1 341st CONS Home of the Two-Time AFSPC Top Dollar Champions! “Takin Care of Business”

Slides:



Advertisements
Similar presentations
1 CLIENT CONSULTANT AGREEMENT. 2 Negotiations Types of Consulting Contracts Standard Form of Contract Form of Contract General Conditions Special Conditions.
Advertisements

A GIA is a contract between a surety company and a contractor (or subcontractor)/principal. A GIA is a standard, typical document in the construction.
Construction Contracting
ABC Change Orders College of Environmental Design
Introduction to Contracting: Contract Modifications.
Presentation by: Tshewang Gyeltshen. The SBD is prepared in line with the PRR 2009 & SBD Large Works General principals of procurement to be applied prescribed.
CARLIN LAW GROUP, APC Dispute Resolution Procedures Contract Claims Requirements Public Contract Code § (schools) Public Contract Code §20104 Government.
Consideration Chapter 8.
772 ESS Lesson Learned Briefing
1 Basics of Government Contracting. Federal Procurement Background The U.S. Government is the world’s largest purchaser of goods and services 2.
Contract Law 2014 NCHCA Education Series- January 23, 2014 Presented by Geoffrey Cantello, City of Ottawa and Ron Price, Rasmussen Starr Ruddy LLP.
Completion Outstanding work and Remedying Defects In order that the Works and Contractor's Documents, and each Section, shall be in the condition required.
OVERSIGHT & COMPLIANCE BRANCH (OCB) MODIFICATION TYPE and AUTHORITY TRAINING November 04,
DPW General Conditions Articles 32 through 37. Articles Covered Today  32 Owner’s Right to Withhold Payment  33 Owner’s Right to Stop Work and Terminate.
1 How to Write an Incremental Funding Modification Sarah Echt May 2004.
POLICY & OVERSIGHT DIVISION (POD) February 2014 PROCESSING CONTRACT MODIFICATIONS TRAINING 1.
Product Liability When goods cause injury, there is a question of product liability. There are three main issues related to product liability cases: –
Contract Administration Chapter 6. Learn. Perform. Succeed. Learning Objectives Determine those contract administration contingency issues most often.
Time for a new standard - AS General Conditions of Contract
ISLAMIC UNIVERSITY OF GAZA FACULTY OF ENGINEERING CIVIL ENGINEERING DEPARTMENT 20. Claim, Disputes and Arbitration [Construction Contract Administration]
Conditions of the Contract for Construction
LOGO October The Employer FIDIC 1999 dasdas Supervisor: Dr.Kamalain shaath Done by: Mahmoud Abu Kmail Construction Contract Administration ENGC.
Construction Engineering 221 Contracts & Contractor Procurement.
Construction Engineering 380 Contract Changes. Types of changes –Cardinal change- drastic change, either single direction or accumulated change in scope.
JSC Action # 2621 Hurricane Allowability/Charging Policy Jose Garcia /5/06.
Construction: Legal Issues. Legal Issues In the Bidding Process Timing of various activities has legal implications. During the bidding process: –A bid.
10 MYTHS OF GOVERNMENT CONTRACTING Kate Whitby 1 North Brentwood, Suite 1000 St. Louis, MO Kate Whitby 1 North Brentwood,
Study Unit 4 Performing Contractual Obligations.  The outcomes for this learning unit are that you should be in a position to: ◦ Discuss Agency ◦ Discuss.
Local Government Forum, 15 September 2010 Tender Negotiations, Indemnity and Exclusion of Liability Kathryn Walker Senior Associate (08)
United States Department of Agriculture Office of Procurement and Property Management Effective Performance Management and Use of Performance Metrics Refresher.
Compensation events and claims Presented by Prof. Khem Dallakoti.
Construction Engineering 380 Engineering Law. Contract Documents After bidding or negotiation to establish price and scope, a contract must be executed-
Jack Friery1 Legal Aspects of Government Contracts-- SDSU Class One.
Factors Affecting Contracts Ending a Contract
King Fahd University of Petroleum & Minerals
Don Mansfield Professor of Contract Management Defense Acquisition University.
General Condition THE EMPLOYER Construction Law Supervised By : Dr. Kamalain Shaath Prepared By : Eng. Fawzy El.farra.
CHANGE ORDER & BACKCHARGES PREPARED BY ABDULAZIZ M. AL-BESHR ID# PREPARED FOR Dr. ABDULAZIZ BUBSHAIT.
CONSTRUCTION CONTRACTS DOCUEMENTS
LECTURE 4 FORMULATION & PRESENTATION OF MONETARY CLAIMS  Recovery of Loss / Expenses / Damages  Notice of intention to claim  Particular and further.
Construction Materials and Workmanship. All workmanship, materials, equipment, and articles incorporated into the work are to be of the best available.
CVE 4070 Construction Engineering Course Review & Critique Prof. Ralph V. Locurcio, PE.
Copyright © 2008 Pearson Education Canada9-1 Chapter 9: The End of the Contractual Relationship.
RPA1 Standard Bidding Documents for the Supply and Installation of Information Systems General Conditions of Contract and Special Conditions of Contract.
7 Plant, Materials and Workmanship. 7.1Manner of Execution The Contractor shall carry out the manufacture of Plant, the production and manufacture of.
Angelica R. Armenta FAR Study Group – Jan Only contracting officers acting within the scope of their authority are empowered to execute contract.
Conditions Of Contract For Construction Conditions Of Contract For Construction Presented BY : Arch. INA’AM J. El TAWIL FIDIC 1999Conditions of Contract.
CON 2001 CVE 4070 Construction Methods/Engineering Changes & Extra Work Prof. Ralph V. Locurcio, PE.
LECTURE 5 FORMULATION & PRESENTATION OF OTHER CLAIMS
 Section Where you go if you disagree on either three elements entitlement, impacts or costs  Begins with the contractors notice 5 working days.
CLAIMS MANAGEMENT. PRESENTATION OUTLINE INTRODUCTION TYPICAL CLAIMS AGAINST OWNER TYPICAL CLAIMS AGAINST CONTRACTOR CRITICAL PATH METHODS UTILIZATION.
ENGINEER Engineer Duties: Carry out the duties assigned in the contract.Carry out the duties assigned in the contract. Engineer's staff shall include qualified.
CVE 4070 Construction Engineering Changes & Extra Work Prof. Ralph V. Locurcio, PE.
Change Orders, Extras and Claims Presented by Geoffrey Cantello, City of Ottawa.
Helen S. Henningsen Department of Veterans Affairs Office of General Counsel.
Kevin Kelly Government Construction Projects & Capital Spend Conference 2016 Wednesday 11th May 2016 Royal Marine Hotel, Dun Laoghaire, Co. Dublin.
The Impact of Budget Reductions on the Procurement Process Jeff Newman 1.
CHANGE ORDER/CLAIMS MANAGEMENT MODULE 9. Change Order Management.
Project Risk Management Execution FE302 Lesson 5 June 2015 Changed Conditions on Construction Projects.
CONTRACT ADMINISTRATION
Administration of a FIDIC Contract - Project Control
Administration of a FIDIC Contract - Commencement Date to + 28 Days -
Administration of a FIDIC Contract - Financial Management
DLA Aviation Product Quality Deficiency Report (PQDR) Allen Gibbs
Speaker: Sarah Chambers, Esq. Claims Counsel| Professional Liability
Certificates JCT 11 SBC allows for 10 different kinds of certificates.
Find the Problems with the Provisions May 11, 2016 Presented By:
Public works contract Clauses 10.5 & 11.5 Explored
Construction Contract Administration
Directed Change Constructive Change
Presentation transcript:

1 341st CONS Home of the Two-Time AFSPC Top Dollar Champions! “Takin Care of Business”

2 Claims Claims definedClaims defined FAR ClausesFAR Clauses Basis for ClaimsBasis for Claims –Changes –Constructive Changes –Delays –Breach of Implied Duties –Mistake Allowable CompensationAllowable Compensation

3 Claims Claim defined - FAR Claim defined - FAR –“a written demand, as a matter of right” –seeking payment of a “sum certain” or adjustment or interpretation of contract terms –“arising under or relating to a contract” –certification required if over $100K Customer/requiring activity must be advised and involvedCustomer/requiring activity must be advised and involved CO required to respond w/i 60 daysCO required to respond w/i 60 days

4 Claims Contract ClausesContract Clauses –FAR Disputes (Contract Disputes Act of 1978) –FAR Changes - Fixed-Price –FAR Changes (used in construction contracts) –FAR Government Delay of Work –FAR Suspension of Work –FAR Differing Site Conditions

5 Claims The Changes Clause - FAR The Changes Clause - FAR –The CO may, at any time, by written order, without notice to sureties make changes within the general scope of the contract in any one or more of the following: Drawings and specsDrawings and specs Method of shipment or packingMethod of shipment or packing Place of deliveryPlace of delivery

6 Claims Changes - fixed-priceChanges - fixed-price –Contractor must assert its right to an adjustment within 30 days from receipt of a written order. What if -What if - –No written notice from contractor is received within 30 days? –No written order is given? –Change is outside the general scope of contract?

7 Claims Constructive Change DoctrineConstructive Change Doctrine –Any oral direction, instruction, interpretation or determination which can be reasonably construed as a change to the contract. What if -What if - –The oral directive comes from someone other than a CO?

8 Claims Changes Clause-Construction FAR Changes Clause-Construction FAR –The CO may, at any time, without notice to sureties, by written order designated or indicated to be a change order, make changes within the general scope of the contract, including: Drawings and specsDrawings and specs Method or manner of performanceMethod or manner of performance In GFP, GFM or siteIn GFP, GFM or site Acceleration in performance of the workAcceleration in performance of the work

9 Claims Changes Clause - ConstructionChanges Clause - Construction –Provides for adjustment based on oral “direction, instruction, interpretation or determination.” Contractor must provide written notice that it considers the action to be a changeContractor must provide written notice that it considers the action to be a change No adjustment shall be allowed for costs incurred more than 20 days before Contractor’s written notice to CO, except for an adjustment based on defective specs.No adjustment shall be allowed for costs incurred more than 20 days before Contractor’s written notice to CO, except for an adjustment based on defective specs.

10 Claims Impact Under Changes ClauseImpact Under Changes Clause –“If any change increases or decreases a contractor’s cost of, or time required for, performance... the Contracting Officer shall make an equitable adjustment in the contract price, the delivery schedule, or both, and shall modify the contract.” Profit includedProfit included

11 Claims Equitable adjustmentEquitable adjustment –What is it? –Claim? Failure to agree to an adjustment shall be a disputeFailure to agree to an adjustment shall be a dispute Contractor required to continue performanceContractor required to continue performance –Certification required? –DFARS 243.2

12 Claims Impact under delay of work clausesImpact under delay of work clauses –An adjustment to the cost of performance (excluding profit) and delivery or performance dates

13 Claims Differing Site Conditions - FAR Differing Site Conditions - FAR –Allows for additional compensation when subsurface or unknown latent physical conditions are experienced that differ materially from those indicated in the contract. –Contractor must notify the Contracting Officer before conditions are disturbed.

14 Claims Claims for Breach of ContractClaims for Breach of Contract –Breach of implied duties CooperationCooperation Good faith and fair dealingGood faith and fair dealing Implied warranty of adequacy of specificationsImplied warranty of adequacy of specifications –Cardinal Changes Claims for MistakeClaims for Mistake –Unilateral vs. Bilateral

15 Claims Modifications in Settlement of ClaimsModifications in Settlement of Claims –Must include release language –Must have legal review and approval regardless of dollar value

16 Claims What if -What if - – Contractor submits a legally deficient claim? – Contractor submits an unsupported claim? – Contractor understates cost impact and we know it?

17 Claims ConclusionConclusion –Evaluate: Has a claim been submitted?Has a claim been submitted? –Are all legal requirements present? Has adequate supporting data been submitted?Has adequate supporting data been submitted? Has customer/requiring activity evaluated the claim?Has customer/requiring activity evaluated the claim? Has a valid basis for a claim been alleged?Has a valid basis for a claim been alleged? Has SJA reviewed claim?Has SJA reviewed claim? Does modification include release & satisfaction?Does modification include release & satisfaction?