Federal Energy Regulatory Commission Large Generator Interconnection Final Rule RM02-1-000 July 23, 2003.

Slides:



Advertisements
Similar presentations
Confidential A PHI Company 1 NJ Off-Shore Wind – Recommended Compliance Structure Stakeholder Meeting January 13, 2009.
Advertisements

E-Tariff - The Problem with Joint and Shared Filings Presented by National Grid NAESB E-Tariff Conference Colorado Springs January 23-25, 2008.
1 WECC/AESO Membership and Coordinating Operating Agreement WECC Board of Directors Meeting December 2007 Diana Pommen Director Interjurisdictional Affairs.
Goals for 2003 Kansas Interconnection Standards Development Larry Holloway Chief of Energy Operations Kansas Corporation Commission.
A Federal View of the Interface of Natural Gas and Electricity Prices Moving Toward Greater Reliance on Wholesale Energy Markets November 30, 2006 Crowne.
Kansas Interconnection Implementation Workshop The FERC Process: What it means for Kansas and other states Wichita, Kansas Oct. 1, 2003 Christopher Cook.
Federal Energy Regulatory Commission Large Generator Interconnection Order on Rehearing (Order No A) RM March 3, 2004.
Federal Energy Regulatory Commission Update Janice Garrison Nicholas Chief Accountant and Director, Division of Financial Regulation Federal Energy Regulatory.
Does owning a solar array make you a utility?...and other questions A presentation to the Kentucky Environmental Quality Commission Andrew Melnykovych.
REPUBLIC OF ALBANIA PUBLIC PROCUREMENT AGENCY Introduction to the Albanian Public Procurement System Central Asia Regional Public Procurement.
Transmission Corridor Zone Designation Process Terrence O'Brien, CEC December 11, 2007 Energy Action Plan.
Regional Transmission Organizations: The Future of Transmission? Dave Edwards 4/17/2004.
Economic Criteria for Transmission Planning in the ERCOT Region Public Utility Law Seminar DeAnn Walker August 3, 2012.
Highway-Byway Cost Allocation: What it Offers MISO January 2010 Presented to the Organization of MISO States CARP and the Midwest ISO RECB Task Force Meeting.
Presentation to WECC Market Interface Committee March 24, 2015
BIOENERGY SYMPOSIUM 2013 ANAEROBIC DIGESTION Regulations Ollie Frazier, P.E., MBA.
Federal Energy Regulatory Commission Proposed Rule on Small Generator Interconnection RM July 23, 2003.
Containing the Cost of California’s RPS Yuliya Shmidt, Senior Analyst February 2, 2012.
Sue Sheridan President and Chief Counsel Coalition for Fair Transmission Policy EEI Transmission and Distribution Conference April 2012 TRANSMISSION PLANNING.
RenewElec October 21, 2010 Robert Nordhaus, David Yaffe Van Ness Feldman 1050 Thomas Jefferson Street, NW Washington, DC (202) FERC’s.
PacifiCorp Participation in the California ISO. 2 Full participation provides significant benefits beyond those of the Energy Imbalance Market EIM BenefitsFull.
Highlights of Commission Activities Little Rock ASHRAE Monthly Meeting October 12, 2011 Presented By: John P. Bethel.
Summary Overview: MADRI Model Small Generator Interconnection Procedures Prepared by Brad Johnson* June 15, 2006 ACN Energy Ventures
Technical Regulations – U.S. Procedures and Practices U.S.-Brazil Commercial Dialogue Digital Video Conference Series August 22, 2006 Mary Saunders Chief,
Reliable Power Reliable Markets Reliable People Performance Targets for the Customer Interconnection Process January, 2008.
Why is WPL filing a rate case?  Last Base Case Rates were set January, 2007  Cost of our utility investments must be reflected in prices our customers.
NERC Data Collection & Coordination. Rules of Procedure: Section 1600 Overview  NERC’s authority to issue a mandatory data request in the U.S. is contained.
October 8, 2003Ontario Energy Board1 Ontario Energy Board Update E.A. Mills Director – Regulatory Affairs Market Advisory Committee October 8, 2003.
Small Renewable Generators Tony Marciano Public Utility Commission of Texas May 2, 2007 (512)
