GlueX Solenoid Update George Biallas May 12, 2010 GlueX Collaboration Meeting.

Slides:



Advertisements
Similar presentations
Zian Zhu Superconducting Solenoid Magnet BESIII Workshop Zian Zhu Beijing, Oct.13,2001.
Advertisements

Muon g-2 Muon g-2 Experiment Quarterly Report Aria Soha All Experimenter’s Meeting March 2, 2015.
GlueX Solenoid Recent progress and Coil cold tests Paul Brindza September 9, 2004.
Coupling Coil Test Facility Update Ruben Carcagno Fermilab September 20, 2012.
CEA DSM Irfu - Bernard GASTINEAU - R3B Technical Board Meeting -April 4, Reactions with Relativistic Radioactive ions Beams GSI Large Acceptance.
Step IV Infrastructure update STFC Tim Hayler Eddie Holtom Norbert Collomb Graham Stokes 14 th December 2011 MICO170 meeting 1Tim Hayler.
1 MICE PM Report General Update –Phase I civil engineering –R5.2 in June –Phase II design work –Phase II hardware –A few questions –Schedule, milestones.
Spectrometer Solenoid Design and Procurement Review Steve Virostek Mike Green Mike Zisman Lawrence Berkeley National Lab MICE Collaboration Meeting October.
Global Magnet Systems including Field Mapping MICE Project Board 28 th June 2011 M Courthold – RAL R Preece - RAL.
Spectrometer Solenoid Fabrication Update Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 14, 2009.
1 MICE PM Report Installations to date Future installation work Preparations for Phase Two Target status MICE Video Conference, 22nd May, 2008.
1S. Virostek - LBNL Spectrometer Solenoid Fabrication Update S. Virostek and M. Green are visiting vendor today for progress update Vendor expects to complete.
Spectrometer Solenoid Update Steve Virostek - LBNL MICE Video Conference #145 December 15, 2011.
Spectrometer Solenoid Fabrication & Testing Update Steve Virostek Lawrence Berkeley National Lab MICE CM24 at RAL June 1, 2009.
1S. Virostek - LBNL Spectrometer Solenoid Fabrication Update Vendor still expecting to complete first magnet by the end of November, before X-mas more.
1 Status of infrastructure MICE Video Conference, August 17, 2005 Yury Ivanyushenkov Applied Science Division, Engineering and Instrumentation Department.
Update Hardware for conductive cooling of the quench resistors has been fabricated at LBNL. Preparation for installation to start this week. Installation.
Spectrometer Solenoids and Coupling Coils Primary Activities and Risks Going Forward Spectrometer Solenoids Completion of SS#2 magnetic mapping Completion,
We are Here! Gluex Collaboration Meeting May Engineering Status - Presented by Tim Whitlatch1.
RF Cavity / Coupling Coil Module
1 Cryostat assembly, integration and commissioning procedures M.Olcese Version: 07 May 2008.
1 Summary of MICE beamline & hall installations This is a very rough summary of the progress since mid-December Richard Apsimon & Andy Nichols MICO meeting.
Spectrometer Solenoid Update Steve Virostek Lawrence Berkeley National Lab Roy Preece Rutherford Appleton Lab October 28, 2011 MICE Collaboration Meeting.
MICE RFCC Module Update Allan DeMello Lawrence Berkeley National Laboratory MAP Winter Collaboration Meeting at JLab, Virginia February 28, 2011.
Status and Integration of the Spectrometer Solenoid Magnets Steve Virostek Lawrence Berkeley National Lab MICE RAL June 15, 2007.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
Preparations in the MICE hall Video Conference 25 th June 09 Tim Hayler Andy Lintern Peter Lau Geoff Barber.
Magnetic Shielding Issues Roy Preece STFC - RAL. Overview Issues Items in harms way – Step IV Step IV mitigation plan –Racks –Compressors Current / Future.
Hall C Meeting SHMS Magnets and Support Structure Design and Procurement Status Paul Brindza January 26, 2009.
Injector/Re-injection Chicane Michael Bevins May 17, GeV Upgrade - Beam Transport Injection, Linac, Extraction, & Correctors Preliminary Design.
