Workshop Accelerator Operation 2012, SLAC S. Claudet (CERN, Geneva) on behalf of the “Cryogenics Group” Technology Department Operation of the LHC Cryogenics.

Slides:



Advertisements
Similar presentations
Status of Cryogenics at point 4 following the power cut L. Tavian 20 August 2011.
Advertisements

Cryogenic system in P4: Possible options S. Claudet & U. Wagner LHC Workshop, “Chamonix XlV” January 2005 (Mostly for RF & beam scrubbing)
Clara Gaspar on behalf of the LHCb Collaboration, “Physics at the LHC and Beyond”, Quy Nhon, Vietnam, August 2014 Challenges and lessons learnt LHCb Operations.
ESS Cryogenic System Design
ESS Cryogenic System Process Design Philipp Arnold Section Leader Cryogenics CEC – ICMC 2015 June 29, 2015.
SC - 04Feb'13Cryo Heaters Review Cryogenic Heaters Review Operation use and wishes S. Claudet - A. Suraci LHC Cryogenic Operation.
Large-capacity Helium refrigeration : from state-of-the-art towards FCC reference solutions Francois Millet – March 2015.
CRYOGENICS AND POWERING
CV activities on LHC complex during the long shutdown Serge Deleval Thanks to M. Nonis, Y. Body, G. Peon, S. Moccia, M. Obrecht Chamonix 2011.
H. Herzog, 22th-26th September 2008 Cryogenics Operations 2008, CERN, Geneva, Switzerland 1 CRYOGENICS OPERATIONS 2008 Organized by CERN LARGE SCALE CRYOGENIC.
Openlab Workshop on Data Analytics 16 th of November 2012 Axel Voitier – CERN EN-ICE.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
The cryogenic systems of the ATLAS and CMS detectors Johan Bremer on behalf of TE/CRG 06/06/2013AFF.
Accelerators for ADS March 2014 CERN Approach for a reliable cryogenic system T. Junquera (ACS) *Work supported by the EU, FP7 MAX contract number.
ORNL is managed by UT-Battelle for the US Department of Energy 2-K Pump Down Studies at SNS Presented at the CEC/ICMC 2015 – C3OrA Matthew Howell SCL Systems.
Workshop Chamonix XIV Shortcuts during installation and commissioning: risk and benefit H. Gruehagen, G. Riddone on behalf of the AT/ACR group 18 January.
LHC Cryogenics: “From cool-down & HWC to operation with beam” S. Claudet, for LHC cryogenics Extended LTC, 3 Mar’08.
Introduction to LHC cryogenic system (layout, architecture) Preparation before cool-down (Purge, flushing) Transient operations to reach nominal operating.
CERN plans towards energy efficiency Serge CLAUDET Nov 2014.
Frithiof Andreas Jensen Notes from: “Green Technologies developed at Research Infrastructures”
Cryogenic update before Fermilab meeting (and after the helium tank review) Coordination meeting 6 th May 2015 K. Brodzinski HiLumi-LHC-CC-Cryo-PPT-18_v1.
AT/ECR CRYOGENICS Organisation, Procedures and Communication with TCR Presentation for TCR-ECR-ACR Meeting 2003 by K. Barth.
ALICE Pixel Operational Experience R. Santoro On behalf of the ITS collaboration in the ALICE experiment at LHC.
S. Claudet - 31st May 2007Power refrigeration for LHC Power refrigeration at 4.5K & 1.8K for the LHC S. Claudet, CERN AT-ACR.
N.Delruelle, 22th-26th September 2008 Cryogenics Operations 2008, CERN, Geneva, Switzerland 1 CRYOGENICS OPERATIONS 2008 Organized by CERN Design choices.
An introduction to Energy aspects at CERN June 2014.
L. Serio COPING WITH TRANSIENTS L. SERIO CERN, Geneva (Switzerland)
Review of the operation scenarios and required manning of the activities P. Schnizer and L. Serio.
1 The ILC Control Work Packages. ILC Control System Work Packages GDE Oct Who We Are Collaboration loosely formed at Snowmass which included SLAC,