WINDPOWER 2003 Austin, TX May 18-21, 2003 Session 4A: Regulatory Issues Monday May 19, :40-5:00 pm Wind Generation Interconnection to Transmission.
Large Generator Interconnection Procedures Reform Stakeholder Meeting February 19, 2009.
OSC Meeting April 27, Transmission Cost Allocation Overview.
Sec. 5 RE-REGULATION- EPAct 1992 FERC Orders 888 and 889 (1996) EPAct 2005 In short these three laws move the power industry towards an increase in competition.
Mandatory Electric Reliability Standards and Transmission Expansion Suedeen G. Kelly Commissioner Federal Energy Regulatory Commission The Canadian Institute.
1 The Costs of Participating in Restructured Wholesale Markets American Public Power Association February 5, 2007 William M. Bateman Robert C. Smith.
Discussion of Market Participant Choice for Transmission Connections Stakeholder Session October 14, 2011.
Duke Energy Carolinas Quarterly Stakeholder Meeting Independent Entity Services Tuesday, April 21, :00 to 3:00 p.m. EDT.
1 Interconnection Update Jay Zimmerman Manager, Transmission Policy Entergy Transmission Planning Summit New Orleans, LA July 8, 2004.
Special Railways Phase III Proposed approach to regulatory changes Jakarta 16 May 2011.
Large Generator Interconnection Procedures Reform 2 nd Stakeholder Meeting May 5, 2009.
Updated 1/28/2011.
CPUC Role in AB 32 Implementation LIOB – 2 nd June, 2010 San Diego, CA.
Demand Response in Energy and Capacity Markets David Kathan FERC IRPS Conference May 12, 2006.
Reliable Power Reliable Markets Reliable People Transition of Authoritative Documents – Information Session September 2009 Doyle Sullivan Evelyn Kelly.
March 30, 2012 Wholesale Generation Interconnection Process Photovoltaic Program Power Purchase Agreements Request for Offers.
Employee Privacy at Risk? APPA Business & Financial Conference Austin, TX September 25, 2007 Scott Mix, CISSP Manager of Situation Awareness and Infrastructure.
Working Paper on Standardized Transmission Services and Wholesale Electric Market Design Alice Fernandez, Derek Bandera, Connie Caldwell, Jignasa Gadani,
Utah Geothermal Power Generation Workshop Regulatory Issues August 17, 2005 Presented by Becky Wilson Utility Economist Utah Public Service Commission.
Order 1000 Implementation in PJM – Challenges and Opportunities Jodi L. Moskowitz Senior Director – Transmission Development & Strategy October 13, 2015.
1 Entergy Transmission Planning Summit Transmission Planning Process Doug Powell New Orleans, LA July 8, 2004.
FERC Staff’s Report on Demand Response and Advanced Metering.
Craig Williams Market Interface Manager August 21, 2014 ISAS, Portland, OR.
Electric Reliability Organization and Issues in Texas Technical Advisory Committee January 4, 2006 Jess Totten Director, Electric Industry Oversight Division.
Philippine Feed-In Tariff System Implementation 1.
Renewable Energy Act of 2008
Lessons Learned from Existing RTOs John Moore January WCEA Meeting January 7 th, 2016.
Kansas City Power & Light and KCP&L Greater Missouri Operations – Suggestions for Chapter 22 Revisions Missouri Public Service Commission Meeting Aug 31,
RTO WEST Summary of RTO West 9/18/02 Declaratory Order Presentation to The Committee on Regional Electrical Power Cooperation (CREPC) by John Carr 10/1/02.
DRAFT – FOR DISCUSSION PURPOSES ONLY © 2013 New York Independent System Operator, Inc. All Rights Reserved. EIPC Roll-Up Powerflow Model Zach Smith Director,
Black Start Service in New England System Operator’s Perspective Robert B. Burke ISO New England Inc. July 23, 2002 IEEE - Chicago, Illinois.
UTC STUDY OF DISTRIBUTED GENERATION AND RECOMMENDATIONS Presentation for the Washington Future Energy Conference October 19, 2011.
EPE INTERNAL CODE OF CONDUCT
Regional Transmission Organizations
Duke Energy Carolinas Quarterly Stakeholder Meeting
Massachusetts Electric Restructuring Roundtable
Pseudo-tie business procedure
GMD Data Request NERC Rules of Procedure Section 1600
Rates & Regulatory Updates
Pseudo-tie business procedure
North America Energy Standards Board
Presentation transcript:

Federal Energy Regulatory Commission Large Generator Interconnection Final Rule RM July 23, 2003

Federal Energy Regulatory Commission 2 Final Rule Requires public utilities to amend their Open Access Transmission Tariff to include standard interconnection procedures and a standard interconnection agreement for generators larger than 20 MW. Standardizes the scope of each study, deposit amount, time of completion of each study, and access to study data.

Federal Energy Regulatory Commission 3 Purpose of Final Rule Reduce overall cost of electricity to customers, including the cost of renewable energy Reduce interconnection time and costs Prevent undue discrimination in interconnections Increase energy infrastructure

Federal Energy Regulatory Commission 4 Purpose of Final Rule (cont’d) Ease entry for competitors while promoting more efficient siting decisions Clarify pricing of transmission enhancements for interconnections Preserve reliability of the transmission system

Federal Energy Regulatory Commission 5 The Rulemaking Process ANOPR issued October 2001 initiating a stakeholder negotiation process Consensus document filed January 2002 NOPR issued April 2002 largely incorporating product of stakeholder negotiation process More than 170 entities filed comments

Federal Energy Regulatory Commission 6 The Rulemaking Process (cont’d) Small generator proponents requested separate treatment Commission issued a separate small generator ANOPR August 2002 applicable to generators up to 20 MW NARUC and state views reflected in much of both rulemakings

Federal Energy Regulatory Commission 7 Advantages to Generators under the Final Rule They can interconnect without requesting transmission service Access to study data so that they can conduct their own interconnection study One set of standard interconnection procedures and a standard interconnection agreement IA clearly lays out the legal rights and obligations of the parties

Federal Energy Regulatory Commission 8 Advantages to Generators under the Final Rule (cont’d) The Final Rule gives generators two interconnection options –Energy Resource Interconnection Service which is low-cost interconnection –Network Resource Interconnection Service which is a higher-cost interconnection that allows a generator to qualify as a network resource

Federal Energy Regulatory Commission 9 Advantages to Transmission Providers under the Final Rule Standard Interconnection Procedures streamline the interconnection process and reduce regulatory burden The Final Rule gives RTOs and ISOs the flexibility to customize interconnection process during compliance phase

Federal Energy Regulatory Commission 10 Advantages to Transmission Providers under the Final Rule (cont’d) Access to data allows generators to study various points of interconnection, reducing the number of interconnection studies to be performed by the Transmission Provider

Federal Energy Regulatory Commission 11 Pricing for Non-Independent Transmission Provider Clarifies who pays for interconnection costs when the transmission provider is not independent Credits to be paid for Network Upgrades over 5 years, with interest –but Generating Facility must first achieve commercial operation

Federal Energy Regulatory Commission 12 Pricing for Independent Transmission Provider –The rule allows pricing flexibility for an RTO or ISO, including use of participant funding –In forming an RTO or ISO, an independent administrator may use participant funding for Network Upgrades for one year, subject to approval by the Commission and affected States

Federal Energy Regulatory Commission 13 The Final Rule Applies to all interconnections to facilities subject to a Transmission Provider’s Open Access Transmission Tariff at the time an interconnection request is made

Federal Energy Regulatory Commission 14 Variations from this Rule Regional variations –Utilities may propose variations that are generally used throughout a region if consistent with or superior to the Final Rule –Utilities may propose variations to comply with a regional reliability rule, subject to Commission approval RTO or ISO –The rule allows greater flexibility for an RTO or ISO, subject to Commission approval

Federal Energy Regulatory Commission 15 Compliance Filing (Amendment to OATT) Public utilities must file amendments within 60 days from the date of publication in the Federal Register