in New England System Operator’s Perspective Robert B. Burke ISO New England Inc. July 23, 2002 IEEE - Chicago, Illinois.
International Telecommunication Union (ITU) Arab Regional Office
Population – 2015 (Million)(2) Energy Generated (TWh) (1)
Damitha Kumarasinghe Director General
“Caucasus Power Transmission Network’’ (Armenia-Georgia overhead transmission line/substations) Loan Project.
Development of an Integrated Energy Market in Saudi Arabia
ERERA AND ECOWAS ELECTRICITY MARKET DEVELOPMENT AND REGULATION
THE REPUBLIC OF MALAWI MALAWI PRESENTATION AT
Electricity Sector in Egypt.
Yangon Region Rural electrification plan
Introductory Material on GCC
Statistics beyond the National Level –Regional Experiences
Albanian power market ERE- Albania Sokol RAMADANI Chairman E R E
Presentation transcript:

Mohamed Al-Shaikh, BSc MSc CEng MIET Manager, Maintenance - GCCIA GCC Interconnection Authority The GCC Interconnection Grid 7th Power Transmission and Distribution Forum Kingdom of Bahrain Mohamed Al-Shaikh, BSc MSc CEng MIET Manager, Maintenance - GCCIA 28-30 October 2007

LEGAL AND ORGANIZATIONAL DEVELOPMENT GCC Interconnection Authority OVERVIEW INTRODUCTION PROJECT DESCRIPTION PROJECT STATUS LEGAL AND ORGANIZATIONAL DEVELOPMENT PROSPECTS CONCLUSIONS

Supply has to increase to match the anticipated demand. Interconnection Rationale Power Demand in GCC Countries is anticipated to increase from 32 GW in 2003 to 94 GW in 2028. Supply has to increase to match the anticipated demand. Considerable investment is required to build new generating capacities . The two common strategies: build capacities independently or interconnect individual systems. Economic analysis of the interconnection indicated a cost / benefit ration 1.77 )all six countries ( Reduces investment for power reserves by 3.5 billion US $ (2008- 2028) for the same reliability.

Benefits of the Interconnection Reduce generating capacity required in each system due to ability to share power reserves Share spinning reserves to cover emergency operating conditions Lower operating costs by using most economic generation unit in the interconnected system Improve the overall system reliability Provide emergency support to any system during black out situations Provide means for energy trading

Sharing of the Costs of the Interconnection Phase I (%) Phases I &III (%) Kuwait 33.8 26.7 Saudi Arabia (ERB) 40.0 31.6 Bahrain 11.4 9.0 Qatar 14.8 11.7 UAE 15.4 Oman 5.6 TOTAL 100.0

PROJECT DESCRIPTION

Geographical Map Substations HVDC Converter Control Center

Single-Line Block Diagram KUWAIT AL ZOUR 400 kV 1200 MW BAHRAIN 310 km AL FADHILI 400 kV SAUDI ARABIA SEC – ERB HDVC BACK-TO-BACK 112 km 90 km JASRA 400 kV 600 MW 1200 MW 100 km 290 km GHUNAN 400 kV QATAR DOHA SOUTH SUPER 400 kV SALWA 400 kV 150 km 900 MW 750 MW UAE SHUWAIHAT 400 kV EMIRATE NATIONAL GRID 400 MW OMAN OMAN NORTHERN GRID 52 km AL WASEET 220 kV AL OUHAH 220 kV

Contract Prices Contract Price Substations $221,983,888 HVDC BtB Conv. $205,896,785 Transmission Lines $280,400,717 Cables $343,122,125 Control Center $27,637,220 Consultancy $16,283,146 TOTAL $ 1,095,323,881

PROJECT STATUS

Al-Zour / Al-Fadhili T/L Al-Fadhili / Ghunan T/L Project Progress Contract No. Contract Actual Percentage (%) 112-A1 Al-Zour S/S 74.33 112-A6 Al-Jasra S/S 66.16 112-A7 Doha South S/S 81.08 112-A2 Al-Fadhili S/S 93.42 112-A4 Ghunan & R.A.Q. S/S 41.74 112-A5 Salwa S/S 74.4 113-A3 Al-Fadhili B2B 51.84 114-B1 Al-Zour / Al-Fadhili T/L 41.06 114-B4 Salwa / Doha South T/L 50.98 114-B2 Al-Fadhili / Ghunan T/L 81.62 114-B3 R.A.Q. / Ghunan / Salwa T/L 28.14 115-B5 Land & Submarine Cable 10.66 116-C Control Systems 64.09 Overall Progress 41.34

Project Status Completed the Submarine Cable Route Survey between Kingdoms of Bahrain and Saudi Arabia Geo-Technical study of the Land Cable in the Kingdom of Bahrain Final stages of the engineering work

Submarine Cable Route

Project Status Foundation work is in progress Al Jasra Doha South Final stages of the engineering work

Project Status Al-Fadhili Converter No. 2 & 3 – Control Building & Valve Hall constructions in progress Final stages of the engineering work

Project Status Salwa to Doha South – Tower Auguring of Foundation Al-Zour to Al-Fadhili – Hoisting of Insulators String Salwa to Doha South – Tower Auguring of Foundation Final stages of the engineering work

Project Status ICC – Reinforcement of Bar for Roof Beams & Slab Construction of the roof of the ICC building is in-progress ICC – Reinforcement of Bar for Roof Beams & Slab Final stages of the engineering work

LEGAL & ORGANIZATIONAL DEVELOPMENTS

The Legal Structure / Framework for GCCIA Legal Framework Organizational Framework GCC Ministerial Committee General Agreement E & W Ministerial Committee Level Regulatory Advisory Committee General Assembly & Board Level Articles / Bylaws GCCIA Board of Directors Planning Committee Operating Committee PETA GCC Utilities Level GCCIA - CEO Transmission & Metering Codes

Legal Agreements General Agreement (GA) Interconnector Transmission Code (ITC) Power Exchange & Trading Agreement (PETA) High level agreement between the Member States setting out the rules and regulations in respect of the inteconnector as well as defining the Regulatory Committee and the regulatory principles. Agreement between the Trading parties setting out the technical provisions which the Authority, the TSO Parties and the Procurement Parties will observe when operating and using the Interconnector . Agreement between the Trading parties setting out obligations in respect of installed capacities and operating reserves as well as Terms applicable to connection, use of interconnector, and Trading.

PROSPECTS

Development of the Electricity Market Provide a Wheeling Services to the power sectors in the GCC countries Becomes a ‘Launch-Pad’ for Energy Trading Provide access to the Electricity Market in the region and beyond

Opportunities for the GCC Electricity Market UCTE East EJLIST Arab Maghreb GCC

Opportunities for the Authority Utilize the OPGW fiber optic excess capacity Authority may lease out fibers Market is being explored

The work progress shows about 41 % accomplishment as on September 2007 Conclusions The Interconnector will provide economic benefits and support in emergency situations The Interconnector’s connection points rated equivalent to the loss of 50% of the largest power plant for each country The work progress shows about 41 % accomplishment as on September 2007 The Interconnector’s legal and organisational frame work is in the process of being finalised The GCC Grid will be a fundamental step that can lead to a regional electricity market The Interconnector Provides an opportunity for capitalizing in fiber optic excess capacity

Thank you www.gccia.com.sa