Florida Department of Transportation District 4 TSM&O Program Advanced Transportation Management System (ATMS) Installation in South Broward County ATMS.

Slides:



Advertisements
Similar presentations
DESTINATION INNOVATION PROGRAM SAFE COORIDOR ENHANCEMENT (SCorE) Jon Jackels Mn/DOT ITS Program Engineer Traffic Topics April 7, 2011.
Advertisements

Beltline Highway ITS – Ramp Metering Project ODOT Planners Meeting April 25, 2012.
SV-ITS PROGRAM: Silicon Valley Smart Corridor Project Overview
Melissa Ackert, E.I. Florida Department of Transportation
ITS Application of advanced sensor, computer, electronics, and communications technologies and management strategies in an integrated manner providing.
AVONDALE ROAD ITS 2006 COUNTYWIDE GRANT. AVONDALE ROAD ITS OVERVIEW OVERVIEW Location Location Avondale Road between Novelty Hill Road and NE 132 nd St.
CALTRANS’ TRANSPORTATION SYSTEM MANAGEMENT & OPERATIONS CTP 2040 PAC 1 Kris Kuhl Assistant Division Chief, Division of Traffic Operations 4/15/2014 CREATING.
Presented by: SAGE KAMIYA, P.E., PTOE
Rick Via Statewide Incident Management Program Manager Office: Leveraging Technology & ITS to Enhance Traffic.
Emerging Transportation Technologies in Virginia Ken Earnest Assistant Division Administrator Operations Division.
Transportation Data Palooza Washington, DC May 9, 2013 Steve Mortensen Federal Transit Administration Data for Integrated Corridor Management (ICM) Analysis,
Evaluation Tools to Support ITS Planning Process FDOT Research #BD presented to Model Advancement Committee presented by Mohammed Hadi, Ph.D., PE.
75 Express Lanes Segments A&B Construction From NW 170 Street to South of Miramar Parkway Community Meeting Presentation Tuesday April 28, 2015.
Gainesville Area Traffic Management System. Traffic Management System  In 1984, the original Traffic Signal Master Plan was developed for the Gainesville.
Lawrence Regional ITS Architecture Update. Today’s Agenda What is ITS? Review 2007 ITS Plans Review the proposed work plan Define project goals and objectives.
San Jose Traffic Signal Communications and Synchronization Project Presented by Ho Nguyen City of San Jose, Department of Transportation May 12, 2009.
Less Stop More Go EXPRESS LANES Travel Choices and Strategies to Relieve Congestion Presentation to FDOT’s Annual ITS Working Group Meeting March 2008.
Melissa Ackert, E.I. FDOT Matt Wilson, P.E. Jacobs Engineering
NE 203 rd Street & NE 215 th Street Intersection Improvements between US 1 & West Dixie Highway Florida Department of TRANSPORTATION Upcoming Project Development.
ITS Sketch Planning Tool Webinar 2:00 – 4:00 PM January 8, 2009.
FDOT District 1 ITS Project Update Katherine Duvall ITS Project Manager.
Definition - CommuterLink CommuterLink is an interagency transportation management system. What does that mean? Put another way, it is the use of computer.
Intelligent Transportation System (ITS) ISYM 540 Current Topics in Information System Management Anas Hardan.
2 Background Lake County –24 x 20 mi area –Population 690,000 –52 municipalities Congestion –No freeways –Limited 4-lane arterials –Transportation controversies.
Fast Forward Full Speed Ahead Presented at the Joint ITS Georgia / Tennessee Annual Meeting September 25, 2006 by Carla W. Holmes, P.E., PTOE Georgia Department.
Capital Improvement Program. During the Annual Strategic Action Plan (SAP) evaluation, long-term needs and priorities are identified by City Council Capital.
TSM&O FLORIDA’S STATEWIDE IMPLEMENTATION Elizabeth Birriel, PEElizabeth Birriel, PE Florida Department of TransportationFlorida Department of TransportationTranspo2012.
Active Traffic Management: The Next Step in Congestion Management NTOC Webinar Presented by Jessie Yung, P.E. Office of Transportation Management April.
Innovative ITS services thanks to Future Internet technologies ITS World Congress Orlando, SS42, 18 October 2011.
July 29, 2009 George Saylor, PE ODOT Senior ITS Engineer.
1 IntelliDrive SM Research, Development and Emerging Technologies National ITS Perspective Panel Joseph I. Peters, Ph.D. Federal Highway Administration.
Briefing on the Washington Metropolitan Area Transportation Operations Coordination (MATOC) Program Presentation to the Transportation Planning Board Michael.
