USING MS PROJECT 2010 Project management software programs such as Microsoft Project 2010 can be used for developing the project schedule and budget, and.

Slides:



Advertisements
Similar presentations
Microsoft Project Tutorial for Chapters 6 & 7
Advertisements

OPMA 5364 Project Management Part 5 Project Scheduling
WBS: Lowest level OBS: Lowest level
USING MS PROJECT Project management software programs such as Microsoft Project can be used to compute the earliest and latest start and finish times and.
CIS 480 Systems Analysis and Design
Project Scheduling: PERT-CPM
Microsoft Project Entering and Organizing Tasks Adapted from the Microsoft Step by Step Series by Aaron Schroeder.
PRJ566 Project Planning and Management Lecture: Network Diagrams.
PRJ566 Project Planning and Management Lecture: Dependencies and Network Diagrams.
Chapter 3 Project Management.
PERTEMUAN 3 PPSI Microsoft Project Presentation. What is a Gantt Chart? A Gantt Chart is a visual tool to help Plan, Manage, and Track a project or projects.
MS Project Tutorial EMEN. Entering Project Properties Choose File Properties Click the Summary tab You can now enter general information about the project.
CPM, Crashing, Resource Leveling using MS Excel & MS Project
Microsoft Project Tutorial for Chapters 4 & 5 This Tutorial explains how to: Build a MSP Project Network Build a Probabilistic MSP Network Use the Calendar.
1 Lecture by Junaid Arshad Department of Engineering Management Abridged and adapted by A. M. Al-Araki, sept WBS: Lowest level OBS: Lowest level.
CSSE Sep.2008 Constructing and Analyzing the Project Network Diagram Chapter 6.
CSSE 372 Week 6 Day 2 Constructing and Analyzing the Project Network Diagram  PERT Chart PERT was invented for the Nautilus submarine project. Ok, maybe.
Microsoft Project.
McGraw-Hill/Irwin © The McGraw-Hill Companies, All Rights Reserved Creating Gantt Charts With Microsoft Project Technology Plug-In T12.
Projmgmt-1/18 DePaul University Evaluating Schedule In MicroSoft Project Instructor: David A. Lash.
Project Plan Optimization Lesson 13. Skills Matrix SkillsMatrix Skill Make time and date adjustments Adjust fiscal year settings within Microsoft Project.
Project Basics Lesson 1. Skills Matrix SkillsMatrix Skill Start Microsoft Project Standard Create a project planOpen a new project plan Specify a start.
EMGT 501 HW #2 Answer. 020/3 X 3 05/601-1/62/3050/3 X 6 0-5/300-2/3-1/3180/3 (c).3/230with )3/80,0,0,3/50,3/20,0(*)*, ( solution Optimal   Z.
EMGT 501 HW #2 Solutions Chapter 6 - SELF TEST 21 Chapter 6 - SELF TEST 22.
OPSM 639, C. Akkan1 OPSM 639 Project Management Introduction to Microsoft Project - Part 2: Developing a Network Plan.
Microsoft Project Presentation By Corey Johnson 10/11/00.
USING MS PROJECT Project management software programs such as Microsoft Project can be used for developing the project schedule We demonstrate the use.
Copyright © Software Process Group 1 Software Process Group Microsoft Project Tutorial Steve Meyers
Project Time Management J. S. Chou, P.E., Ph.D.. 2 Activity Sequencing  Involves reviewing activities and determining dependencies.  A dependency or.
Project Management Software Tools Cheryl A. Wilhelmsen Lee Ostrom.
Chapter 6 Introduction to Microsoft Project
Tracking progress on tasks and assignments TUTORIAL # 3.
ERT461 BIOSYSTEMS ENGINEERING DESIGN 1 ERT424 BIOPROCESS PLANT DESIGN 1.
Refining Your Project Plan Lesson 4. Skills Matrix SkillsMatrix Skill Apply a task calendar to an individual task Change task typesChange scheduling formula.
Microsoft Project – Tutorial 2 Project Goal network company computers to easily share resources within a time frame of three months and within a budget.
1 Microsoft Project 2010 Demo Part 1. 2 Project: Initial Screen To start click Project/Project Information. Add start date.
Project Time Management J. S. Chou, P.E., Ph.D.. 2 Activity Sequencing  Involves reviewing activities and determining dependencies.  A dependency or.
TA. MARAM AL-KHAYYAL NET481 MS Project Overview. Outline Introduction to project management.  Project 2007 can help you manage project time, resources,
Microsoft Project Tutorial for Chapters 4 & 5 This Tutorial explains how to: Build a MSP Project Network Build a Probabilistic MSP Network Use the Calendar.
SOFTWARE PROJECT MGT. SESSION # 3– LAB MANUAL AMAN QUADRI
Microsoft ® Office Project 2007 Training Linking Project tasks [Your company name] presents:
Project Management Part 5 Project Scheduling. Topic Outline: Project Scheduling Identifying relationships among activities Project network diagrams Identifying.
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
Microsoft Project Tutorial Jesal Bhuta
Chapter 6: Project Time Management Information Technology Project Management, Fourth Edition Using Critical Path and MS Project 2003 Tuesday, February.
A tutorial on MS Project James Burns. 22 Learning Objectives  Entering Tasks in the Gantt View  Task subordination  Linking of Tasks  Setting start.
DECISION MODELING WITH MICROSOFT EXCEL Chapter 14 Copyright 2001 Prentice Hall Publishers and Ardith E. Baker Part 3 andand PERT CPM.
Irwin/McGraw-Hill  The McGraw-Hill Companies, Inc Project Scheduling IENG 321 IENG 321.
Microsoft Project Tutorial for CSCI 577 Fall 2006 Jesal Bhuta
Dependencies and Network Diagrams. Agenda Dependencies Milestones The Network Early/Late Start/End dates Slack/Float Critical Path.
Microsoft Project 2010 ® Tutorial 1: Planning a Project.
Microsoft Project 2010 ® Tutorial 5: Tracking Progress and Closing the Project.
Scheduling and Budgeting Engineers Without Frontiers CEE 402.
Project Management – Part 1. Overview What is a project? Project management techniques Activity lists Network diagrams Critical path analysis Gant charts.
Scheduling Scheduling : is the process of converting a project action plan into an operating time table. Why scheduling ? To answer the following questions:
CE 332 – Construction Engineering and Management
MICROSOFT PROJECT MODULE 2 - BUILD A HOUSE.
Microsoft Project 101: How to Build a Project Plan
Software project mgt. session # 3– lab manual.
Project Scheduling Chapter 14.
A tutorial on MS Project
Project Time Management.
ENGINEERING MANAGEMENT (GE 404)
Guide to Project.
Software project mgt. session # 3– lab manual.
Microsoft Project 2007 Demo Part 1
ENGINEERING MANAGEMENT (GE 404)
General Foundry Example of PERT/CPM
Information System Analysis
In-Class Scheduling Exercise
Presentation transcript:

USING MS PROJECT 2010 Project management software programs such as Microsoft Project 2010 can be used for developing the project schedule and budget, and tracking actual vs. planned progress We demonstrate the use of MS Project 2010 for a sample project Complete model found in construction.mpp on class web page Begin by launching MS Project 2010 M. J. Liberatore VSB 3008

MS Project 2010 Setup Select File, Options, click on “Schedule” tab For Calendar options for this project: “Select “All New Projects” For Scheduling options for this project: select “All New Projects” For New Tasks Created: select “Auto Scheduled” For Duration is entered in: select “weeks” For default task type: select “fixed duration” make sure New tasks are effort driven is NOT checked Click OK when finished

MS Project 2010 Setup

Creating a Project Click on Project, Project Information, select 10/3/11 as the Start date, click OK Click on Save as, type in project name such as Demo, click OK Your project is saved as Demo.mpp

Creating a Project

Example Project Task, Duration, and Immediate Predecessor Information for Construction Project IMMEDIATE DURATION TASKDESCRIPTION PREDECESSORS(WEEKS) 1START --0 2Excavate and Pour Footers 13 3Pour Concrete Foundation 21 4Erect Rough Wall & Roof 34 5Install Siding 46 6Install Plumbing 43 7Install Electrical 44 8Install Wallboard 6,75 9Lay Flooring 86 10Do Interior Painting 83 11Install Interior Fixtures 9,103 12Install Gutters & Downspouts 52 13Do Grading & Landscaping FINISH 11,130

Entering Task Information Default view, Entry table on left, Gantt Chart on right You can delete the two left-most columns, “i” and “task mode” by highlighting these columns and pressing the “delete” key (not needed by us) Task numbers now in left-most column Enter task name and duration in their field The default is weeks or “w” “d” for days and “h” for hours can be used Enter predecessor task number(s) in the “Predecessors” field MS Project automatically gives start and finish dates based on critical path analysis

Entering Task Information

Task Information Double-clicking on a task name opens the Task Information” screen

Project Charts The Gantt Chart view shows task linkages Since START and FINISH are dummy activities with 0 duration, they are milestones in MS Project (black diamonds) Right-click on dates in the chart and then “zoom” as desired Change view to Network Diagram by clicking on “View” in the menu and then select “Network Diagram” (zoom as desired)

Gantt Chart

Network Diagram

Critical Path Analysis MS Project 2010 automatically computes the critical path and the earliest and latest start and finish times and slack Project, Project Information, Statistics shows the critical path is 26 weeks in our project

Project Critical Path Length

Critical Path Analysis Use the “Detail Gantt” to best display the critical path Select “View”, “Other Views”, “More Views”, “Detail Gantt” then “Apply” Use the “Schedule Table” to display all of the early and late start and finish information, along with total and free slack Again from “View”, select “Table”, and then “Schedule”

Schedule Table & Detail Gantt

Critical Path Analysis Critical path tasks can be identified as those have zero total slack (TS) or float TS = LF – EF = LS – ES The TS of only 1 task can be used if we want to be certain about not delaying the project Free slack (FS) of a task is the difference between the smallest of the ES’s of the task’s immediate successors and the task’s EF. Using FS does not affect the start times of a task’s successors FS <= TS FS of multiple tasks can be used without delaying the project FS is shown on the Detail Gantt

Critical Path Analysis Notice that tasks 12 and 13 both have 7 weeks of total slack However, if task 12 uses this slack, it is not available to task 13, so its slack is not free Tasks 12 and 13 are linked, so delaying the start of 12 delays the start of 13 by the same amount

Summary Tasks Summary tasks can be used to better organize a project (see constructionS.mpp) We add three summary tasks: Structure, Interior, and Exterior Structure includes current tasks 2 – 4, Interior includes 6 – 11, Exterior includes 5, 12, 13 Example: highlight “Excavate and Pour Footers,” click on “Tasks”, click on” Summary,” enter “Structure” Indent first three tasks under “Structure” by highlighting them and selecting “indent” (thick green arrow going to the right)

Creating a Summary Task