Valuations and interim certificates. Purpose Value the works taking account of: – the physical work done on site; – any extra work ordered by the client;

Slides:



Advertisements
Similar presentations
1 CLIENT CONSULTANT AGREEMENT. 2 Negotiations Types of Consulting Contracts Standard Form of Contract Form of Contract General Conditions Special Conditions.
Advertisements

CONTRACT PAYMENTS & VARIATIONS
Cash Flow Sewon Kim Kevin Tran Mary. Index Introduction Clients cash flow Contractors cash flow Cash flow forecasting Improving cash flow Example References.
4/13/2017 1:54 PM.
OCR Payment Process Training 01/17/2012. Article 9 – Compensation and Payment General Conditions – Article 9 – 9.1 Preconstruction Stage Compensation.
Construction Contract Administration (ENGC 6363) ( FIDIC Chapter 15) EMPLOYER BY TERMINATION Presented by: Mustafa Al tayeb.
Basic Financial Requirements for DoD Government Contracting 2015 National SBIR/STTR Conference The views expressed in this presentation are DCAA's views.
LOGO October The Employer FIDIC 1999 dasdas Supervisor: Dr.Kamalain shaath Done by: Mahmoud Abu Kmail Construction Contract Administration ENGC.
Contract price & payment
2.A. Budgeting and Payment Procedures for All other Types of Contracts
ACCOUNTING PRINCIPLES SIXTH CANADIAN EDITION Prepared by: Debbie Musil Kwantlen Polytechnic University Chapter 3 Adjusting the Accounts.
Revise lecture 29.
Project risk and control. Tender risk Programme and method – Tightness of completion LAD’s Extent of change – Construction method Temporary works Change.
Compensation events and claims Presented by Prof. Khem Dallakoti.
CONSTRUCTION CONTRACTS – MASTER CHART
1 © 2012 John Wiley & Sons, Ltd, Accounting for Managers, 4th edition, Chapter 8 Accounting for Inventory.
Measurement and Payment. Construction Progress Payments –Contractor gives a bill for progress to RPR Outlines what bill is for Give details as needed.
CONSTRUCTION CONTRACTS DOCUEMENTS
LECTURE 4 FORMULATION & PRESENTATION OF MONETARY CLAIMS  Recovery of Loss / Expenses / Damages  Notice of intention to claim  Particular and further.
ARC 807: Professional Practice and Procedure Department of Architecture, Federal University of Technology, Akure, Nigeria ARC 807: Professional Practice.
Cost valuation reconciliation. When Usually commences after the external valuation Time dependent upon the complexity and size of project Usually takes.
FORMULATION & PRESENTATION OF EOT CLAIMS
CONSTRUCTION ADMINISTRATION Measurement and Payment Dr. Alaattin Kanoğlu Spring, 2013 Professional Practice Management I.B.U. Architecture Undergraduate.
1 CONTRACT COSTING. 2 Method where each contract is treated as cost unit and Profit & Loss is ascertained separately. Contract Costing defined: Employed.
7 Plant, Materials and Workmanship. 7.1Manner of Execution The Contractor shall carry out the manufacture of Plant, the production and manufacture of.
Project Closeout Module #14 Prepared by Dr. Randy R. Rapp July 2005.
Programme and progress. Programme Employer requirements – Sectional completion Pre-tender programme – Use for ascertaining completion risk – Subcontractor.
Project Cash Flow.  In order to make a workable project plan, the resources needed for the project and their availability must be checked.  Money is.
CE 366 PROJECT MANAGEMENT AND ECONOMICS Robert G. Batson, Ph.D., P.E. Professor of Construction Engineering The University of Alabama
© 2013 John Wiley & Sons, Ltd, Accounting for Managers, 1Ce, Ch 7 1.
Chapter 13 Estimates for Remodeling Work
Chapter 18: Revenue Recognition Intermediate Accounting, 11th ed. Kieso, Weygandt, and Warfield Prepared by Jep Robertson and Renae Clark New Mexico State.
Financial Management Glencoe Entrepreneurship: Building a Business Analyzing Your Finances Managing Your Finances 21.1 Section 21.2 Section 21.
Stakeholder and regulatory environment © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 1.
LECTURE 5 FORMULATION & PRESENTATION OF OTHER CLAIMS
Measurement and Payment
TOPIC-7- PROJECT CASH FLOW
Joint Report to Select Committee on Appropriations by Northern Cape Department of Health Northern Cape Department of Roads & Public Works supported by.
Performance Based Payments And Progress Payments Bryant, Wilson, Wheeler, Lyons October 29, 2015 Overall Classification Unclassified // None.
Service Departments © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 1.
Final Accounts. Accounts Submissions Last Bill for Contracted Works ( excluding Retention) Presented at Practical Completion Practical Definition dependant.
Technical Assistance Office TCP Projects 2005 Contractual and Financial Management Administrative and Financial Handbook Prepared by IA, 14/12/2001 SOCRATES.
Company Structure © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 1.
Collaboration of Entitlement and Cost Efforts in Claims Analysis Rubino & McGeehin Consulting Group June 27, 2005.
ICTAD Formula Method for EMERGENCY NORTHERN RECOVERY PROJECT
1. 2 Cost & Price Analysis Breakout Session # 312 Beverly Arviso, CPA, Fellow, CPCM, CFCM, Arviso, Inc. Melanie Burgess, CPA, CFCM, Burgess Consulting,
Administration of a FIDIC Contract - Project Control
Bills of Quantities Introduction to FIDIC - Bills of Quantities -
Financial Clauses and Procedures.
Drawings Introduction to FIDIC - Drawings -.
Administration of a FIDIC Contract - Financial Management
Contractor’s Post-contract Cost Management Processes
COST PLANNING AND ESTIMATION
Project Development and Managing your Build Agenda
COST PLANNING AND ESTIMATION
TOPIC-7- PROJECT CASH FLOW
Chapter 19: Revenue Recognition
Presented by Peter Barnes
Resource procurement.
Engineering Project Tendering.
Corporate governance and management
TOPIC-7- PROJECT CASH FLOW
Certificates JCT 11 SBC allows for 10 different kinds of certificates.
ARCH 435 PROJECT MANAGEMENT
Contracts and documentation
Financial management.
Unique General Conditions of the Alabama Building Commission (ABC)
Certified Cost or Pricing Data vs
ICTAD Formula Method for Price Fluctuation Price Fluctuation.
Presentation transcript:

