June 8-th 2004W.Baldini1 Ferrara production center Ferrara production center Production Readiness Review OverviewOfOperations P R R.

Slides:



Advertisements
Similar presentations
Lyon Gantry Status TEC meeting Dec D. Contardo Module production in Lyon Rigidifier test on R4 Frame tolerance effect on assembly plates Short term.
Advertisements

Muon EDR: Chamber design M2/3 R1/2 16/04/20031T.Schneider/LHCb Muon EDR 1.General description - AW read out -Cathode pad read out -HV supply 2.Details.
1 Short update Itzhak Tserruya HBD meeting BNL, April 11, 2006.
SEACORK INSTALLATION ON A CATAMARAN The first step is to make templates of all corner pieces to be cut from sheet material, which will be used for border.
G.Barber Tracker Planning & Mechanical Preparation June Tracker Planning & Mechanical Preparation An outline of (known) outstanding work to be carried.
Status Update on Mechanical Prototype in Rome November 6,
Plan for MRPC Production Yongjie Sun Center of Particle Science and Technology University of Science and Technology of China.
PRODUCTION and CERTIFICATION of Multi Wires Proportional Chambers for the LHCb Muon System at CERN K.Mair for the LHCb Muon Group CERN* Poster anlässlich.
University of Athens ATLAS BIS MDT assembly HEP 2001 Presented by Heraklion, 6-8 April 2001 D. Fassouliotis D. Fassouliotis.
MM mechanical prototype Work progress at CERN MicroMegas General Meeting, CERN, 5-6 November
Operational prototype work at CERN Status report MM Gen. Meeting, 06/11/2013 J. Wotschack1.
Engineering Design Review for TRD-Readout Chamber
MM mechanical prototype Work progress at CERN MMM Rome, 15/07/20131.
Production Readiness Review of Frascati MWPC Production Site December 4 th, 2003 – P. Campana.
LHCb MUON MPWC STATUS OF TOOLING, SITES, PRODUCTION AND MATERIAL PROCUREMENT.
WP7&8 Progress Report ITS Plenary meeting, 23 April 2014 LG, PK, VM, JR Objectives 2014 and current status.
Chamber Construction QC at CIEMAT B. de la Cruz CIEMAT (Madrid) CMS Week June 2002.
G. Martellotti CERN 22/04/20021 Tooling / Test Stations for MWPC (Meeting LNF, Roma1/Pz ) Production rate : 408 chambers (Fe + LNF) :192 R4 M1.
ISR Work Progress Report Muon Week April 10 th 2003 A. Benvenuti INFN Bologna.
Ferrara 8 june 2004M.Savrié1 Production Readiness Review Ferrara MWPC Production Site.
Status of CERN M1R2 production LHCb Muon meeting sept.061Thomas Schneider -Beginning of 2006 two visits to Erbicol because of several reasons: -Material.
Malte HildebrandtDC Status Report, Dear MEG Committee,PSI, April 14 th 2009 this is the first report concerning the drift chamber status as.
Status Report of activities in LNF Soldering procedure 1.Status of soldering machine 2.Measurement of wire position Chamber prototypes 1.Construction of.
M. Alfonsi LNF/INFN Cagliari 5 May 2006 M1R1 mechanical requirements  Space constraint Frame and pannel Pads readout and trigger sectors Gas inlet and.
Tariq J. Solaija, NCP Forward RPC EDR, Tariq Solaija Forward RPC EDR The Standard RPC for low  regions Tariq J. Solaija National Centre for.
Production Readiness Review Production steps and quality control 1.Panel production 2.HV bar gluing 3.Preparation of side material 4.Wiring and gluing.
RPC production at GT (status and plans). Status After the IFR meeting in Rome a new version of the Production Plan have been proposed to GT Main requirements.
T.Schneider/LHCb Muon EDR
News from the lab Large size Micromegas chambers Saclay, April Givi Sekhniaidze / Joerg Wotschack.
Production of Forward RPC Gaps CMS Forward RPC EDR (10/10/2002 – 11/10/2002) Seong Jong Hong KODEL, Korea University.
Status of production at LNF E. Dane, C. Forti, D. Pinci, A. Sarti – LHCb Muon CERN 25-may-04 Monday 24-may: closed chamber 30. Will close 2 more this week.
MWPC sandwich panels C.Forti INFN-LNF / LHCb-MUON EDR CERN 16 th April sandwich panels typologies of cathodes the mould the production procedure.
SD-HCAL technological prototype – Chamber and cassette production Nick Lumb Lyon, 3 February 2011.
