SKA Pre Construction Phase Infrastructure Tracy Cheetham Carel van der Merwe General Manager: Infra & Site OpsInfrastructure System Engineer

Slides:



Advertisements
Similar presentations
Design Constraints For Engineering Projects
Advertisements

SKA South Africa Overview Thomas Kusel MeerKAT System Engineering Manager April 2011.
WBS & AO Controls Jason Chin, Don Gavel, Erik Johansson, Mark Reinig Design Meeting (Team meeting #10) Sept 17 th, 2007.
Dominion Radio Astrophysical Observatory DVA-1 Reflector Development Timeline Gary Hovey NRC-HIA Dominion Radio Astrophysical Observaotry.
Electrical Installation CM39 Andy Gallagher & Ian Mullacrane.
All content in this presentation is protected – © 2008 American Power Conversion Corporation Rael Haiboullin System Engineer Capacity Manager.
1 ILC ( International Linear Collider ) Asian Region Electrical Design H. Hashiguchi, Nikken Sekkei, Co. Ltd., A. Enomoto, KEK ILC Mechanical & Electrical.
Electrical & Control CM40 Daresbury Laboratory. CM40 Electrical Infrastructure Update RRM2 Latest Latest on Installation Progress Rack Allocations Racks.
CSG Panel – May 10, 2006 Key Lessons for New Data Centers Project overview Requirements Lessons learned Going Forward.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
PACS IBDR 27/28 February 2002 PACS DEC/MEC1 Detectors & Mechanisms Controllers (DEC/MEC) J.-M. Gillis Centre Spatial de Liège (B)
NASA’s Goddard Space Flight Center LRO Integration and Test Joanne Baker GSFC Code 568 August 16-17, 2005.
IT Update Sally Waselik June 2005 IOC meeting. IT Vision - “We Deliver Quality Solutions For Our Customers” 2 Today l Level of Service Concepts l IT Enterprise.
INFRA:DISH = DISH INFRA: LFAA = LFAA INFRA:SDP = SDP INFRA:CSP = CSP INFRA:SADT = SADT INFRA:MGR = MGR INFRA:AIV = No IF? Infra ICD Leads.
Investigating EMC policies for the SKA Paul van der Merwe Prof. HC Reader Stellenbosch University.
Commitment Process Presented by Edward B. Luers October 2008 Interplanetary Network Directorate Deep Space Network.
Physical Infrastructure Issues In A Large Centre July 8 th 2003 CERN.ch.
Electrical Integration CM38 Steve Griffiths & Ian Mullacrane.
1 WP4 – System Testbed Trial 2 preparation Barcelona 3/03/05 Marco Bobbio Pallavicini - Carlo Gavazzi Space SpA.
CRISP & SKA WP19 Status. Overview Staffing SKA Preconstruction phase Tiered Data Delivery Infrastructure Prototype deployment.
1 Infra-SAN: Technical architecture buildup. 2 Technical architecture buildup Purpose : Service driven Formalise the test definition and realisation Technical.
1 Mission Discussion & Project Reviews 祝飛鴻 10/14/93.
GIF in EHN1- layout, construction and schedule Adrian Fabich, EN-MEF-LE GIF users meeting, 12 th February 2014.
MICE RF System Power Supplies, Control and Monitoring Status report February 2012 Chris White, STFC Daresbury Laboratory MICE Collaboration Meeting CM32,
Dan MertelyEVLA Feeds CDR 17 February RFI Concerns Relating to EVLA Feeds Dan Mertely.
ID 308 Construction + Materials IV: Construction Documents Prof. Brody Endicott College Systems Coordination.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
Computing Facilities CERN IT Department CH-1211 Geneva 23 Switzerland t CF CERN Computer Centre Upgrade Project Wayne Salter HEPiX November.
Reproduction interdite © ALMA EUROPEAN CONSORTIUM Reproduction forbidden Design, Manufacture, Transport and Integration in Chile of ALMA Antennas Page.
AAVS 0.5: An Overview Peter Hall ICRAR/Curtin, Bologna, October 22, 2012.
Assembly, Integration & Verification 2015 SKA Engineering Meeting Richard Lord 11 November 2015.
SKA Interface Workshop: AIV Interfaces – Summary and Wrap AIV consortium Manchester June 2013.
SKAO Power Update 2015 Engineering Meeting: Penticton Adriaan Schutte
Datacenter Energy Efficiency Research: An Update Lawrence Berkeley National Laboratory Bill Tschudi July 29, 2004.
Reproduction interdite © ALMA EUROPEAN CONSORTIUM Reproduction forbidden Design, Manufacture, Transport and Integration in Chile of ALMA Antennas Page.
Head of Project Update Alistair McPherson November 2015.
Hall D infrastructure and integration Elton Smith Hall D Collaboration Meeting September 9-11, 2004.
Rosie Bolton 2 nd SKADS Workshop October 2007 SKADS System Design and Costing: Update and next steps Rosie Bolton University of Cambridge.
Georgina Harris 11 th October nd SKADS Workshop – Observatoire de Paris 2-PAD Infrastructure Georgina Harris SKADS System Design and Team Leader.
CERN - IT Department CH-1211 Genève 23 Switzerland t Power and Cooling Challenges at CERN IHEPCCC Meeting April 24 th 2007 Tony Cass.
Conventional Facilities integration: Approach and Issues Daniel Piso Fernández WP Leader (WP13 Conventional Facilities Integration Support) November 5,
SKA Interface Workshop: AIV interfaces AIV consortium Manchester June 2013.
West Cambridge Data Centre Ian Tasker Information Services.
AADC - LFAA 12-Apr-161 Aperture Array Design & Construction Consortium Low Frequency Aperture Array (LFAA) LFAA System Requirements STFC (UK ATC) Prepared.
SKA Interface Workshop: Dishes External Interfaces Thomas Kusel & Mark Bowen For Dishes consortium Manchester June 2013.
SKA Status – Tango Collaboration Meeting Lize van den Heever June 2016.
TRIO-CINEMA 1 UCB, 2/08/2010 System Design Dave Curtis UCB/SSL Space Sciences Laboratory University of California, Berkeley.
S A Griffiths CM42 June 2015 Electrical & Control.
Spacecraft Technology Structure
Update on the PSB Cooling and Ventilation Systems
Electronics and Controls
MICE RF System Power Supplies, Control and Monitoring Status report
CLIC Civil Engineering & Infrastructure Working Group Meeting
CERN Data Centre ‘Building 513 on the Meyrin Site’
Electrical and electronic systems projects
PM view of SAFe SAFe Construction Planning Workshop A J Casson
SKA Element Interface Management Workshop CSP Element
EVLA NSF Mid-Project Review System / Antenna Status
GLAST Large Area Telescope:
TEST PLANS for HL LHC IT STRING
EVLA NSF Mid-Project Review System / Antenna Status
Technical Foundations & Enabling Technologies – DS4
SADT Overall Summary Total ICD count is currently 37 system level ICDs across 6 Elements LFAA 3 ICDs DISHES 7 ICDs CSP 12 ICDs TM ? Unable to proceed.
Maintenance at ALBA facility: Strategy for the conventional services
A Draft Funding Model for the SKA
SDP Interface Identification
SDP-lead Interfaces Summary
Infrastructure Interface – Power, cooling & building
On-Site Facilities for Pre-production deployment
Electronic : PH0 (former IH0)
Presentation transcript:

SKA Pre Construction Phase Infrastructure Tracy Cheetham Carel van der Merwe General Manager: Infra & Site OpsInfrastructure System Engineer Michelle Storey Rebecca Wheadon CSIRO SKA Executive OfficerProject Manager

Requirements Allocation

Construction sequence

Flow of Requirements

SE Process for INFRA

ICD – 3 Iterations

Iteration 1 (DRAFT1) –Part of Requirement Definition (by RR) –Concept Driving IF requirements Iteration 2 (DRAFT2) –Agreed ICD between INFRA and other elements –Part of Preliminary Design (Part of PDR pack) Iteration 3 (FINAL) –Signed Off at conclusion of PDR process –Formal change control for detailed design ICD – 3 Iterations

Vessel and Payload

INFRA ICDs with other elements

IF Lead = INFRA IF Boundaries –Array Layouts (SKA1-MID, Survey) –Dish construction Facilities –Antenna Foundations IF Types –Foundations Physical (Structural, cables) –Dish Electrical Power Budget (Electrical) –Power Backup & UPS (or not) (Reliability) –Earthing and LP –Staff requirements (ILS) ICD INFRA and DSH

Issues –Final Array Layouts –Loadings and Mechanical Interface –Responsibility for Bolt cage assembly (DISH?) –Power per antenna –Fibre / sleeve IF to DISH (INFRA or SaDT) –UPS for stowing (Dish or INFRA?) –Separate enclosure for Survey (RFI shielded) –Assume 10% of array can fail? ICD INFRA and DSH...

ICD lead = Dish - Bilateral

ICD Lead = LFAA / INFRA (AUS)? IF Boundaries –Array Layout –Array Foundations –On site Bunker IF Types –Physical –Antenna Electrical Power (Electrical) –Cooling –Power Backup (Reliability) –Local infrastructure ICD INFRA and LFAA

Issues: –Power system design –Compatible array config between DSH and LFAA –Power requirements per antenna –Solar Power –Impact on buildings ICD INFRA and LFAA....

Lead = Bunker, 256 racks + a few Fibre management (RF over Fibre) Integrate correlator ? Maser? MGR? In bldg Fibres (2 per antenna) Fibre design = LFAA, who supplies? Cable buried ? Or conduit vs phase stability (MRO tests) LFAA - Bilateral

Solar power for each 25k antenna, Battery tech? Total 2-3 MW MRO = 80 racks (Double screen),80 single screen ICD doc LFAA-INFA

ICD Lead = INFRA IF Boundaries –Racks in Processing Facilities / containers –Fibre buried / cables –Fibre on Power Lines? (Physical) IF Types –Space if facilities (No racks, size) –Power & Cooling –LAN / Data Interface (Data) –Staff requirements (ILS) ICD INFRA and SaDT

Issues –Location of Super computer centre (RSA) –IRD or ICD for SaDT and INFRA –Use of existing Fibre links (Buried & Overhead) –IF / cut over from Integrated LAN (RSA) –Environmental Data Document (SKAO?) –Special requirements for Masers? –Telephone data responsibility? –BMS data over network ICD INFRA and SaDT.....

ICD Lead = CSP? IF Boundaries –Racks in Processing Facilities / containers IF Types –Racks (Qty, Space, Mass) –RFI screening –Power Type and Load –Power Usage and Backup / UPS (Reliability) –Cooling type –Cooling redundancy (Reliability) ICD INFRA and CSP

IF Types.... –LAN / Data interface (Data) –Access control / BMS (Functional) –Staff Requirements (ILS) Issues –250 racks for Pulsar search (RSA) –Rack requirements for LFAA/Survey (AUS) ICD INFRA and CSP.....

Space, Power, Cooling –Survey ~ 100kW,MID ~ 100kW, LFAA ~ 50kW –Confirm UPS requirement (AUS) –3phase AC 400V interface –P search = 1MW = 50 racks (100m distance, spigot) –Air or Liquid cooling for P search ? –AUS = Liquid, RSA = Air –Fibre racks (overhead 400mm) –RFI spec TBC (100dB) CSP – Bi Lateral

Process –AIV to spec growth path Cable marking etc –Doc of what we have (INFRA) – Before T0 Space, power, cooling RFI screening (RFI ITT) Smoke, gas, access/CCTV, ESD (interlock?) Standards –ICD Doc (CSP) – T0-12W Limits (Power) Agreed doc –RR to PDR (update via CM) –PDR to CDR (update via CM) CSP - Bilateral

IF Boundaries –Racks in Processing Facilities IF Types –No Racks in facility (Qty, Size & mass) –RFI screening –Power Type AC/DC/Voltage/1 or 3 Phase –Power Usage & Backup / UPS (Reliability) –Cooling type –Cooling redundancy (Reliability) ICD INFRA and SDP

IF Types –LAN / Data interface (Data) –Access control / BMS (Functional) –Staff Requirements (ILS/Con Ops) Issues: –Space requirements for LFAA/Survey (AUS), –User supplied equipment space –Location of SDP (On site, off site) ICD INFRA and SDP

ICD lead = INFRA IF Boundaries –Racks in Processing Facilities / containers IF Types –Racks (space, size, mass) –Power Type & Quality –Power Backup / UPS (Reliability) –Cooling redundancy (Reliability) –LAN / Data interface (Data) ICD INFRA and MGR (TM)

IF Types..... –Access control / BMS (Functional) –Staff Requirements (ILS) Issues ICD INFRA and MGR.....

KAPB –130 racks in screened facility –640kW cooling –5kVA average per rack –Flexible feed to rack (1,3 ph A and B bus) –40 Fibre cables entering building –150 Fibre penetrate RFI screened room Existing facilities – SA Site

Overall Power –2.5 MVA fitted –5 MVA with full UPS (N+1) –6-7.5 MVA from current grid Sheds –Size of shed vs dish size Support base / workshops –Derived from Con Ops Existing – SA Site

KAPB

Nov 2012 June 2013

KAPB Rack Layout

Rack Growth

Limitation – Grid Power

Support base

MRO – AUS Site

MSF – AUS Site

Pawsey Centre – AUS Site