HF UPGRADE PROJECT Y. Onel PM June 11, 2012 1. Recent Highlights and News-I The PMT deliveries are now completed. Testing is going well. We had a meeting.

Slides:



Advertisements
Similar presentations
HIGH VOLTAGE POWER SUPPLY SYSTEM FOR CMS FORWARD SUBDETECTOR Lubomir Dimitrov, Ivan Vankov Nuclear Electronics Laboratory, Institute for Nuclear Research.
Advertisements

1 S. Lusin, LV Cabling, CERN 06 Apr 06 LV Cabling 06 Apr 06 S. Lusin Fermilab / CERN Cabling from USC to UXC, Power Distribution.
Status of the ATLAS MM project
CMS WeekDec 2002E. Hazen HF Electronics Status Report E. Hazen, J. Rohlf, E. Machado Boston University.
HCAL-Fermilab7 Feb 2003Hazen / Machado HF Electronics PMT Readout Update E. Hazen, J. Rohlf, E. Machado Boston University.
Production Monitoring and QC FCal1 Production Advancement Review February 20, Peter Loch University of Arizona Tucson, Arizona FCal1 Production.
Lab5 Production Status: Optics and RBX integration Pawel de Barbaro U. of Rochester.
HF UPGRADE PROJECT Y. Onel PM June 11, Recent Highlights and News-I The PMT deliveries are now completed. Testing is going well. We had a meeting.
Yu. Guz 18/12/20061 HCAL commissioning: status and plans Yu. Guz, IHEP, Protvino Outline 1. current status of HCAL a)CW+PM b)signal cables c)LED monitoring.
CMS ECAL End Cap EDR Meeting CERN 28 Nov. to 29 Nov 2000 A.B.Lodge - RAL 1 ECAL End Cap CMS ECAL End Cap Engineering Design Review. EDR meeting held 28.
Proposal of new electronics integrated on the flanges for LAr TPC S. Cento, G. Meng CERN June 2014.
Noise studies: hardware tests and preliminary results Anna, Anton, Giovanni, Pigi, Silvia, A. Boiano, A. Vanzanella.
HF Cabling Upgrade Options T. Shaw 30-OCT HF 2012 Upgrade Meeting 30-OCT-10 T. Shaw.
LHC ARC Commissioning report during LS1 Agenda: VRGPE documentation (former VRJGE) Active Penning modification By-Pass Valves modification LHC ARC commissioning.
Saverio Minutoli INFN Genova 1 1 T1 Electronic status Electronics Cards involved: Anode Front End Card Cathode Front End Card Read-Out Control card VFAT.
CMS ECAL End Cap Meeting CERN 19 June to 23 June 2000 A.B.Lodge - RAL 1 ECAL End Cap High Voltage Cards and 2000 Electrical/Thermal Model. Progress on.
The LST High Voltage System LST Readiness Review May 5, 2004 Klaus Honscheid Ohio State University.
High Voltage System outside Drawers Tilecal upgrade meeting at Stockholm (3-5 June 2013) François Vazeille on behalf of Roméo Bonnefoy, Christian Fayard,
GEM chambers for SoLID Nilanga Liyanage University of Virginia.
HF UPGRADE PROJECT Y. Onel PM Report May 14,
HF UPGRADE PROJECT Y. Onel PM Report March 19,
Status report on the development of a readout system based on the SALTRO-16 chip Leif Jönsson Lund University LCTPC Collaboration Meeting
CLAS12-RICH Mechanical Design Status-Report CLAS12 RICH Review September 5-6 th 2013 S. Tomassini, D. Orecchini1 D. Orecchini, S. Tomassini.
HF UPGRADE PROJECT Y. Onel PM Report March 5,
Update on the Triple GEM Detectors for Muon Tomography K. Gnanvo, M. Hohlmann, L. Grasso, A. Quintero Florida Institute of Technology, Melbourne, FL.
VVS Prototype Construction at Fermilab Erik Ramberg 26 February,2002 Design issues for VVS Details of VVS prototype design Schedule and Budget Testing.
ROBOX with Multi Anode PMT’s Status and plans A.Mestvirishvili, I. Schmidt, S. Sen, F. Ozok University of Iowa.
HF 2008 : Status and Plans CMS Week, February 2008 Aldo Penzo HCAL Commissioning Status (INFN-Trieste, Italy) (23 February 2008)
PSD upgrade: concept and plans - Why the PSD upgrade is necessary? - Concept and status of the PSD temperature control - Concept of the PSD analog part.
HF UPGRADE PROJECT Y. Onel PM Sept 17, Recent Highlights and News-I The PMT deliveries are now completed. The PMT and Base Boards System tests.
HF UPGRADE PROJECT Y. Onel PM Report April 30,
HF UPGRADE PROJECT Y. Onel PM July 9, OLD PMT vs NEW PMT 2 Old PMTs exhibit systematic gain loss vs Integrated Luminosity, rate of loss slowing.