Chamber construction Construction Tools Production sites Assembly Sequence (“travelers”) Manpower P. Campana LNF – LHCb Muon EDR Cern April 16 th, 2003.
16/04/20031PNPI / LHCb Muon EDR Wire Pad Chambers PNPI design for regions R4 in Stations M2,M3,M4  4 gas gaps of 5mm±70µm;  Active area: 1224x252.8 mm².
11/05/2000Wire Chamber Working Group Visit to Fermilab Participants: –Giulio Auriemma, Thomas Schneider, Burkhard Schmidt General Remarks: –Visit was organized.
LNF activities on WPC Panels Construction of prototypes and layout Status of tooling Proto 0, open items, plan,...
G. PassalevaRoma - July 28, 2004 Status of MWPC production site in Florence G. Passaleva.
Givi Sekhniaidze1 CERN, 25 March Givi Sekhniaidze2 The angles for the chambers are: LM1 – ° LM2 – 7.224° SM1 – ° SM2 – ° Do we.
14-Dec-15S.Movchan Straw manufacturing and QC1 Straw manufacturing procedure and QC tape and straw parameters specification conditions of straw production:
Total Cross Section, Elastic Scattering and Diffraction Dissociation at the LHC January 17, 2003TOTEM plenary meeting -Marco Bozzo1 CSC detectors for T1.
4-Jan-16S.Movchan Straw manufacturing and QC1 Straw tracker manufacturing procedure Dubna: assembly halls procedure conclusion Presented by S.Movchan.
Production Readiness Review at PNPI Chamber assembling: Main production and quality control steps 30 January 2004 – G.Alkhazov 1.Input components control.
22/04/20011Wire Chamber Working Group Status on O-ring closed Prototype Foam panels from Frascati (size: 279mm*341mm) No pad structure 4 independent gas.
Muon Meeting April 2004JsG Status of Chambers Production at CERN Jean-Sebastien Graulich o Open Questions from the PRR O-ring Aging, Aging tests, Storage.
Radioactive source and cosmic-ray test for the MWPC Davide Pinci on behalf of the Frascati-Roma1 MWPC group.
QA/QC in MM SM1 Mod 0 Production at INFN QA/QC MM SM1 Mod 0 - G. Maccarrone 19-Jan
Chamber Quality Control Before the construction several checks are performed on:  Panels (cathode and pad PCB)  GEM foil Tests on assembled detector.
10/7/2003Thomas Schneider1 Status report of CERN/PNPI Tooling support for PNPI M2R2 Prototype Plans towards the PRR.
To measure 0, mechanical oscillations of the wire to be tested are induced by applying a periodic high voltage (about 900 V) with a frequency of 300 ÷
Chiho Wang ATLAS TRT Krakow Workshop Duke University May, HV Plate Design & Assembly Chiho Wang Duke University.
Status of production at LNF E.Dane’ and C. Forti – Meeting with LHCb referees Firenze 14-mar-05 Christmas 3 ch/week Ch. 43.
G. PassalevaFirenze - September 8, 2004 Production Readiness Review Firenze MWPC Production Site G. Passaleva.
Zaragoza, 5 Julyl Construction of and experience with a 2.4 x 1 m² micromegas chambers Givi Sekhniaidze On behalf of the Micromegas community.
A.Cheremukhin (JINR, Dubna) CMS Preshower PRR, July 5-6, 2001, CERN1 Micro-module assembly -  -module elements - alignment of the silicon sensors to the.
CMS Upgrade Workshop, FNAL, Oct 28-30, O.Prokofiev Update ME4/2 Chambers and Tooling A construction of new ME4/2 prototype at CERN Factory tooling,
11/02/2005M. Alfonsi - LNF1 DETECTOR CONSTRUCTION M. Alfonsi - LNF.
Proposal for the construction procedures for the NSW chambers Harry van der Graaf, Nikhef Frascati, Nov
Chiho Wang ATLAS TRT Duke University CERN, Sep Barrel integration status.
2010/12/14 Caltech Massimo Benettoni FDIRC FBox (almost) ready for production Box design finalized (as possible) Gives precise Fblock positioning wrt guiding.
Activity report from LNF Panels Soldering tests Production site and tooling status WPC miscellanea (+7 cm layout, cathode costs, aging tests)
BM&N STS ladders assembly in VLHEP
RE 4/3 RPC Pre-assembly manual 1. HCP case preparation
Update on Pavia MM mechanical prototype
Quality Control in Straw Production
Status of straw production straw module assembling
Gluing jigs for Demonstrator
Tracker Outer Barrel COOLING Antti Onnela, CERN.
Overview of the Frascati Production Facilities
Gas Monitoring Chamber Production Status
Presentation transcript:

June 8-th 2004W.Baldini1 Ferrara production center Ferrara production center Production Readiness Review OverviewOfOperations P R R

June 8-th 2004W.Baldini2 1.WGS machine: Wiring, gluing, soldering, pitch measurement 2.WTM table: wire cutting, side bars gluing, wire tension measurement, open air HV test (single panel) 3.Assembling table: chamber assembling 4.Service table: HV connections, mylar tape on HV bar A, repairing/fixing problems Operations overview Clean room Outside the clean area 1.Gas leakage test 2.OPB mounting and soldering 3.Conditioning / HV test of the chamber 4.Uniformity test with source (?)

June 8-th 2004W.Baldini3 Clean room operations Preliminary operations Mounting the clamps to fix the panels on the frame (4 in the corners + 3 along each side of the panel) Positioning / alignment of panels on the frame Check of half gap height Protect the cathode with a Kapton foil Final cleaning of wire pads with Isopropyl alcohol Panels entering the clean room have been cleaned already (outside the clean area and in the grey room) and have been checked for geometry and general quality HV bar A HV bar B corners

June 8-th 2004W.Baldini4 We had problems with wires touching the HV bars, this was due to too high HV bars and to the presence of some tin in the points where the fixing clamps go The HV bars height has been reduced (in Potenza), the clamps have been slightly modified and the tin will be put only after the wiring Screwed to the frame Clamp for the panel Reference surface Clean room operations

June 8-th 2004W.Baldini5 1.Wiring 2.While wiring we prepare the guard wires and the glue dispensers (about 5 min before the end of the wiring process) 3.Put the guard wires 4.Gluing 5.Soldering 6.Measurement of the wire pitch (for the first chambers we plan to measure the pitch after each process ) 7.Turn the frame and repeat the operations 8.Rough cut of the wires Operations Operations on the WGS machine Clean room operations

June 8-th 2004W.Baldini6 M1R4 (min) M2R3 (min) M4R1 (min) M4R2 (min) M4R3 (min) M5R1 (min) M5R2 (min) Wiring (14 rpm) Wiring (10 rpm) Soldering Gluing Panels per frame Expected times Preliminary operations: right now it takes about min Clean room operations

June 8-th 2004W.Baldini7 Clean room operations Soldering of HV connections Gluing of the side bars Precise cut of the wires Wire tension measurement (for the moment 1 panel at a time). We plan to measure 2 panels at the same time, it needs about half a day of work. HV test in air of single panel Operations on the WTM table At this point, if all the quality tests are passed (conditions will be shown in the traveler), the panel is ready to be put on a chamber and will be stocked in the shelf: “ready to be assembled”

June 8-th 2004W.Baldini8 Clean room operations Assembling of the chamber We assemble the chamber using the same tooling used in Frascati We plan to distribute the glue automatically (not yet implemented). This allow a better control of the amount of glue The height of the chamber is measured (while assembling) in 14 points for each layer A B

June 8-th 2004W.Baldini9 Clean room operations Assembling of the chamber We observe some discrepancies form the expected heights, this could be due to: Too high pressure on the panel from the “forks” Some discrepancies in thickness and planarity of the panels The problem is still under investigation