AASHTO SUBCOMMITTEE ON SYSTEM OPERATIONS AND MANAGEMENT PHOENIX, AZ – APRIL 2013 SYSTEM OPERATIONS AND MANAGEMENT TONY KRATOFIL, P.E. MARK GEIB, P.E. STEVE.
THE I-75 DAYTON RECONSTRUCTION
“SIComP” Broward County Communications Upgrade Florida Department of Transportation District 4 November 21, 2005.
TRANSPORTATION ENGINEERING Planes, Trains, Automobiles and More Ardrey Kell High School February 23, 2012.
0 Christopher A. Pangilinan, P.E. Special Assistant to the Deputy Administrator Research and Innovative Technology Administration, ITS Joint Program Office.
Using Real Time Transportation System Performance Measures to Fuel a Regional Congestion Management System Robert L. Bertini Portland State University.
U.S. 31 at C.R. 400 South Intersection Improvement Clifty Creek Elementary School May 22, 2014, 6:00 p.m.
ORANGE COUNTY TRAFFIC MANAGEMENT SYSTEM FEBRUARY 13, 2007.
Georgia’s Intelligent Transportation System
Tennessee DOT SmartWay Update Presented by: Don Dahlinger, P.E. – TDOT September 2006 Presented by: Don Dahlinger, P.E. – TDOT September 2006.
2010 Regional Intelligent Transportation Systems Plan: 2015 Progress Report on Implementation.
SIGNAL OPTIMIZATION STUDY COMMUNITY DEVELOPMENT DEPARTMENT.
Bay County’s Intelligent Transportation System (ITS) Keith C. Bryant, P.E., PTOE Public Works Director Bay County, FL 2015 TRANSPORTATION SYMPOSIUM November.
Clay Packard, PE ITS GC Software Project Manager Florida Department of Transportation WAZE – FDOT Integration.
Traffic Management System Status Update February, 2008.
Update on the Escambia/Santa Rosa Regional Advanced Traffic Management System (ATMS) Feasibility and Implementation Plan Ben Faust, P.E. Advanced Traffic.
December 16, :00 – 2:45. MPM Team Agenda 1.Review of MPM Program and Team 2.Consensus items document 3. Upcoming activities 4. Discussion.
2010 Regional Intelligent Transportation Systems Plan: 2015 Progress Report on Implementation.
Transportation System Management & Intelligent Transportation Systems May 5, 2009 Steve Heminger Metropolitan Transportation Commission.
Work Zone Operational Enhancements Jennifer Livingston, P.E. ADOT – Senior Project Manager.
Brian Kary – Freeway Operations Engineer Minnesota Department of Transportation.
Orlando-Orange County Expressway Authority Update L.A. Griffin Manager of Expressway Operations March 20, 2008.
Intelligent and Non-Intelligent Transportation Systems 32 Foundations of Technology Standard 18 Students will develop an understanding of and be able to.
Work Zone & Incident Management Strategies Denise Markow, PE, TSMO Administrator Susan Soucie, PE ITS Project Manager ACEC/NHDOT 2016 Technical Exchange.
GRTC Bus Rapid Transit Project July 17, Agenda 1.BRT Concept 2.Project Goals 3.Project Benefits 4.Project Corridor 5.Proposed Multimodal Access.
Arterial Travel Times Using Bluetooth Detection Presented by Amit Sidhaye, P.E., PTOE Project Manager SIGNAL SYSTEMS & ITS ARLINGTON COUNTY May 16, 2013.
U.S. 1 AT CANAL STREET INTERSECTION IMPROVEMENTS U.S. 1 AT CANAL STREET INTERSECTION IMPROVEMENTS U.S. 1 AT CANAL STREET From South of Smith Street To.
TMCs – The Next Generation ITS Tennessee Annual Meeting / October 8, 2009 Dr. Robert Edelstein, PE, PTOE.
S.R. 30A / U.S. 98 / Panama City Beach Parkway Project Development & Environment (PD&E) Study F ROM M ANDY L ANE TO T HOMAS D RIVE I NTERSECTION B AY C.
A presentation by Kittelson & Associates, Inc. Broward Boulevard Presentation to the Broward MPO TCC and CIR March 2012 Agenda Item NA-1, Attachment.
Safer Work Zones Through ITS Interim Traffic Management System Florida Department of Transportation Tahira Faquir.
Statewide Mobility Performance Measures Team Purpose Consensus on approach and measures.
1 Benefits of ITS During Hurricane Evacuations Hurricane Evacuation Transportation Workshop April 5, 2003.
Project Overview – Phase 1
S.R. 30A / U.S. 98 / Panama City Beach Parkway
Lecturer: Andrzej Bujak Summer School 2015 Wroclaw School of Banking
Intelligent Transportation Systems
2010 Regional Intelligent Transportation Systems Plan: 2017 Progress Report on Implementation The Florida-Alabama, Okaloosa-Walton, and Bay County Transportation.
Presentation transcript:

Florida Department of Transportation District 4 TSM&O Program Advanced Transportation Management System (ATMS) Installation in South Broward County ATMS Deployment in Southern Broward County Financial Project Number(s): Federal Aid Project Number(s): A Contract Number: E4M79 PRESENTATION ATMS Deployment in Southern Broward County

Provide citizens with an overview of the ATMS Installation in Southern Broward County and it’s link to the Transportation System Management and Operations program (TSM&O). Provide public with an understanding of project benefits. Raise awareness of construction schedule and impacts. Facilitate coordination between the Florida Department of Transportation (FDOT) and impacted municipalities. Provide contact information for FDOT Design Project Manager, Melissa Ackert & Vladimir Velasco and Construction Public Information Officer, Dayana Iglesias. Meeting Objectives ATMS Deployment in Southern Broward County

TSM&O is a new program within FDOT. It is based on measuring performance, actively managing the multimodal transportation network and delivering positive safety and mobility outcomes to the traveling public in South Florida. Intelligence Transportation Systems (ITS) devices are the main components of any TSM&O approach. TSM&O and ATMS Concepts ATMS Deployment in Southern Broward County

TSM&O Program Objectives Improving efficiency of the existing transportation network through: Performance monitoring. Active arterial management. Integrating freeway management with arterial management. Incident management on arterials and freeways. ATMS Deployment in Southern Broward County

ATMS in Broward County Partnerships: FDOT District Four. Broward County MPO. Broward County Traffic Engineering Division. All municipalities within the project boundary. ATMS Deployment in Southern Broward County

-Hallandale Beach Boulevard -Hollywood/Pines Boulevard -US-1 -Pembroke Road ATMS in Broward County ATMS Deployment in Southern Broward County TSM&O Systems: Freeway(I-95). Arterial.

Congestion Relief Reducing delays Increasing average travel speed Increasing trip reliability Environmental Benefit Reducing fuel consumption Reducing emissions Improved Safety Reducing accidents caused by congestion, speed differential and sudden land changing Reducing in secondary accidents TSM&O Benefits ATMS Deployment in Southern Broward County

Benefits Increase motorists awareness of travel time and vehicular incidents. Improve incident response time through early detection. Data collected used to adjust traffic signals to improve timing and flow of traffic. Construction Timeline Summer Fall 2014 Cost: $5.3 million Contractor: World Fiber Technologies, Inc. Lane Closures: The project team will coordinate construction to have limited impact on the communities surrounding and within the project limits. When lane closures do occur, the project team will provide advanced notice to the impacted communities. TSM&O in Southern Broward County ATMS Deployment in Southern Broward County

Total Project Components 21 miles of fiber optic communication infrastructure. 42 Traffic Monitoring Cameras. 4 Arterial Dynamic Message Signs (ADMS). 15 Microwave Vehicle Detection Sensors (MVDS). 15 Travel Time System (TTS) readers. TSM&O in Southern Broward County ATMS Deployment in Southern Broward County

ATMS in Southern Broward County Devices Arterial DMS BlueTOAD Travel Time System (BlueTooth Origin And Destination) ATMS Deployment in Southern Broward County

ATMS in Southern Broward County Devices Traffic Monitoring Camera and Microwave Vehicle Detection Sensor on a Pole ATMS Deployment in Southern Broward County

Project Area -Hollywood/Pines Boulevard from NW 142 nd Avenue to South 28 th Avenue -Hallandale Beach Boulevard from SR-7 to Three Islands Boulevard ATMS Deployment in Southern Broward County -US-1 from Miami-Dade County Line to Hollywood Boulevard -Pembroke Road from I-95 to US-1

City of Hallandale Beach ATMS Deployment in Southern Broward County Project Components 6 miles of fiber optic communication infrastructure. 13 Traffic MonitoringCameras.(CCTV) (not to be confused with Red Light Running Cameras) 4 Microwave Vehicle Detection Sensor (MVDS ). 7 Travel Time System (TTS) reader; BlueTOAD.

City of Hallandale Beach ATMS Deployment in Southern Broward County Project Status All underground infrastructure is complete. 75% of Fiber Optic Cable has been installed. 25% of CCTVs completed. 100% of MVDS. 100% of ADMS. All ATMS device testing is anticipated to be completed by June 22 Anticipated Project Completion Date is July 22.

Contact Information Melissa Ackert, P.E. & Vladimir Velasco, E.I. FDOT Design Project Manager Dayana Iglesias Project Public Information Officer For more information visit ATMS Deployment in Southern Broward County