LHC Cryogenics HWC day 19 March 2009 Serge Claudet TE-CRG-OA (LHC Cryo OP)
Process Definition of the Operation Modes for Super-FRS Magnet Testing CSCY - CrYogenic department in Common System, GSI, Darmstadt Y. Xiang, F. Wamers.
Luigi Serio CRYOGENICS PERFORMANCE AND OPERATION L. Serio, on behalf of the LHC Cryogenics Operation and Cryogenics Performance Panel.
LHC Cryogenics for sector 45 and Perspectives S. Claudet, for LHC cryogenics HWC Review, 28 Fev’08.
Heat loads and cryogenics L.Tavian, D. Delikaris CERN, Cryogenics Group, Technology Department Accelerators & Technology Sector Friday, October 15, 20101HE-LHC'10.
AB/CO Review, Interlock team, 20 th September Interlock team – the AB/CO point of view M.Zerlauth, R.Harrison Powering Interlocks A common task.
Conclusions on UPS powering test and procedure I. Romera Acknowledgements: V. Chareyre, M. Zerlauth 86 th MPP meeting –
TE-CRG Activities D. Delikaris, TE-CRG.
1.8 K cycle and specificities CC: - 3D wheels - Bearings (300K) HX: - Very Low Pressure “Mixed” Compression P ratio ≈ 80 HX Stainless Steel Plate Axial-centrifugal.
ITER Liquid Helium Plants Status and Test Protocol ICEC June 29th, 2015 / Grenoble / FranceY. FABRE.
PIP-II Cryogenics Arkadiy Klebaner and Jay Theilacker PIP-II Collaboration Meeting 9 November 2015.
5-year operation experience with the 1.8 K refrigeration units of the LHC cryogenic system G. Ferlin, CERN Technology department Presented at CEC 2015.
LHC Cryogenics From cool-down to 1st beams Serge Claudet (LHC Cryo OP), On behalf of cryo teams involved.
RF Commissioning D. Jacquet and M. Gruwé. November 8 th 2007D. Jacquet and M. Gruwé2 RF systems in a few words (I) A transverse dampers system ACCELERATING.
LHC Cryogenics, equipment & interventions around P3/P7 S. Claudet, “volunteer” for TE_CRG 16 Oct’14.
CV works in the non- LHC accelerator complex during 2008 and plans for 2009 ATOP days 2009.
FCC Infrastructure & Operation Update on the cryogenics study Laurent Tavian CERN, TE-CRG 28 October 2015.
Cryogenics Operations 2008, CERN, Geneva, Switzerland 1 CRYOGENICS OPERATIONS 2008 Organized by CERN Industrial contributions to the maintenance of CERN.
LHC intervention scheduling with the Work Acceptance Tool
LCLS-II Technical Requirements
ILC Cryogenics: Study of Emergency Action and Recovery - in progress -
M Chorowski, H Correia Rodrigues, D Delikaris, P Duda, C Haberstroh,
Innovative He cycle Francois Millet.
Cryoplant Installation Scope
Dana M. Arenius Jefferson Laboratory Cryogenics Dept Head
SPS cryogenic proximity equipment and SM18 validation
CRYOGENICS – strategy, unavailability root causes and limitations
Update on HW commissioning
Hongyu Bai LCLS-II 2 K Cold Box FDR March 9, 2017
As energy coordinator for CERN Accelerators & Technology
Hollow e- lens, Cryogenic aspects
Use Cases - Cryo Services Speaker: Klaus Barth on behalf of TE/CRG
CEPC Cryogenic System Jianqin Zhang, Shaopeng Li
Why are particle accelerators so inefficient?
TEST PLANS for HL LHC IT STRING
The Fermi National Accelerator Laboratory is a U. S
ILC Experimental Hall Cryogenics An Overview
Operator Training Requirements
Cryogenic management of the LHC Run 2 dynamic heat loads
Review Bloc 4 and SM18 facilities and upgrade
Laurent Delprat CERN, Geneva, Switzerland
Presentation transcript:

Workshop Accelerator Operation 2012, SLAC S. Claudet (CERN, Geneva) on behalf of the “Cryogenics Group” Technology Department Operation of the LHC Cryogenics system and interface with beam & machine operation