June 8-th 2004W.Baldini10 Clean room operations Assembling of the chamber HV_side A B L1 = 9.50 L2 = L3 = L4 = L5 = The height of all the layers is measured with a micrometer while assembling the chamber. Exp. Values: L1 = 9.00 mm L2 = mm L3 = mm L4 = mm L5 = mm

June 8-th 2004W.Baldini11 Operations outside the clean area 1.Gas leakage test 2.OPB mounting 3.Conditioning/HV test of the chamber: It’s not clear yet how much time it will take the chamber conditioning. We have anyway space for 20 chambers (8 weeks production) in the rack for the conditioning. 4.Uniformity test with source (??) Once the chamber has been assembled it is moved outside for the following operations:

June 8-th 2004W.Baldini12 Operations outside the clean area Gas leakage test Flow in from the bottle Differential manometer Requirements:  5 mb overpressure The system has been tested with sealed volumes Chamber 1 is under test, at present it shows a very high gas leak

June 8-th 2004W.Baldini13 Quality control Wire pitch measurement Pitch distribution right after wiring Pitch distribution after the gluing of the wires Pitch distribution after the gluing and soldering processes Some fine tuning is still needed (optimize the contrast of the images) Side A Side B

June 8-th 2004W.Baldini14 Quality control Wire pitch measurement P428 (L4) P489 (L1) P535 (L2) P491 (L3) Chamber 1 Side A: 99.7% < ± 50µm 100% < ± 100 µm Side B: 95.9% < ± 50µm 99.5% < ± 100 µm Side A: 99.8% < ± 50µm 94.4% < ± 100 µm Side B: 99.7% < ± 50µm 99.8% < ± 100 µm Side A: 100% < ± 50µm 100% < ± 100 µm Side B: 99.7% < ± 50µm 99.8% < ± 100 µm Side A: 91.0% < ± 50µm 95.4% < ± 100 µm Side B: 91.0% < ± 50µm 91.4% < ± 100 µm Side A Side B

June 8-th 2004W.Baldini15 Quality control Wire tension measurement Laser Photodiode wire Machanical excitation Panel This simple and reliable method has been developed together with Firenze and Roma II

June 8-th 2004W.Baldini16 Quality control Wire tension measurement Laser Mechanical Excitation Photodiode At present it takes about 3.5 sec/wire (about 40 min/panel) With 2 panels it will take less that 2 sec/wire (40 min 2 panels) We are confident to setup the double panel measurement in about half a day of work

June 8-th 2004W.Baldini17 Quality control Wire tension measurement p173 Before the reinforcement of the frame After the reinforcement of the frame The wire tension is in average too high (> 75g) it will be reduced by 5 g

June 8-th 2004W.Baldini18 Quality control Wire tension measurement L1 L2 L3 L4 T = (76.4 ± 3.6) g T = ( 77.3 ± 4.0) g T = (76.3 ± 4.3) g T = (76.1 ± 4.6) g Chamber 1

June 8-th 2004W.Baldini19 Panel number Panel type ChamberComments 213L diplaced wire (by 1 mm) 175L Broken wire 161L10No WTM yet 221L20No WTM yet 208L30No WTM yet 178L40No WTM yet 173L4----Few wires with tension < 50 g 214L2----Bump on the cathode 489L11OK 535L21OK 491L31OK 428L41displaced wires 537L2OK 384L3Several broken wires 602L1Under test 437L3Wired and glued 494L4wired So far we have produced 15 M2R3 panels, the best 8 panels have been assembled in M2R3-CH0 and M2R3-CH1

June 8-th 2004W.Baldini20 Conclusions All the production and quality control processes are set and working. There are still some fine tuning needed (2 panels measurement with WTM, fine adjustment in the pitch measurement ) but they are essentially in their final version So far we have produced 15 M2R3 panels and we have assembled 2 chambers. The very first one (M2R3-CH0) was used essentially to exercise the assembling procedure, the second one (M2R3-CH1) is at present under leak test but it shows a high gas leak. We have to improve the chamber assembling The procedure to optimize all the production steps is almost in its final version The learning process of all the people involved is under way