Guy Crockford AB/OP OP Days, 7/2/2007 LHC Specific BI Systems This presentation reviews the status of the specific BI systems for the LHC. The work plan.

Slides:



Advertisements
Similar presentations
Jan Uythoven, AB/BTLHCCWG, 3 May 2006 Page GeV Commissioning Machine Protection Needs to be commissioned to: Prevent damage with the used, higher.
Advertisements

IEFC Workshop – 22/03/2011 JJ Gras on behalf of BE-BI 1.
Commissioning LHC Beam Instrumentation for Nominal Bunch Intensities Beam Commissioning Working Group June 15 th 2010 Rhodri Jones (CERN Beam Instrumentation.
Status and plans for LHC DC BCT systems P.Odier DC BCT hardware modifications Proposal for choice of acquisition system (VD80 or 24- bit ADC) for the CCC.
BI SW for LINAC4 On behalf of BE/BI/SW BI software development process Specifications List of BI Systems – Not covered: PSB ring systems Conclusions Lars.
Breakdown of tests foreseen in preparation for beam Equipment folder: tests results, handling of NC, performance below specs, machine as commissioned vs.
Matching and Synchrotron Light Diagnostics F.Roncarolo, E.Bravin, S.Burger, A.Goldblatt, G.Trad.
Eric Prebys USPAS, Knoxville, TN, Jan , 2014.
Distributed BI Systems BLM, BPM, BTV and BRAN Laurette Ponce & Fabio Follin Thanks to: Anthony Rey, Enrico Bravin, Rhodri Jones, Bernd Dehning, Mariusz.
LHC beams in the SPS in 2014 H. Bartosik, G. Rumolo, G. Iadarola With the help from K. Kornelis, V. Kain and SPS OP crew.
Feedback from MEF  Only possible, if COMMON COORDINATION MEETINGS  Main possible conflict: SAFETY –No “work permits” in the injectors. MEF working on.
B.O.S.S. SPS ring and transfer lines Serge Massot for BE-OP-SPS European Organisation for Nuclear Research CERN CH-1211 Genève 23 Switzerland 27/05/2014CERN.
LHC Utilities & Facilities WAO Daejeong 12/04 – 16/04/2010 Markus Albert on behalf of LHC Operations.
BCT for protection LHC Machine Protection Review April 2005 David Belohrad, AB-BDI-PI
ATF2 beam commissioning status and beam time request Toshiyuki Okugi 2008 / 11 / 12 ATF2 Commissioning Meeting.
:00: Prepared new fill B1: Q X =0.293, Q Y =0.269; lifetime = 25h ✔ B2: Q X =0.297, Q Y =0.267; lifetime = 5h ✗ Strong 50Hz and 100hz lines.
C. Fischer – LHC Instrumentation Review – 19-20/11/2001 Gas Monitors for Transverse Distribution Studies in the LHC LHC Instrumentation Review Workshop.
1 BROOKHAVEN SCIENCE ASSOCIATES Storage Ring Commissioning Samuel Krinsky-Accelerator Physics Group Leader NSLS-II ASAC Meeting October 14-15, 2010.
Eric Prebys Accelerator Physics Center Program Director, LARP December 7, 2009.
The Stripping Foil Test Stand in the Linac4 Transfer Line
Based on Lars’ progress report of LIU SPS BI Status of follow-up 13/10/2015Lars K. Jensen, V. Kain1.
H.Schmickler, AB-BDI Chamonix XIV workshop, CERN January 18, Beam Commissioning of LHC instrumentation Chamonix XIV, January 2005 H.Schmickler.
Nominal Workflow = Outline of my Talk Monitor Installation HWC Procedure Documentation Manufacturing & Test Folder Instantiation – NC Handling Getting.
Overview Consolidation projects for PS LIU-PS Main observable review Conclusion Acknowledgements S. Gilardoni R. Steerenberg G. Metral H. Damerau BI colleagues.
Updated Overview of Run II Upgrade Plan Beam Instrumentation Bob Webber Run II Luminosity Upgrade Review February 2004.
1 Commissioning and Early Operation – View from Machine Protection Jan Uythoven (AB/BT) Thanks to the members of the MPWG.
Post Mortem Workshop Session 4 Data Providers, Volume and Type of Analysis Beam Instrumentation Stéphane Bart Pedersen January 2007.
LIU-SPS progress for BE/BI L. Jensen on behalf of BE/BI 27/08/2015Lars K. Jensen BE/BI/SW1.
Outline Availability for BI (figures from Evian 2012) Availability seen from BI Sketch of control system with dependencies Tools used for BI availability.
Outline of 2014/2015 plans V. Kain, M. Lamont, J. Wenninger 6/18/2013Optics Measurement and Correction Review
CONTENT: Beam characteristics and MP concerns BI configuration Operational settings Collimators Planning Shift breakdown Thanks to: P.Baudrenghien, G.Bellodi,
The Dashboard The Working Conditions The Common Chapters State What’s Next.
Beam Instrumentation Overview Status for initial commissioning & recent results with BBQ & PLL LHC Machine Advisory Committee 7 th December 2006 Rhodri.
F Monitor of Beam in the Abort Gap Randy Thurman-Keup DOE Review of Tevatron Operations at FNAL March 29-31, 2005 a.k.a. Abort Gap Integrator (AGI)
MD377 Schottky diagnostic M. Wendt, M. Betz, T. Lefevre.
11/3/2010 CM15 Controls for LARP and LAFS - 1 Terri Lahey LARP/LAFS/CERN and SLAC.
Eric Prebys Accelerator Physics Center Program Director, LARP Important material Contributed by Elliott McCrory (FNAL), Ryoichi Miyamoto (BNL), Alan Fisher.
PS Complex Controls Renovation S Baird AB/ABP ATC/ABOC Days: Session Jan 2008.
The Minimum Workable LHC : Providers’ Commitments Summing-Up the following presentations: 1.ATB commitments and major issues [O. Aberle] 2.BI commitments.
Hardware Commissioning Review BDI Equipment
RF acceleration and transverse damper systems
The TV Beam Observation system - BTV
Beam Gas Imaging Kick-off meeting 30-Oct-2012
DRY RUNS 2015 Status and program of the Dry Runs in 2015
M.Fitterer, A.Patapenka, A.Valishev (FNAL)
LHC Commissioning with Beam
BE-BI Software for LINAC4
Mike Lamont on behalf of the LSA team
Friday 07:00 Power glitch on the EDF network. Point 8 affected.
Saturday 09:40 Stable beams #1369 (56 bunch scheme)
Fill 1410 revisited Peak luminosity 1.4e32 Beam current 2.68/2.65 e13
Wednesday /Thursday 09-11:00 Verification of the LSS6 interlocked BPMs: took longer to fill due to some problems with RF cavities in the PS. In the mean.
Distributed BI Systems
Machine Protection Xu Hongliang.
LHCCWG Meeting R. Alemany, M. Lamont, S. Page
Interlocking of CNGS (and other high intensity beams) at the SPS
Lost at 12:05 to power converter (RTQX2.R1) problem
Agenda 9:00-10:00 Beam Interlock System Changes Following the 2006 Audit Benjamin Todd 10:00-11:00 Beam Dump System follow-up from the 2008 Audit Jan Uythoven.
LHC Morning Meeting - G. Arduini
Tuesday 28th September Fill 1375 ongoing 09:00 Move in Roman Pots
Wire almost entirely through beam before BLM triggers dump
450 GeV Initial Commissioning with Pilot Beam - Beam Instrumentation
BI cont. *** Summary Matching Monitor test *** We only had ~15minutes of inject and dump, but managed to see a profile with ~9e9 p (!)
LHC dry-runs (BE-BI view)
Machine Protection System Commissioning plans
Thursday Fill 1364 (24 bunch) dumped at 07h
1v1.
The LHC Beam Interlock System
Tuesday End of fill 1393 Movement of suspicious Roman pots OK
Measurement of the beam (transverse) emittances
Presentation transcript:

Guy Crockford AB/OP OP Days, 7/2/2007 LHC Specific BI Systems This presentation reviews the status of the specific BI systems for the LHC. The work plan between now and the LHC machine cold checkout is described, and areas of concern, where resources still need to be allocated, are high-lighted.

OP days, 7/2/2007 G.Crockford CERN Contents  BI cold checkout coordination plan.  BCT Beam Intensity Measurements.  BGI Ionization Gas Monitor.  BBQ Base Band Tune Measurement.  BSRA Abort Gap Monitor.  BSRT Synchrotron Light Telescope.  BWS Wire Scanner.  Conclusions.

OP days, 7/2/2007 G.Crockford CERN BI Cold Checkout Coordination mandate  Define and document Commissioning procedures Performance evaluation methods  Organize BI-MD time with LHCCWG Based on operational scenarios  Report LHC-BI-TB, LHCCWG… Procedures and results  Linkman: Michael Ludwig

OP days, 7/2/2007 G.Crockford CERN BI Cold Checkout Coordination mandate (2)  Inside All BI-LHC Instruments Public SW interface: assessment, reliability, errors… Performance assessment (with and without beam) Documentation of procedures, evaluation methods, results Report to working groups  Outside Specific instrument application software development Safety and machine protection (but aware of) Documentation of software interface (necessary as input for test procedures) Extras such as fixed-displays, sequencer tasks, logging

OP days, 7/2/2007 G.Crockford CERN BI Website.

OP days, 7/2/2007 G.Crockford CERN BI Experts and responsibilities

OP days, 7/2/2007 G.Crockford CERN Commissioners per instrument  Close collaboration between BI/OP/ABP

OP days, 7/2/2007 G.Crockford CERN Test Procedures, documentation. EDMS  Work in progress. Expect for end of this year.

OP days, 7/2/2007 G.Crockford CERN MTF, View online status of test progress

OP days, 7/2/2007 G.Crockford CERN Our Wiki page

OP days, 7/2/2007 G.Crockford CERN BCT: Beam Current Transformer  BCTDCLHC: DC Transformer, 4 Loss rates, DC beam lifetime Injection, Acceleration and Coasting beam  BCTFDLHC: Fast BCT, Dump lines, 4  BCTFRLHC: Fast BCT, ring, 4 Bunch by bunch measurements  Bunch currents, lifetimes and loss rates Turn by turn measurements  Intensity during first n turns  Intensity information for beam presence flag

OP days, 7/2/2007 G.Crockford CERN BCT: Status  Among the better documented instruments.  Hardware P.Odier (slow), D.Belohrad (fast)  Real-time and front-end software Michael Ludwig  OP dedicated application, fixed display Markus Albert

OP days, 7/2/2007 G.Crockford CERN BSRA: Abort Gap monitor  Continuous verification of abort-gap 3us rise time of the Dump extraction kicker (MKD) 2 BSRA installed  Responsible Hardware: S.Hutchins Real-time front-end: S.Bart-Pedersen Application: Black-box for OP/CCC (?)

OP days, 7/2/2007 G.Crockford CERN BGI: Ionization Gas Monitor  H & V beam profile measurements  Works for Ion beams (BSRT does not)  Hybrid instrument Instrumentation controls, BI B-field magnet controls, AB/PO, LSA Gas injection controls, AT/VAC Controls for the latter 2 to be clarified.  2 BGI’s burnt during bake out (June) Should be replaced in time for checkout!

OP days, 7/2/2007 G.Crockford CERN BGI: Ionization Gas monitor (2)  Installed in LSSR4  Integration time 20ms H or V profile and position, B1, B2 Rest gas ionization signal  Measurement frequency 1Hz  Emittance measurement Given accurate knowledge of linear optics  Responsible Hardware: J.koopman Front-end software: A.Guerrero Operational application: ???

OP days, 7/2/2007 G.Crockford CERN BQBBQLHC: Base Band Tune Measurement  QH,QV measurements, B1, B2 Hardware for both FFT and PLL measurement systems. 14 BPL pickups, 4 BQK kickers Sensitive equip, install late as possible  Both slow controls and fast-feedback  Various excitation methods Chirp over range of frequencies Simple kick PLL

OP days, 7/2/2007 G.Crockford CERN BQBBQLHC (2)  Responsible Hardware: M.Gasior Real-time & Front-end: P.Karlsson Feedback: R.Steinhagen Application software: R.Steinhagen  Help from OP for both requirements and software effort requested

OP days, 7/2/2007 G.Crockford CERN BQHTLHC: Head Tail monitor  Chromaticity measurement Relies upon periodic de-phasing and re- phasing between the heat and tail of a bunch with non-zero chromaticity Requires turn-by-turn beam position measurement using a stripline coupler  Responsible Hardware: R.Jones Front-end software: S.Bart-Pedersen Application software: R.Steinhagen +OP?

OP days, 7/2/2007 G.Crockford CERN BQSLHC: Schottky pickup  Foreseen for phase II But pickups ready and installed  4 BQS Schottky pickups Hardware developed at Fermilab Uses same front-end software as BBQ system. Application software  No HR effort defined at present  Possible future LAFS collaboration effort?

OP days, 7/2/2007 G.Crockford CERN BSRT: Synchrotron Light Telescope  Beam image collected by cameras From Synch radiation emitted by beam Onduler magnet required for signal enhancement up to 2TeV  Requires control and calibration of onduler current vs beam energy, LSA software.  Separate slow and fast device in 2 FEC Implemented as separate FESA class Fast camera device triggered by BST turn clock, 1 image every 25ns

OP days, 7/2/2007 G.Crockford CERN BSRT: Synchrotron Light Telescope (2)  Responsible Hardware: S.Hutchins Front-end software: A.Guerrero Application software: E.McCrory  LAFS

OP days, 7/2/2007 G.Crockford CERN BWS: Wire Scanner  Profile measurement H or V projections, B1 and B2 Individual bunches up to whole beam The calibration device for other transverse profile monitors (BSRT, BGI, BTV)  Delicate instrument, not for standard operation. Normally to be used with a single bunch Strict intensity vs energy limitations Risk of burning wire, exceed quench limit

OP days, 7/2/2007 G.Crockford CERN BWS: Wire Scanner (2)  Responsible Hardware: J.Koopman Front-end software: A.Guerrero Application software. E.McCrory  As part of the LAFS collaboration

OP days, 7/2/2007 G.Crockford CERN Conclusions  BI have a clear framework in place to prepare for the cold-checkout.  A close collaboration between BI, OP and ABP is encouraged!  Some instruments still missing manpower for application software.  OP fixed display requirements for BI need to be defined.  Interfaces to BIC, Sequencer need to be clarified.