Workshop Accelerator Operation 2012, SLAC LHC Cryogenics, interface with beam operation2/30 Outline Introduction to LHC Cryogenics Operation, organisation and results Availability and interaction with beam operations Summary

Workshop Accelerator Operation 2012, SLAC LHC Cryogenics, interface with beam operation3/30 LHC accelerator 24 km of superconducting K, 8.33 T p-p collision cm -2.s -1, 14 TeV, 0.5 GJ stored energy Machine operation Technology

Workshop Accelerator Operation 2012, SLAC LHC Cryogenics, interface with beam operation4/30 Magnets Distribution Layout of LHC cryogenics 8 x 4.5 K 1’800 sc magnets 24 km & K 36’ K 130 t He inventory LHC cryogenics is the largest, the longest and the most complex cryogenic system worldwide

Workshop Accelerator Operation 2012, SLAC LHC Cryogenics, interface with beam operation5/30 How does it compare ? Tevatron, RHIC, Jlab, SNS, HERA, Tristan, … ITER Before LHC: existing experience for design, safety, controls, operation, availability, … We did not start from scratch!

Workshop Accelerator Operation 2012, SLAC LHC Cryogenics, interface with beam operation6/30 LHC compressor station (x8) MotorsOil/Helium CoolersCompressors 4.2MW input power Bldg: 15m x 25m

Workshop Accelerator Operation 2012, SLAC LHC Cryogenics, interface with beam operation7/ K Refrigerators (x8) K to 75 K K to 20 K - 41 g/s liquefaction LHe: 3’600 l/h 4m diam, 20m long, 100tons

Workshop Accelerator Operation 2012, SLAC LHC Cryogenics, interface with beam operation8/30 1.8K Units with cold compressors (x8) Axial-centrifugal Impeller (3D) Fixed-vane diffuser 3-phase induction Electrical motor (rotational speed: 200 to 700 Hz) Active magnetic bearings 300 K under atmosphere Cold under vacuum Inlet Outlet Pressure ratio 2 to 4 Spiral volute Cold Compressor 200 to 800 Hz) 125 g/s GHe from 15 mbar to P atm with 3 or 4 stages

Workshop Accelerator Operation 2012, SLAC LHC Cryogenics, interface with beam operation9/30 Electrical feed boxes for current leads LSSL2 of the LHC 48 Boxes, 1200 leads

Workshop Accelerator Operation 2012, SLAC LHC Cryogenics, interface with beam operation10/30 From LHC Magnet String test One LHC sector: production-distribution-magnets x 13.5 Extremely large installed cooling capacity Complexity associated with 1.8K units Extremely large distribution system => Recovery from failures can last from few minutes to 20 hrs, exceptionally 2-3 days Total for 8 sectors: Compressors: 64 Turbines: 74 Cold Comp.: 28 Leads: 1’200 I/O signals: 60’000 PID loops: 4’ km

Workshop Accelerator Operation 2012, SLAC LHC Cryogenics, interface with beam operation11/30 Interfaces: follow-up electrical perturbations EL perturbations and their impact on our LHC Cryo system Duration [ms] Electrical systems recover in ms Cooling systems recover in min Cryo systems recover in hrs => A big incentive to be as tolerante to glitches as possible Voltage change [%] Typical tolerance envelope

Workshop Accelerator Operation 2012, SLAC LHC Cryogenics, interface with beam operation12/30 Main reasons to superconducting Compactness through higher fields E beam ≈ 0.3. B. rE beam ≈ E. L [Gev] [T] [m][Gev] [MV/m] [m] Capital Cost Operating Cost For accelerators in high energy physics Saving operating energy Electromagnets:Acceleration cavities Resistive: P input ≈ E beam P input ≈ Rs.L. E 2 /w Superconducting: P input ≈ PrefR s ≈ R BCS + R o R BCS ≈ (1/T) exp(-BT c /T) Be sure that at design stage, working at higher temperature was considered, but not selected to maximise LHC beam energy => Cryogenic systems takes longer to recover from failures than conventional ones (but we work on it!)

Workshop Accelerator Operation 2012, SLAC LHC Cryogenics, interface with beam operation13/30 Interactions between LHC systems Static and Dynamic heat loads Beam related Dynamic heat loads Powering OK or interlock

Workshop Accelerator Operation 2012, SLAC LHC Cryogenics, interface with beam operation14/30 Outline Introduction to LHC Cryogenics Operation, organisation and results Availability and interaction with beam operations Summary

Workshop Accelerator Operation 2012, SLAC LHC Cryogenics, interface with beam operation15/30 Key factors for operation Equipment architecture: –Central liquefier to intermediate buffer, distribution decoupled –Cooling capacity production in line with demands Type of operation –Transients (cool-down / warm-up) or various recovery –Alarm monitoring, simple reset actions, calling for experts –Detection of process degradation and curing action –HW checks and preventive treatment of slow evolving problems Frequency of required actions: –Once per month, once per week –Once per 1-2 days On-call adapted LHC: A huge and complex system without significant buffer and frequent operator actions required Dedicated 24/7 required so far !!!

Workshop Accelerator Operation 2012, SLAC LHC Cryogenics, interface with beam operation16/30 Structure - Coordination - Outils Coordinations: Team Leaders + Management (1/wk) Performance panel (1/2wks) Operation / Maintenance panel Methods & Tools panel MechanicsElectricity-Controls Instrum-Cryolab Operation Accel.Operation Detect. Management Methods - Logistics Tools (web interface DB oracle): e-logboog operation for any change of configuration (wanted or not) or observation and diagnostic request Diagnostic tables, work-orders, intervention reports Asset & spares management, intervention procedures Maintenance plan Scheduling

Workshop Accelerator Operation 2012, SLAC LHC Cryogenics, interface with beam operation17/30 Staff & team evolution High level requirements for recruitment (Bachelor & Masters) Formalised induction process: Academic training - On the job training - Shadow shifts => Certification after ≈ 10 months as shift operator (alone!) Senior operator (>3 yrs): Able with all sub-systems, ability to optimise production-needs-time Certification diploma: Written - Site - Simulator - Improvement study (report + presentation) If selected for indefinite contract: –Operation for 5 to 10 years –Ability to become “production Eng.” as site responsible –Ability to switch to support teams or another activity at Cern People should be able to quit, newcomers should be integrated

Workshop Accelerator Operation 2012, SLAC LHC Cryogenics, interface with beam operation18/30 Cryo operator in Cern Central Control room Shift 24/7 Process synoptics and orders Tendancy curves (summary) Fixed displays

Workshop Accelerator Operation 2012, SLAC LHC Cryogenics, interface with beam operation19/30 Operation, indicators Powering Alarms Global availability Efficiency

Workshop Accelerator Operation 2012, SLAC LHC Cryogenics, interface with beam operation20/30 Outline Introduction to LHC Cryogenics Operation, organisation and results Availability and interaction with beam operations Summary

Workshop Accelerator Operation 2012, SLAC LHC Cryogenics, interface with beam operation21/30 Availability: a signal Yes/No is required Cryo Maintain: Few important conditions checking integrity of HW, with slow power abort in case this signal is lost (leading to beam dump !) Cryo Start: set of conditions to allow powering of concerned sub-sector, with no action if powering started (illustrates good stability of process) SP set-point CM CS T2 indicator w.r.t EN T2 = Achieved up time during required time / Required time x 100 (operational availability) CS CM Sum CM 8 sectors: Global availability CM Possibility to treat thousands of channels in a structured way to match at best the LHC powering sub-sectorisation and the cryo sub-sectorisation

Workshop Accelerator Operation 2012, SLAC LHC Cryogenics, interface with beam operation22/30 LHCCryo global availability Excellent 1st part to TechSTop - Heavy works done during Technical Stop #1, and cabling weakness caused difficult recovery - Very moderate impact from High Luminosity operation in Excellent 1st part to TechSTop - Heavy works done during Technical Stop #1, and cabling weakness caused difficult recovery - Very moderate impact from High Luminosity operation in Target % SEU? P8+R5 L7 TT891 2xP8 CCs P18 oil P4 ice P4 CCs

Workshop Accelerator Operation 2012, SLAC LHC Cryogenics, interface with beam operation23/30 Performance and origin of downtine (260 days)(271 days) Evolution: : Correcting early Cryo bugs : Adapting to SEU : So far rewarding !!! Global availability as seen by LHC during beam operation periods Others according to relative ratio of their average for the 8 sectors (Full days, Mondays & Fridays of Technical Stops not counted here) (137/290)

Workshop Accelerator Operation 2012, SLAC LHC Cryogenics, interface with beam operation24/30 Availability: from global to single plant Single sector and cryoplant Considering 8 independent sectors

Workshop Accelerator Operation 2012, SLAC LHC Cryogenics, interface with beam operation25/30 Indicators: recovery categories & tendency + Better global control/tuning (operation, instrumentation) - ! SEU ! + No longer recurrent Cold Compressors particular issues (Leaks, electronics) Less Cryo induced failures,. (but 3 VERY LONG ones!) - More Supply (EL) failures - ! SEU ! Serious cases requiring specific monitoring and significant efforts Annoying if frequent, to be kept low with moderate efforts From the books: Immediate effect of (good!) practice Nice tendency, promising for 2012 or new surprises to come up? Nb stops

Workshop Accelerator Operation 2012, SLAC LHC Cryogenics, interface with beam operation26/30 Operation structure & approach 2007/2008 cool-down & HWC: Per site, one experienced engineer with agreed minimum protocol to guide a local team of operators, with help of support teams (instrumentation, experts, controls) Since 2009 and operation with beam: One operator in shift 24h/7d, more transverse structure site/CernControlCenter, procedures & operation tools For machine controls (temperature, level, pressure): Basic interlocks and simple PID loops with generic tools for fast orders, now completed with automated sequences & procedures Indicators: From temperature stability to daily availability on-line cool-down curves to on-line cryo-status Control rooms: site - CCC- office

Workshop Accelerator Operation 2012, SLAC LHC Cryogenics, interface with beam operation27/30 Power Consumption for LHC Cryogenics Installed power Operation with 8 plants Cryo optimized power Stop Cryoplant Tests Cool down Gain ≈ 8MW (20% of installed power) Net gain ≈ 50 GW.h per year (3 MCHF / year !!!) LHC physics 6200 h LHC physics 6500 h HWC 91% Cryo Availability 90% Cryo Availability 700 h Cryo unavailability breakdown Power [MW]

Workshop Accelerator Operation 2012, SLAC LHC Cryogenics, interface with beam operation28/30 Helium inventory follow-up Helium invenrory [tons] Now < 30kg/day With 50kg/day in 2011 and better tendency to be CHF/kg - 50kg/day # 2’500 CHF/day t # 7.5 MCHF

Workshop Accelerator Operation 2012, SLAC LHC Cryogenics, interface with beam operation29/30 Text zone Interfaces with Beam-OP HW signals: –Cryo Start and Cryo Maintain towards Powering Interlock module SW panels: –Cryo web page People in Control Room (LHC): –1 Eng in charge + 1 operator –1 Cryo operator –1 operator for technical infrastructure Possible evolutions ? – Closer discussions with Eng. In charge in case of cryo problem – Other operators involved to help diagnostics/recovery – No longer cryo operators at night (on call only)

Workshop Accelerator Operation 2012, SLAC LHC Cryogenics, interface with beam operation30/30 Summary LHC cryogenics is the largest, the longest and the most complex cryogenic system worldwide. We could achieve a reasonable availablity (> 90 %) so far with beams. This demonstrates that there are no big issues in concept, technology or global approach for operation. Despite all our efforts, we had very hard time and lengthy commissioning to learn how to tune all these sub-systems together while permanently consolidating what was not conform. Experience has been converted into automatism, procedures, tools, training Cryogenics operation is well integrated in central control room with LHC main systems, but operated/supported independently (about 50 people) Maintenance is as well reaching an efficient preventive/corrective ratio, with efforts to be made for non-standard cases. We have to prepare for higher energies and intensities with continued gain in reliability !