Valuations and interim certificates

Purpose Value the works taking account of: – the physical work done on site; – any extra work ordered by the client; – the work of any specialist-nominated subcontractors; – the cost of running the site (the contractor’ s preliminaries); – the value of any materials delivered to site. © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 2

Timing In accordance with the JCT SBC/Q 2011, Interim Valuations shall be made by the Quantity Surveyor whenever the Architect/Contract Administrator considers them necessary for the purpose of ascertaining the amount to be stated as due in an Interim Certificate Under the ICC – Measurement Version, the methodology is different because it is the Contractor who shall submit to the Engineer … a statement showing the estimated contract value … carried out up to the end of that month. It is the opinion of the Engineer that decides the amount to be certified for payment. © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 3

Methods of payment Stage payment – Link to contract sum analysis and programme – Link to agreed value profile Measure and value – Remeasurement and application of contractor rates Payment notices – The act requires notices to be provided. Retention – Alternatives- bonds – Release of moieties – Retention limit under the ICC conditions – the physical work done on site; – any extra work ordered by the client; – the work of any specialist-nominated subcontractors; – the cost of running the site (the contractor’ s preliminaries); – the value of any materials delivered to site. © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 4

Retention limits © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 5

Principles Accumulation – Cumulative Deduction of previous payments Types of valuation – External valuation – Internal valuation – Subcontract valuation © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 6

Valuations…. © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 7

Techniques Inspection – Easy and quick – But inaccurate Measurement – On site or from revised drawings – Accurate and agreement assured – Timely and difficult to isolate variations Ogive curve (reference to a model of planned expenditure) – Simple and adjustments to forecasts can be made – Inaccurate and slow progress may lead to over payment Gantt chart – Easy to agree and relate to stage payment – Inaccurate and can be abused by loading © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 8

Materials on site Lists and inspection Retention of title – Sale of good act 1979 – Dawber Williamson – Ensure entitlement © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 9

Interim valuation © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 10

External valuation- Contract provisions © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd.

Components of an interim valuation measured work completed; ● incomplete measured work; ● work which may not be built to specification (but overlooked); ● work completed or partially completed which may be a variation to the contract; ● extra work carried out to the verbal instructions of the architect/engineer; ● work done by the contractor which may have to be valued on a prime cost basis (i.e. daywork); ● preliminaries, that is the contractor’ s fixed and time-related costs of running the site; ● materials brought to site which the contractor is entitled to be paid for; ● materials or components being prepared or fabricated off-site; ● the impact of progress which might be ahead of or behind the master programme; ● the contractor’ s entitlement to loss and expense for non-culpable delay and/or disruption; ● circumstances where the contractor may be entitled to extra preliminaries; ● the impact of adjustments to the time for completion of the contract; ● deductions from the contractor’ s payment due to set-off by the employer; ● deductions for liquidated and ascertained damages where the contractor has exceeded the time for completion of the contract. © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 12

Valuation of variations For similar items of work carried out under similar conditions with no significant difference in quantity – use bills of quantities rates. For similar items of work carried out under dissimilar conditions and/or with significant differences in quantity – use bills of quantities rates as a basis for the valuation. For dissimilar items of work carried out under dissimilar conditions and/or with significant differences in quantity – value the work at fair rates. Where an approximate quantity proves to be a reasonably accurate forecast of the quantity of work required – use the rate or price in the bills of quantities. Where an approximate quantity is not a reasonably accurate forecast of the quantity of work required – use the rate or price in the bills of quantities as a basis for valuation. Where the work involved in a variation cannot be properly valued by measurement – use daywork as the means of valuation. © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 13

Daywork- prime cost and uplift © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 14

Daywork- records © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 15

Preliminaries © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 16

Internal valuation- relationship to external valn. © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 17

Subcontractor valuations © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 18

Final accounts © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd.