Planning PERT - Project Evaluation and Review Technique) and CPM - Critical Path Method are network analysis techniques that are commonly used in project.
Advertisements

 Chapter 6: Activity Planning – Part 1 NET481: Project Management Afnan Albahli.
Project Scheduling Tools As part of CSA3040 © 2003, 2004 – Dr. Ernest Cachia.
Scheduling The Project  Scheduling Planning, budgeting and scheduling are all part of the same process Planning a project, developing a budget for it,
Tutorial 2 Project Management Activity Charts (PERT Charts)
Management & Development of Complex Projects Course Code - 706
Chapter 6 Activity Planning McGraw-Hill Education ISBN
2 Project Management  Management of work to develop and implement an innovation or change in an existing organization Examples: –New buildings –Weapon.
1 Project Management Inventory Management – In-class Example  Number 2 pencils at the campus book-store are sold at a fairly steady rate of 60 per week.
PROJECT TIME CONTROL. PROJECT SCHEDULING REFERENCES PRIMARY REFERENCE IN THIS PRESENTATION IS Operations Management, Ed 6, Heizer & Render, Prentice Hall,
Project Time Management
ELC 347 DAY 7. Agenda Questions Assignment 3 Due Assignment #4 posted  Due next week Group Progress report due next week Exam 2 next week  Same format.
Lecture 4 Project Management Chapter 17.
Roberta Russell & Bernard W. Taylor, III
1 B. SW Project planning & scheduling Recap from previous slide: It is important to decide on who is responsible for each activity. See Yeates & Cadle.
Software project management (intro)
Drawing AOA and AON networks
Project Scheduling & Budgeting CEE 402 Engineers Without Frontiers Lecture 6 February 26, 2003.
Software Project Management
Chapter 5 Planning. 222 Learning Objectives  Clearly define the project objective  Develop a work breakdown structure  Develop a network diagram 
Workshop-3 Gantt and Pert Chart.
Software Project Management Task Sequencing Activity Sequencing Concepts PERT charts Critical Path Analysis.
PROJECT MANAGEMENT Outline What is project mean? Examples of projects… Project Planning and Control Project Life Cycle Gantt Chart PERT/CPM.
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
ENGM91 ACTIVITY PLANNING Unit 2
COMP 208/214/215/216 Lecture 3 Planning. Planning is the key to a successful project It is doubly important when multiple people are involved Plans are.
Project Management: A Managerial Approach
WEEK 4 Introduction to Project Management. Agenda Phase 2: Planning ◦ Communication Plan ◦ Scheduling Preparation  Build an AON Diagram  Determine Critical.
© Pearson Education Limited 2004 OHT 8.1 Cadle and Yeates: Project Management for Information Systems, 4th edition Critical Path Method(CPM)
Create a Work Breakdown Structure (WBS) n Develop the project goal yourself n Take a cursory pass at defining the objectives –the preliminary plan n Have.
Geog 469 GIS Workshop Project Management.
Software Project Management
1 OMGT 3123 Project Management  Project Controlling  Project Management Techniques: PERT And CPM  The Framework Of PERT And CPM  Network Diagrams And.
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
PMI-Planning Process Group Lecture 08 Ms Saba Sahar.
Project Management Project Planning. PLANNING IN PROJECT ENVIRONMENT Establishing a predetermined course of action within a forecasted environment WHY.
Chapter 8 Scheduling.
University of Sunderland CIFM02 Unit 2 COMM02 Activity Planning Unit 2.
Project Management Organization Scheduling 31 January.
Chapter 7 : Risk Management – part 2
(M) Chapter 12 MANGT 662 (A): Procurement, Logistics and Supply Chain Design Purchasing and Supply Chain Analysis (1/2)
Projects and Activities Defining activities some assumptions that will be relevant when we start to produce an activity plan. Activities must be defined.
 Chapter 6: Activity Planning – Part 3 NET481: Project Management Afnan Albahli.
 Chapter 6: Activity Planning – Part 2 NET481: Project Management Afnan Albahli.
Unit 2 Time Management Prepared by: Prof. Seemaah Keddar.
Copyright 2006 John Wiley & Sons, Inc. Beni Asllani University of Tennessee at Chattanooga Project Management Operations Management - 5 th Edition Chapter.
Project Planning 1. Statement of work: written description of what is to be done 2. All activities are identified. Activity = job that requires labor,
Network planning models These project scheduling techniques model the project's activities and their relationships as a network. In the network, time flows.
Chapter 9 Planning. 222 Learning Objectives  clearly defining the project objective  developing a work breakdown structure  developing a network diagram.
Project Management Planning and Scheduling. “Failing to plan is planning to fail” by J. Hinze, Construction Planning and Scheduling Planning: “what” is.
Tools to Help  Product flow Dependencies and relationships of deliverables  Work breakdown structure The parts  PERT charts Program Evaluation and.
Activity Planning. Effort estimation – For whole project – For individual activity Detailed plan – Starting of each activity – End of each activity –
Critical Path Method(CPM)
Business Decision Making
Operations Research Lecture 5.
Project Management for Business
Activity Planning.
ACTIVITY PLANNING AND RISK MANAGEMENT
Software Development & Project Management
PERT - The Program Evaluation and Review Technique
Drawing the AON network
PROJECT MANAGEMENT (BSBI 622)
CEM 510 Construction Planning & Scheduling Dr Almohawis
Project Management (lecture)
Software Project Management 4th Edition
Software Project Management 4th Edition
Chapter 6 Activity Planning.
Project Management (lecture)
Chapter 6 Activity Planning.
Presentation transcript:

Chapter 6: Activity Planning – Part 2 NET481: Project Management Afnan Albahli

Identifying Activities There are three approaches to identify the activities or tasks that will make up the project: The activity-based approach. The product-based approach. The hybrid-based approach.

The activity-based approach The activity based approach consists of creating a list of all activities that the project is thought to involve. How? Brainstorming session involving the whole project team The analysis of similar past projects. One useful way is to divide you projects into stages and think what activities might be required at each stage. On way of creating the activity or task list is to create WBS (Work Breakdown Structure).

The activity-based approach (cont’d)

The activity-based approach (cont’d) In WBS we: Identify the main (high level) tasks (activities) required to complete a project. Then break each of these down into a set of lower-level tasks.

The activity-based approach (cont’d) When preparing the WBS: Too great depth should be avoided. Why? Will result in a large number of tasks that will need to be managed. Too shallow structure should be avoided. Why? This will provide insufficient detail for project control.

The activity-based approach (cont’d) Advantages (WBS) More likely to obtain a task catalogue that is: Complete and كاملة Composed of non-overlapping tasks غير متداخلة WBS represents a structure that can be refined as the project proceeds. Early in the project, It can start shallow. في البداية مبسط Developed as information becomes available e.g. during project analysis and specification phases. لاحقاً بتفاصيل أكبر Once the project activities have been identified (whether using the WBS or not) they will need to be sequenced.

The product-based approach It consists of producing a product breakdown structure PBS, and a product flow diagram PFD. Product Breakdown Structure (PBS) To show how a system can be broken down into different products for development. Advantage: It is less likely to omit a product.

The product-based approach (cont’d) Product Flow Diagram (PFD) Once a product breakdown structure has been created, work can then begin on creating a product flow diagram which identifies the order of precedence of products and will typically include multiple and complex parallel paths.

PBS

PFD

The hybrid-based approach A mix of the activity-based approach and the product- based approach. Most commonly used approach. The “WBS” in the hybrid approach is based on: a list of the deliverable products of the project; and a list of activities for producing each product.

The hybrid-based approach (cont’d)

Network Planning Models Network Planning Models: are project scheduling techniques that model project activities and their relationships as a network. Activity-on-Arrow techniques: CPM (critical path method). PERT (program evaluation review technique). Activity-on-Node techniques: Precedence Networks. These three methods are very similar and many people use CPM to refer to all of them.

Precedence Networks In the precedence networks: The nodes represent activities. The lines between nodes represent dependencies.

Precedence Networks (cont’d) Rules and Conventions • A project network should have only one start node. • A project network should have only one end node. • A node has duration. • Links have no duration. • Precedents are referred to the immediate preceding activities. • Time moves from left to right. • A network may not contain loops. • A network should not contain dangles.

Precedence Networks (cont’d) Loops can't be directly represented in a project network. If you know the number of times we expect to repeat a set of activities, then we can draw them in a sequence repeating them for the appropriate number of times.

Precedence Networks (cont’d) A dangle: Here what is meant by the diagram is: that the project will be finished once we “the program has been installed” and “the user manual is written”. “Write user manual” is a dangling activity.

Precedence Networks (cont’d) resolving the dangle