FABRICATION OF BLOCKS OWNERS REQUIREMENT DESIGN CLASSIFICATION SOCIETY PROCUREMENT SURFACE PREPATION CUTTING FABRICATION ERRECTION
OWNERS REQUIREMENT CONTRACT WORKING SPECIFICATION VESSELS PARTICULARS MACHINERY AND EQUIPMENTS PAINTING SPECIFICATION CLASSIFICATION SOCIETY.
DRAWINGS DESIGN SECTION. BASIC DRAWING CONSTRUCTIONAL DRAWING AS PER BLOCKS CUTTING PLAN (NESTING)
CLASSIFICATION SOCIETY BASIC DRAWING APPROVAL CONSTRUCTION DRAWING APPROVAL MATERIAL APPROVAL WELDING PROCEDURE APPROVAL WELDERS QUALIFICATION APPROVAL
PROCURREMENT OF MATERIAL(STEEL) CLASSIFICATION SOCIETY DIMENSION AS PER DRAWINGS & CUTTING PLAN GRADE OF MATERIAL AVAILABILITY.
STACKING OF MATERIALS
LOADING OF PLATE ON ROLLERS FOR SURFACE PREPARATION THE PLATE HAS TO BE DRY AND FREE FROM GREASE OIL ETC.BEFORE BLASTING.
SURFACE PREPARATION BLASTING Abrasive used for blasting sand Copper grit Iron grit CLEANING
SHOP PRIMER PAINTING Shop primers are thin coatings which are applied to steel plates and profiles after blast cleaning to provide temporary corrosion protection during transport, storage and production.
PAINTING
PAINT DRYER
STACKING OF PLATES
CUTTING OF PLATES CUTTING PLAN Nesting of plates as per drawing. NOTE:-Nesting is done taking in consideration the shrinkage area after welding. Program is fed to the CNC cutting machine. Plate placed on the cutting bed is as per the dimensions in the program fed. Plate squareness is checked & cutting is proceeded according to the program.
PARTS CUT FROM PLATES FLOORS MARKING ON FLOORS
EDGE PREPARATON
BENDING OF PLATES
TEMPLATES
BLOCK FABRICATION (e.g. Double Bottom) SUBASSEMBLY Bottom panel Tank top panel Floors Girders Bulkhead Margin brackets
SUBASSEMBLY BOTTOM PANEL TANK TOP PANEL
SUBASSEMBLY FLOORS GIRDERS MARGIN BRACKETS BULKHEAD
UNIT ASSEMBLY Fitting & welding Tank top panel shifting Floor, girder, bulkhead and margin bracket fitting to the tank top panel and its welding. Pipe line fitting and welding accept end connections Bottom panel fitting. Bilge plate fitting and welding.
Bilge plate fitting and welding
Welding The block is toppled and welding of floors, girders, bulk head and margin brackets to the bottom panel is carried out ,this is done to change the position of welding from overhead to down hand. As down hand welding is faster then overhead and also consumable required is less. Dry survey is carried out .
STACKING OF BLOCKS
FABRICATED BLOCKS Aft block. Bulbous bow
Erection of blocks
Joining of Mega Blocks
Test to check the soundness and water tightness of blocks NDT Ultra sonic testing Radio graphic testing Magnetic particle testing Die penetrant testing/ Liquid penetrant testing. WATER TIGHTNESS Air pressure test Hydrostatic test Hose test.
Painting of blocks Surface preparation as per painting specification. Cleaning of surface from water, grease, oil etc. Blasting, buffing (power tooling). Cleaning of grit after blasting and surface inspection. Painting as per specification.
Launching Pre launching Activities Under water survey Drain plug fitting Over board valves to be closed. Anode fitting to be checked. Propeller to be locked. Rudder to be locked. Clearing the path of slipway etc. Launching.
Final out fitting Sea trials Delivery.