HF HV Decision path Y.Onel. HV Micro PRR August 3, 2012 Follow up of August 3 rd Meeting At the meeting the HCAL HF group presented the HV PSU options.
HF UPGRADE PROJECT Y. Onel PM Report April 2,
Proposal for LST-based IFR barrel upgrade Roberto Calabrese Ferrara University Workshop on IFR replacement, SLAC, 11/14/2002.
Pixel power R&D in Spain F. Arteche Phase II days Phase 2 pixel electronics meeting CERN - May 2015.
1 Calorimeters LED control LHCb CALO meeting Anatoli Konoplyannikov /ITEP/ Status of the calorimeters LV power supply and ECS control Status of.
Status of the PSD upgrade - Problems with PSD in Be runs - Modification of cooling system - New temperature control - Upgrade of HV control system - MAPD.
9/12/2003Ivan Hruska1 First box prototype –Box design in July ‘03 –Box produced during August ’03 Tested last week in few fingers Small changes necessary.
LHCf Detectors Sampling Calorimeter W 44 r.l, 1.6λ I Scintilator x 16 Layers Position Detector Scifi x 4 (Arm#1) Scilicon Tracker x 4(Arm#2) Detector size.
PMT Tests for HF Upgrade Ugur Akgun. HF PMT Proposed Tests On Every PMT: – Rise Time – Negative Pulse Width – Transit Time – Transit Time spread – Single.
Status of the PSD upgrade - Status of the PSD cooling and temperature stabilization system - MAPD gain monitoring system - PSD readout upgrade F.Guber,
PSD upgrade: concept and plans - Why the PSD upgrade is necessary? - Concept of the PSD temperature stabilization and control - Upgrade of HV control system.
HF UPGRADE PROJECT Y. Onel PM October 1 st
EMCAL Calibration & Assembly at Yale University Mark Heinz, Project Mgr EMCAL Meeting Nantes July 15, 2008.
Status report on the development of a TPC readout system based on the SALTRO-16 chip and some thoughts about the next step Leif Jönsson AIDA Meeting Vienna.
HF I&C status Alexi Mestvirishvili, University of Iowa LS1 session, December CMS week1.
J. Valls, CMS L2-L3 Meeting, Sept ROD Production at CERN  ROD Flow During Production  ROD Flow at CERN  ROD Testing Areas  Infrastructure  Equipment.
1 hcal installation and commissioning status pawel de barbaro, vitali smirnov, june 11, 2007.
Status of NEWCHOD E.Guschin (INR), S.Kholodenko (IHEP), Yu.Kudenko (INR), I.Mannelli (Pisa), O.Mineev (INR), V.Obraztsov (IHEP), V.Semenov(IHEP), V.Sugonyaev.
Upgrade of the MEG liquid xenon calorimeter with VUV-light sensitive large area SiPMs Kei Ieki for the MEG-II collaboration 1 II.
CMS HF PMT SYSTEM By Y. ONEL U. of Iowa, Iowa City, IA CMS Meeting, CERN, Dec 1-8,2001.
PandaX 实验中的电子学概述 郭国栋 Outline Introduction Original scheme Improved scheme PMT base design in PandaX I and PandaX II Decoupler design in.
HF UPGRADE PROJECT Y. Onel PM Sept 3, Recent Highlights and News-I The PMT deliveries are now completed. Testing is going well. We had a meeting.
News about the WA104 Programme C. Montanari – INFN and CERN technical working group meeting, September 16,
Straw Working group Ferrara 4/9/2014. Outline Status and Plans Installation of Chambers 1-3 Chamber 4 Vacuum test SRB Readout, monitoring and software.
HF UPGRADE PROJECT Y. Onel PM November 26,
HF - Fiber and PMT Purchases By Y. Onel U. of Iowa, Iowa City, IA CMS Meeting, CERN, Dec 1-8,01.
TOTEM CSC construction and Quality Control Status report A.Krivshich Petersburg Nuclear Physics Institute March 07, 2006 CERN.
HF ROBOX PRR3 Apr 2003E. Hazen HF Front-End Electronics ● System Description – Overview – PMT Board, ROBOX, Patch Panel – Signal Cable, Front-end boards.
HF “Slice test box” installation
The PSD at Pb-Pb run PSD drawbacks at Ar beam
FTK infrastructure in USA15 Status and plans for 2015 A
- STT LAYOUT - SECTOR F SECTOR A SECTOR B SECTOR E SECTOR D SECTOR C
HF Test station at P5 A.Mestvirishvili.
HF “Slice test box” fabrication and installation
T1 Electronic status Conclusions Electronics Cards:
Mini-drawers, FE-ASIC , Integrator
ROBOX modification plans
HF Test station at P5 A.Mestvirishvili.
Presentation transcript:

HF UPGRADE PROJECT Y. Onel PM June 11,

Recent Highlights and News-I The PMT deliveries are now completed. Testing is going well. We had a meeting with Hamamatsu regarding our reject tubes. We have shipped back about 10 PMT’s ( low gain, high dark current and black cover problems) to be tested by them. The Base Board production is also going well. Working on the New HV testing system and forming a committee to evaluate the RFP responses. Bulgarian new module testing is completed. (there were some problems- we are working on this- We expect the reworked proto will be at CERN soon).Waiting a detailed report from German and Alexi. Both power supplies will be tested and evaluated at CERN E- pool using professional equipment and high expertise level of pool technicians. The HV RFP and decision committee is now formed. Members are: Germain, Alexi, Ianos, S.Los, M.Miller, D.Winn from HF and Magnus and S. Lusin from CMS Coordination. We have decided on the shield length- 54 mm (looks good !! the presentation by Ianos during HF meeting on May 14 th ) we will inform Mike Fountain to start with the production. Gain Sorting Proposal by Ugur is now ready. -A uniform gain distribution for one HF is outlined from the foist 900 PMT sample. Other than the fringes at the edge of the sample, we can get gain uniformity within2% -EM and HAD, and 4 Quadrant separation would work if we can deliver different HV for each group (total 24 groups). -As the operation gain is decided, we can develop sorting and HV distributions for each group. 2

CAEN and Bulgarian PSU’s Two modules from CAEN A1535 and A1511. Both floating ground. A1535 – to power cathode circuit, A1511 – two last dinodes Both modules shows perfect performance up to the 3 mA current (max for these module). Presently A1535 has up to 3kV output. Needs to be reworked to have lover Voltage and higher current A1535A1511 Modified Bulgarian Power Supply – Power supply was modified to meet needs of new m-anode PMT’s. Lower voltage. Current up to the 10 mA. New firmware to fix the spike problems. Both power supplies will be tested and evaluated at CERN E-pool using professional equipment and high expertise level of pool technicians Between two oscillators within the same channel cross-talk was detected during the tests of Bulgarian PSU. Unit is back to Sofia, will be fixed and will be back at CERN by June 8th HV Board

Recent Highlights and News-II There is an agreement for a new cable purchases– Thanks Chris Tully, Jeremy Mans and Pawel De Barbaro for this. There is also a strong support from Austin and Magnus on this. Decision is to purchase all ROBOX inside cables and 1/8 of 5m cables FEE and connector cables to the existing FEE and start installing these and purchase the remaining by Mid-2013 that we have all cables installed during LS1. This will enable us to go to the 2 channel readout option by LS1.5 or YETS ( ).This means that the HF FEE design and construction will go rather fast (att. to our Turkish and Brazilian groups ). HF new front end integration will be presented by Ianos. HF Electronics Packaging as well as the agreement within HCAL that we should pursue the Winchester Cables presented by Terry Shaw. Developing our “Project Org Chart” adding Brazilian Universities and ITU, Istanbul. Alberto Santoro and Gilvan-Augusto Alves are named as Co-L2’s for Brazil in our org chart. E.Gulmez BU-Istanbul is L2 for Turkey. 4

HF2012 Organization Chart 5

New Advanced Schedule 6

PCB production 12x Jumper base board production/checking jumper board testing PCB production Board assembly/testing Testing and QC at Iowa First shipment of PCB's to CERN 50% board production done All done, tested and delivered to CERN 3/1/ /15/12 4/15/ /15/12 5/15/12—6/15/12 6/15/12– 12/1/12 6/30/12 - 7/15/12 7/31/12 (Int. Milestone) 10/1/12 (Int. Milestone) 12/7/12 (Int. Milestone) SL SL, IS, AM SL MM, JC, DS, ZJ, GF, JK ZJ SL

PMT's Delivery dates at CERN Set 1 Set 2 Set 3 Set 4 Set 5 Set 6 Set 7 Set 8 05/15/12 06/01/12 06/15/12 07/01/12 08/01/12 08/14/12 09/01/12 09/14/12

Test stand setup Test new box ( set-up new ROB) Produce and assemble test equip Establish Testing Procedures Produce Test stand equipment AM Tests new Box New ROBOX at 904- operating New ROBOX at SX5- operating Test Stands at SX5—operating 4/23/12 - 5/15/12 3/31/12 - 6/30/12 4/23/12 - 7/31/12 4/15-6/30 5/15 - 6/7/12 7/31/12 - 8/31/12 7/31/12 12/23/12 IS, AM IS, MF, PD, TK AM, IS, AP IS, MF, PD, TK AM, HB, EB AM, IS, AP, GA, YG AM, IS, AP, GA, YG, SD, YOz, FO, SS, SC, NB Adding two students Marcos and Thiago from Brazil. 9

ROB mechanics Finalize Shield dimensions & All materials ordered QN + Iowa students pre-assembly Ship to CERN CERN Setup HF+ mechanics pre-assembly/cable prep. ROB Completion Dates 25% completion 50% completion 75% completion 100% completion Production contingency 04/01/ /14/12 06/01/ /01/12 09/01/12 09/14/ /01/12 10/01/ /01/13 05/01/ /31/12 07/01/ /31/12 09/01/ /31/12 11/01/ /21/12 12/22/ /28/13 PB, MT, IS, PD, TK ZJ, ET, GF, JC, JK, DS Olga, TK, PD, (+2 crews x2) 10

11 Assembly and Testing Base board population learning/training Populate and test baseboards HF+ Q1 (27) HF+ Q2 (54) HF+ Q3 (81) HF+ Q4 (108) HF- Q1 (135) HF- Q2 (162) HF- Q3 (189) HF- Q4 (216) 07/31/ /21/12 08/22/ /07/12 09/07/ /22/12 09/22/ /07/12 10/07/ /22/12 10/22/ /07/12 11/07/ /22/12 11/22/ /07/12 12/07/ /22/12 AM, IS, DK, MK, OK AM, IS, DK, MK, OK, EE, OO, BU, MY, SD, YOz, HO, KD

Activities on HF (HF+ HF-) HF + HF+ ROB’s out Disassemble Reassemble + testing HF - HF- ROB’s out Disassemble Reassemble + testing 12/03/ /18/12 12/19/12- 02/03/13 02/04/ /08/13 12/19/ /15/13 01/16/ /19/13 03/20/ /25/13 12

Back-up 13

PMT test in 2012-I Iowa is planning is to have all PMT's at CERN sometime in Sept All of the PMT's and base boards will be tested in 2012 at CERN We are in process of defining all test-stand setups and needed equipment to handle the testing of the base boards and PMT's. WE plan on having setups to test the equivalent of two boxes worth of PMT's at a time. Burn in HF Plus Side ROBOXs in Garages 210 days Mon 3/12/13 - Mon 1/14/14 and Burn in HF Minus Side ROBOXs in Garages 9/21/13 (as defined by the HF Project Schedule). 14

PMT test in 2012-II Functionality test – All base boards will be equipped with PMT’s and PMT + base board assembly will be tested at CERN. Primary readout is with HCAL DAQ and HF QIE etc. We will have four light distribution boxes (three in addition to existing one).  Number augmented to allow base board + PMT testing in parallel with new ROB test development. Two will be set up for testing of PMT’s + base boards (6 base boards tested at a time).  In addition to light distribution unit, setups will have: “Dark box” cover Signal and HV cables ( At the moment we only have cables for the one upgraded box.) Support for Base boards + PMT’s (using production ROB parts) All the necessary equipment components are designed currently at Iowa. 15

PMT test in 2012-III Before majority of PMT’s will be shipped, we will have 24 m-anode PMT’s + three baseboards at CERN to assemble and test one more “upgraded” ROBOX for test- stand/testing development  Most mechanics already assembled at CERN.  Needs cables from Fermi box.  Will be assembled and ready for use by May. This ROBOX will be used to define all the test procedures –LED and PED runs, SPE runs. We will define what info goes to database, traveler runs etc. 16