Superstructure Replacement Substructure Repair Rehabilitation of I-95 Bridges 11 Bridges Along I-95 Corridor 10 9 8 7 5 1 2 3 4 6.

Slides:



Advertisements
Similar presentations
Gordons Corner Road Over US Route 9 Mahesh Patel, P.E. George Afful, P.E. Gregory Bitsko, P.E.
Advertisements

ODOT Structure Project Manager Training
Actions and Retrofit of Post Earthquake-Damaged Bridges
July Training Outline Part 1 Cost-per –SF and Detailed Estimate Pay Item Detailed Estimate Segments Bridge Level Data Segment Level Data Supports.
REPAIR OF FLOATING CONCRETE PANTOONS AND CATHODIC PROTECTION OF MOORINGS, BODRUM (KARADA) MARINA TURKEY.
Indianapolis Airport Interchange Bridges Presented to: TRB Bridge Aesthetics Subcommittee January 11, 2005.
Findings from On-site Inspection (Rt 202/US Rt 23 BRIDGE)
MDOT ACTT Workshop Structures I-94 From I-96 to East of Connor Participants Steve Stroh, URS Corp Vijay Chandra, Parson Brinckerhoff Raj Ailaney, FHWA.
Dan Gorley, P.E. IDAHO TRANSPORTATION DEPARTMENT REMOTE PBES.
Bridge over BNSF Railroad 7 km East of Windham - East Bridge Replacement Project Using Accelerated Bridge Construction.
Fire Response Recommendation Upon dispatch to an industrial accident: Battalion needs to confirm location of incident - north side, south side, or in.
AASHTO Sub-Committee on Design Meeting April 28, 2010.
Subpart R Steel Erection. Workers of the past were sometimes referred to as “Dare Devils.”
Totally Precast Concrete Bridges
3 June Rapid Replacement of the Hood Canal Bridge Approach Spans Joseph Merth, P.E. Bridge Design Engineer 3 June 2008.
Reconstruction of the Eads Bridge Highway Deck
SR-528 (Beach Line)/ SR-3 (Courtenay Blvd) Emergency Bridge Repair January 21, 2011.
 Project Delivery  Design Considerations  Lessons Learned.
Performance of Slag Pavements Prepared by Peter Rufford P E E C E.
Damage Illustrations. Potential Bridge Damage Bridge Component / DamagePossible Cause Approach Slab or Pavement  Raised, lowered, cracked, or buckled.
Bridge Maintenance and Repair.
Schematic Design of an Accelerated Bridge Construction Project Michael P. Culmo, P.E. Vice President of Transportation and Structures CME Associates, Inc.,
Bearings and Beam Ends Jeff Naum Maine DOT. Bridge Nomenclature.
Bridge Rehabilitation W Interstate 290 over CSX Railroad and 4 City Streets I-290 Viaduct Reconstruction.
The nature of concrete can be determined through petrographic examinination.
OPTIMUM COATING SOLUTIONS OPTEK PRODUCTS CEMETITIOUS COATINGS AND ADDITIVES Brief overveiw.
Public Information Meeting Rehabilitation of Bridge No Flat Rock Hill Road over I-95 Old Lyme, Connecticut Rehabilitation of Bridge No Flat.
By PARIKH KALPESH. Overview Introduction Structural evaluation of the bridge deck, girders, abutment, and piers Recommended non destructive tests Short.
Office of Highway Safety Bridge Inspections Dan Walsh.
Introduction The service life of concrete elements in highway bridges is often limited by the corrosion deterioration of reinforcing bars. In cold regions,
Copyright 2008, CRS Holdings, Inc. Improving Tomorrow’s Infrastructure: Extending the Life of Concrete Structures with Solid Stainless Steel Reinforcing.
Enosburg BRO 1448(40) Bridge 48 on TH 2 Over the Tyler Branch Alternatives Presentation.
Approaches to Historic Bridge Rehabilitation Case Study #4
Introduction to a pit installation
WVDOH Accelerated Construction Concepts Benjamin Beerman, PE.
Bridge Engineering (5) Substructure – Abutments and Piers
St Johnsbury BF 7000(20) Bridge 6 on VT Route 2B over the Lamoille Valley Rail Trail Presenter: John Byatt, PE Consultant Project Manager.
REPAIRS AND REHABILITATION OF STRUCTURES UNIT – II
34 th Annual Airports Conference Hershey, PA Preservation of Airport Infrastructure: Using Correct Tools to Save Costs Siva Venugopalan Principal Engineer.
Progress Photos Goodnoe Elementary School Additions and Renovations Project November 2013 Goodnoe Elementary School.
Hoan Bridge Failure Analysis Hoan Bridge Failure Analysis Wisconsin Department of Transportation City of Milwaukee, WI December 13, 2001 City of Milwaukee,
Enosburg BRO 1448(40) Bridge 48 on TH 2 Over the Tyler Branch Public Information Meeting.
The Use of Zinc Anodes to Extend the Life of Concrete Patch Repair Jack Bennett J.E. Bennett Consultants, Inc.
Foundation Loads Dead Load Live Load Wind Load
Delmar Boulevard bridge replacement over Interstate 170.
Repair and Strengthening of Concrete Bridges and other Structures
LOI # Pilot Program Design & Related Services for Development of Accelerated Bridge Construction Standards & Pilot Bridge Construction.
Construction Methodology for Suramadu Main Bridge.
P3 (Preventive Pile Protection)
Initial Condition Assessment: Concrete Traffic
Level II Inspection.
Structural Slab Analysis
TOTAL BRIDGE REPLACEMENT OF M-13 OVER CHEBOYGANING CREEK
CIVI 6061-Strengthening of bridges using FRP
Offsite manufactured Bridges
Concrete Bridge Decks Large Percentage of All Bridge Decks (over 90%)
High Bridge Re-Deck Project
Introduction to Bridge INspection
Oregon DOT Integral Abutment Design Criteria
Project Purpose and Objective
Ness Bridge Construction
INTEGRAL BRIDGES Guided by: Dipu.V.S Lecturer Civil Engg Dept
New Bridge Construction
US26: Cornelius Pass Rd -185th Ave
Board of Commissioners Meeting
Site Based Preconstruction – Enabling Work
Standards, Best Practice Guidances and Thresholds
Narrows Bridge - Perth Concrete Repair Works
Protective surface finishes
Post Seismic Bridge Inspection
Presentation transcript:

