How to make a Progress Report Activity Reporting Lead partner and partner seminar Voss, Norway June 2008 Maxi Nachtigall
Project partner: Statement of Expenditure + documentation National controller: First level control - Certificate of Expenditure Lead Partner: - Activity report - Project Claim - Certificates of Expenditure - Summary of COE JPS-MA-CA Assessment and payment of grant Project partner: -Certificate of Expenditure + Partner Activity Report Activity Report - Activity report - Project Claim - Certificates of Expenditure - Summary of COE
Why to report? Monitoring of project by - PMC - MA - Secretariat Guarantee satisfactory project implementation Continous measurement and quantifiaction of project outputs Cross-check project application/ decision vs implementation Information and knowledge to broader public
What to report? Activity Report template on (template launch 1 September 2008) 9 Sections: General information Project Activities and Performance Project Indicators Project Financial Information Project Management and Partnership Dynamics Horizontal Principles Project Communication Additional information
Section 1 General Information Project title Acronym and Duration Priority and Target Area Partnership information Based on the information from the application Note: Changes need prior approval by the Secretariat Lead partner’s written request to Secretariat by mail
Section 2 Project activities and performance Executive summary of the reporting period (last 6 months) Progress on project implementation Overview on project activities Information on outputs achieved so far with focus on products and services Project activities Highlights of the project implementation activities Inter linkage of WPs Description WP structure and WP activities Accumulatively Chronologically In comparison to approved application Results All WPs
Section 2 Project activities and performance Change of activities in comparison to approved application Any activity changes need pre-approval by Secretariat Justification of the change and impact on implementation of project 1 request for change per year Project outcomes Overall description of project implementation process Status of development of products and services (outcomes so far, compared with objectives set out in application) Description of innovative features of developed products and services Transnational impact Could the product/ service being transferred to other countries How does it make a difference across the region Organisational learning? Added value of the adopted transnational approach
Section 3 Project Indicators General indicators based on indicators outlined in application and decision Priority specific indicators Activity Output Result Additional project indicators Project activity and outcome performance Analysis of project activity and outcome performance in relation to: Indicators Time plan Budget
Section 4: Project Financial Information Analysis of the financial performance in comparison to budget Underspendings/ Overspendings/ Unexpected expenditures % of budget spent vs. % of time spent according to project plan Will the project keep in the budget and still achieve outputs Good value for money Could have been more achieved with the same inputs of money or could same outcomes have been achieved with reduced financial inputs? General questions on efficiency of budget use and value for money achieved Cross referring to the financial report Budget changes Justification for the change Description of impact of changes for the project implementation 1 request for change per year
Section 5: Project management and Partnership dynamics Description of Project Management structures Analysis of Project Management dynamics Arrangements that were used to implement the project, involved partners List of issues discussed List of decisions taken Description of impact of decision on project implementation Dynamics in the project partnership Advantages of the transnational partnership approach Challenges of international cooperation in transnational setting
Section 5: Horizontal Principles Equal Opportunities Gender: provision of day care for children during partner meetings Age: Special tailored staff recruitment plan for young employees Social: Special employment plan for indigenous people Sustainable Development Implementation of Sustainable impact assessment tool for resource use Minimized travel plan for meetings – ICT solutions, use of environmental friendly transportation, voluntary carbon offset Corporate Social Responsibility (CSR) plan Transnational/ shared use of rescue equipment
Section 6: Project Communication Indicating number of tools/ methods of external and internal communication used/ realised in the project implementation Based on an communication indicator list Accumulatively Summary of Communication activities Analysis of activities performed to ensure that project outcomes are publicised – status/ evaluation of success of implementation of project communication plan Are minimum requirements met within first 6 months How does the project ensure transnational dissemination
Section 7: Changes in project partnership, indicators and other changes Additional changes in comparison to the approved application/ to the decision All changes require pre-approval by Secretariat: Partnership Target area Indicators Duration Work packages’ structure
Section 8: Additional information Feedback and Suggestions To NPP bodies Cooperation and procedures Reporting and claiming Overview on supporting documents requested Project claim Certificates of expenditure Summary of certificates of expenditure Examples of information/ dissemination material
Processing of Activity Report Please send the Activity report as part of the Progress report together with other required documents to: Northern Periphery Programme Secretariat Att.: Responsible Desk Officer Strandgade 91, 4.Sal DK-1401 Copenhagen-K Denmark and per
No report – No money!!!