Schedule and Work We are moving into a very intensive 4 months with a lot of work to be carried out Electrical services to the devices – after the South.
MICE CC Test Status Ruben Carcagno 11/06/13 1. Cooldown Coil Temperature (calculated average in each of 8 coil segments) SC Transition (voltages across.
Spectrometer Solenoids MICO 214 Steve Virostek LBNL February 6, 2013.
Spectrometer Solenoid: Plans to Fix Magnet 2 Steve Virostek Lawrence Berkeley National Lab Spectrometer Solenoid Review November 18, 2009.
Status of the MICE Project & Dashboard MICE Project Board 14 th November 2013 Roy Preece.
Spectrometer Solenoid Overview Roy Preece 31 st January 2011.
Progress to Date PPPL Advisory Board Meeting May 20101NSTX Upgrade – R. L. Strykowsky CD-0 Approved February 2009 The NSTX Upgrade Project organization.
Spectrometer Solenoid Fabrication & Testing Update Steve Virostek Lawrence Berkeley National Lab MICE CM25 at RAL November 6, 2009.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
Curtis A. Meyer 20 May, 2004 GlueX Detector Infrastructure The issue of infrastructure includes details of how we assemble the detector as a whole. How.
Spectrometer Solenoid Update Steve Virostek Lawrence Berkeley National Lab MICE Collaboration Meeting #28 Sofia, Bulgaria.
MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
Spectrometer Solenoid Fabrication Status and Schedule RF Cavity / Coupling Coil Module Plan and Progress Steve Virostek Lawrence Berkeley National Lab.
Spectrometer Solenoid Fabrication Update Steve Virostek Lawrence Berkeley National Lab NFMCC at LBNL January 25, 2009.
1 Integration and Milestones Elton Smith Hall D Detector Review October 20-22, 2004.
Hall D infrastructure and integration Elton Smith Hall D Collaboration Meeting September 9-11, 2004.
Spectrometer Solenoid Update Steve Virostek Lawrence Berkeley National Lab MICE Video Conference 120 May 7, 2009.
1 Mice Collaboration Meeting CM27 STFC Rutherford Appleton Laboratory, UK 7 th -10 th July 2010 Daresbury Laboratory Electrical Infrastructure Report Authors.
Installation of the T600 at Fermilab CSN2, September 22,
Status of the MICE Construction Project Resource Loaded Schedule Review 29 th April 2014 Roy Preece.
DON LYNCH NOVEMBER 6, AGENDA November 4, BABAR Magnet Update Global Design Concept – Update Outer HCal Structural Analysis (2 nd pass) sPHENIX.
OsC mtg 15/10/2014 MICE Step IV Alan Grant. Content Step IV – Construction Status – Finances – Schedule – Risks – Summary 2.
Technical Board Summary Alan Bross MICE CM17 CERN February 25, 2007.
LCLS-II Prototype Cryomodule Vacuum Vessel and HGRP Tom Peterson 4 December 2014 Design Review.
Tuesday 9 th January Project Status Report Project Achievements Project Schedule Issues Finance Summary Risk Register Photos.
Overview of On-going Cryogenic Work At the MTA Barry Norris AD/Cryo February 14, 2005.
XVII SuperB Workshop and Kick Off Meeting - La Biodola (Isola d'Elba) Italy May 28 th June 2 nd 2011 P.Fabbricatore Sezione di Genova Reuse of Babar sc.
Proton PMG September 3 rd 2015 Cons Gattuso AD Shutdown Manager.
Schedule and Milestones Roy Preece STFC RAL FAC 17 th April 2015.
Superconducting Cryogen Free Splittable Quadrupole for Linear Accelerators Progress Report V. Kashikhin for the FNAL Superconducting Magnet Team (presented.
S A Griffiths CM42 June 2015 Electrical & Control.
WBS 1-7 System Assembly & Installation John Voirin August 10-11, 2011.
Status of the MICE Construction Project
MICE CM31 Schedule summary
Teleconference ACS – FREIA 20th February 2018
SNS Cryoplant Commissioning Past Experiences
Hall D Cryogenic requirements
Daresbury ESS In-Kind Contributions
Polarized 3He target installation
Presentation transcript:

GlueX Solenoid Update George Biallas May 12, 2010 GlueX Collaboration Meeting

Update: May 2010 Lehman Review Findings Recent review of existing SC solenoid concluded: Design & fabrication of a replacement solenoid would delay CD-4 significantly Refurbishment of the existing solenoid should continue. Leaks and shorts to ground are being repaired. Shorts to the supporting strip cannot be repaired. Individual coil tests will complete in May Full solenoid tests, with realistic operating conditions, will complete in September Comments: The solenoid is prone to shorts. In GlueX, it will be operated under different conditions than in the past, and its coils will be exposed to larger mechanical forces. Consequently, there is risk of new shorts that could compromise operation or permanently damage the solenoid during a quick discharge.

Update: May 2010 Lehman Review Continued Analysis of the impact of shorts should be extended to worst case situations. Means to reduce risk of permanent damage should be developed, for instance by decreasing induced voltage in shorted turns, e.g.by reducing discharge voltage or using additional low heat load current leads and cold diodes. Design & structural analysis of coil supports against axial forces should be completed. Means should be pursued to shorten the projected schedule for producing a replacement solenoid. Refurbishment and testing of the existing solenoid should continue expeditiously. The SC solenoid is a critical component of the GlueX Spectrometer, which is a centerpiece of 12 GeV Upgrade Project. Recommendations Initiate design of a back-up, replacement solenoid now. Convene an external peer review to review risk mitigation plans and to advise regarding implementation of a replacement solenoid. Report on outcome at next DOE review.

Update Continued Response to Lehman Review Evaluating Turn–to-Turn failure mode Re-convening the internal review board tomorrow Solenoid Coils Refurbishment Coil 1 – In final leak test Coil 3 – IUCO starting to apply new, stainless steel shield Coil 2 – taken apart in the test lab for Sub Coil 2D buttressing Coil 4 – Ready to Test Coil Testing Cryo Can nearing completion at Meyer Tool & Manufacturing for May –June delivery Some Mechanical Hardware in fabrication – Anaconda support Platform assembled, Rails and mounting surfaces installed for yokes A few auxiliary items in design and bidding Chimney interconnect piping and shield, Top of Cryo Can relief stack Yoke ring movement in contracting

Update Continued Controls Substantial activity continuing – Elliot Wolin and a great cast of Electrical Folk – Most hardware on hand, Racks being wired PLC Programming in last stages, Screens being worked Analysis of Pressure System – Use of Access plates in Vacuum Vessel as reliefs to keep any overpressure very low was successful, trial of two examples opened at 15 psig – use on 3 coils – Coil 2 needs further work because Yoke blocks venting Hall D Installation Jack stands given to Concrete Pier Contractor Design of Magnetic Baffles, Yoke gap fillers, BCal supports 90 % detailed Design of Cryo box, U-tube Can, Cryogen Transfer Line, Piping and relief system well under way

Solenoid Coil Test Set Up Page 6 Detail designs complete on all long lead items Cryo Can due in June All hardware ready by end of May Racks complete (and tested) by early June Power supply in place Rails/Supports in place Anaconda Cryo Can Power Supply Rails Coil 1 End Plate Racks

Test Platform Assembled

Solenoid Test/Repair Set Up Rails ready to be grouted Coil 1 & 2 being repaired Page 8

Solenoid Repair/Test Manpower 3 Hall D Staff Techs 1 Full time Magnet Tech. Hall D Work Coordinator 2 Mechanical Engineers 3 Designers Help as needed from JLAB Mechanical Inst’l, Vacuum, SRF, Physics Electronics and Engineering Electrical Fab groups. (Tasks include rigging, leak check, wiring, cable fab) IUCO Repairing Coil #3 Page 9

Solenoid Control Racks Page 10 Fully Populated and Ready for wiring!

Summary Repairs nearing completion Test setup underway Testing will prove that repairs are robust Staff in place for repair and tests Confidence in repairs Technical/Safety review for repairs and testing scheduled for end of May. Still 1 month free float on BCAL inst’l Page 11