Superstructure Replacement Substructure Repair Rehabilitation of I-95 Bridges 11 Bridges Along I-95 Corridor

ROLLED BEAMS  Existing deck is 7-1/2” thick  Replacement deck creates overstress in beams  Category E fatigue detail at cover plate ends  Paint is in poor condition and lead based  Replace steel beams

Lombardy/CSX Bridge 12’ Shoulders (8’-8” Widening Each Side) Robin Hood Rd. Bridge Ramp Extension (14’-8” Widening SBL) Sherwood Ave. Bridge Ramp Extension (14’-8” Widening SBL) Rehabilitation of I-95 Bridges Bridge Widening

Preconstructed Composite Units (PCU) Rehabilitation of I-95 Bridges Superstructure Replacement

PCU’s Chosen option uses Pre-Constructed Units assembled in a casting yard, trucked to site and lifted into place by cranes PCU Being Placed during early test day PCU ready in Casting Yard

Construction Sequence

Construction Sequence Setup of Maintenance of Traffic Traffic Shifting Traffic waiting to Shift Moveable Traffic Barrier Setup Initiating MOT

Construction Sequence Preparation for PCU Repair Bearing Pads Cut Deck and Diaphragms and remove Existing Repaired Pier Cap

Construction Sequence Preparation & Installation Moving PCU to Pick up Point Placement of PCU

Construction Sequence Placing PCU Aligning PCU & then Disconnecting

Match-Cast Longitudinal Joint Cast-in-Place Closure Pour Highly Skew Bridges Lombardy / CSX Robin Hood Hermitage Westwood Rehabilitation of I-95 Bridges

Surface Repairs at Abuts. & Piers Pier Cap Replacement 5 Piers for Lombardy/CSX Bridge Pier Cap Strengthening Infill Wall between Columns on Piers at Boulevard Bridge Rehabilitation of I-95 Bridges Substructure Repair

Cathodic Protection Chloride Extraction (ECE) Sealing Concrete Surfaces Pier Caps Rehabilitation of I-95 Bridges Substructure Repair

SCS’s Role in 11 Bridges

Condition of Structure Cost of Maintenance Internal Damage First Visible Damage Critical Point Damage Accelerates Potential Failure Corrosion Cost Progression

Temporary Piers

Corrosion Damage

How much delam/spall existed at the time? Chloride presence at various depths? Future penetration & effects of chlorides? Active corrosion occurring? How quickly? Existing and future damage? Presence and progression of ASR? High risk of prescribing a poor solution without proper diagnosis… Evaluation

Boulevard - Structure Total Chloride Concentration Histogram

Line Scan 28 Line Scan 29 Abutment Wall

GPR – Good Concrete

GPR – Delam. Concrete

Visible concrete damage – significant increase  Developed a concrete damage % for each element Average recorded cover – low Majority of potential readings – active corrosion High chloride readings behind rebars Near future concrete damage will result Significant weakening of the structure within five years Conclusions

Based on a unique methodology, we developed recommendations for repair / replace / life extension Concrete repair on all bridges ECE to lower the chloride concentration on certain bridges certain bridges Sacrificial CP on the rest of the bridges Sprayed Zinc – widely used, easy to apply Recommendations