The ATS MD part III (Achromatic Telescopic Squeezing scheme) Participants: Any (active) volunteers Goal: 1)MD1 (S. Fartoukh & R. Assmann  10h): “Pre-squeeze’’

Slides:



Advertisements
Similar presentations
DS Quench TEST 2  MOTIVATION and METHOD: 1. Achieve 500kW on beam 1 – TCP7 collimators.(so far 500kW with beam 2 and 235kW over 1s with beam 1 were reached.
Advertisements

Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
1 Analysis of MD on IR1 and IR5 aperture at 3.5 TeV – progress report C. Alabau Pons, R. Assmann, R. Bruce, M. Giovannozzi, G. Müller, S. Redaelli F. Schmidt,
Highlights of the ATS MD part I (injection and ramp) … An 8h video game party carefully organized by Jorg et al. 1S. Fartoukh, LSWG 24/05/2011.
* IP5 IP1 IP2 IP8 vertical crossing angle at IP8 R. Bruce, W. Herr, B. Holzer Acknowledgement: S. Fartoukh, M. Giovannozzi, S. Redaelli, J. Wenninger.
LHC progress with beam & plans. Of note since last time Transverse damper Beta beating in the ramp Collimation set-up at 450 GeV & validation LBDS – systematic.
● 08:30 Loaded by mistake squeeze function to 2 m  Dumped beams ● 10:30-13:00 Test of new algorithm for long. Emittance blow-up to minimize oscillations.
LHC Technical Committee, 23/05/20071 LHC Commissioning Phases Squeeze presented by Massimo Giovannozzi on behalf of the LHCCWG Particular thanks to S.
Plan for start-up with beam Friday  19:00 Machine closed. Ramp for powering tests & pre-cycle  22:00 Pilots through nominal cycle up to collisions. Measure.
Friday to Saturday 02:00: Machine closed. 09:00: Cryogenics all OK. Preparing pre-cycle. 10:00: Pre-cycle started. 11:30: Pre-cycle finished. 14:00: Beam.
S. Fartoukh1st General HL-LHC meeting, The Achromatic Telescopic Squeeze (ATS) S. Fartoukh CERN/BE-ABP  Motivations  Basic principles of.
Summary Session 2 Machine Studies 15/2/2012 Ralph Aβmann & Giulia Papotti Thanks to Frank Zimmermann LHC Performance Workshop, Chamonix, R.
R. Assmann - LHCCWG Two Beam Operation R.W. Aßmann LHCCWG Acknowledgements to W. Herr, V. Previtali, A. Butterworth, P. Baudrenghien, J. Uythoven,
Evian 2014 historical perspective run 1: 2010: L peak >10 32 cm -2 s -1  2x10 32 cm -2 s : produce >1 fb -1  delivered.
LHC Progress Friday 30 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
S. FartoukhLSWG Day, Monday 18th, ATS MDs for Run II S. Fartoukh for the ATS MD team  Reminder  Goal & overall strategy  Proposals for 2016/
Saturday ● 06:00: Physics fill from the night shift ● 15:00: End stable beam mode: – problems with incorporation of settings for the squeeze ● 16:40:
MD Wed – Sat DayTimeMD Wed06:00UPS repair, ATS optics checks w/o beam 12:00Cycle, test ATS optics w/o beam 16: TeV: BPM offset determination for.
S. FartoukhLSWG Day, Monday 18th, ATS MDs for Run II S. Fartoukh for the ATS MD team  Reminder  Goal & overall strategy  Proposals for 2016/
LHC progress Sunday 3rd May 2015 Coordination: Mike Lamont, Wolfgang Hofle.
1 Commissioning and Operation of the machine protection system L. Ponce Acknowledgements: M. Zerlauth, J. Wenninger, D. Wollmann, V. Chetvertkova, G. Valentino,
Β*-dependence on collimation R. Bruce, R.W. Assmann C. Alabau Pons, F. Burkart, M. Cauchi, D. Deboy, M. Giovannozzi, W. Herr, L. Lari, G. Muller, S. Redaelli,
Saturday 11.9 ● From Friday – Minimum required crossing angle is 100  rad in 2010 – Plenty of aperture at triplets: > 13  (n1 > 10) – Can stay with 170.
CONTENT: Beam characteristics and MP concerns BI configuration Operational settings Collimators Planning Shift breakdown Thanks to: P.Baudrenghien, G.Bellodi,
Cryo back at 17:30 Beam back at 19:00 IR2 aperture until ~03:00 Since then no beam from the SPS:  Connector problem on MKD  Connector eroded, needs to.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Tue 23/8 – Wed 24/8 09:00 Start 90 m optics run – Preparation and verification of the collimation functions – Re-generation of functions for Transverse.
Preliminary MD Report R. Assmann, G. Papotti, F. Zimmermann
Wednesday
Ralph Assmann, Giulia Papotti, Frank Zimmermann 25 August 2011
MD Planning Fri – Sat (26. – 27.8.)
M.Fitterer, A.Patapenka, A.Valishev (FNAL)
Wednesday 8.9 External crossing angles:
1st LHC MD Period Started
LHC Commissioning with Beam
-9:00: Test IP transverse adjustment (CMS) and optics verification.
Saturday 24 March 2012.
Wire, flat beams and beam-beam MDs in 2017
ATS optics Results from MD3, MD4 and MD5
Saturday 21st April 00:33 Interlock during ramp on BLM HV
Friday 30th September 06:00 Operator dump fill #2171, int. lumi about 75 pb-1 Previous operator dump from physics was on 14 September ! 07:00 Start of.
MD2490 Measurement of the TMCI threshold at flat-top
Asynchronous free ATS optics for LHC & HL-LHC S. Fartoukh, BE-ABP
Thursday morning – optics correction
Tuesday TOTEM and transverse loss map (1) OK
LHC commissioning Week 38
Week 35 – Technical Stop and Restart
Summary of Week 26 Main aims: G. Arduini, B. Holzer, M. Lamont
04-05/08/2010 End of physics at ~11:00 after 18.5 hours ~120 nb-1.
Friday morning 10:30 Optics measurements and corrections.
Thursday :00: Physics fill from the night shift
BI cont. *** Summary Matching Monitor test *** We only had ~15minutes of inject and dump, but managed to see a profile with ~9e9 p (!)
Saturday 7th May Sat – Sun night
Collimation margins and *
Summary Thursday h21: Stable beams fill #1303.
Monday :20 beta beat corrections during squeeze for flat machine finished Afterwards fixing issues at injection: BPM rephrasing for B2 solved.
Pushing the LHC nominal luminosity with flat beams
Monday morning 09:40 Dump fill 2838, integrated ~130 pb-1.
Sat morning Until 12:40: Loss maps at injection
MD Planning Fri – Sat (1. – 2.7.)
Summary for LPC (March 7th, Ralph Assmann)
Plan for 1 m b* J. Uythoven & J. Wenninger
Saturday 12 March Morning: problem on RSD1.A12B2 – flow rate problem on the cooling water for the converter. 14:00: Loss map -500 Hz (positive energy offset)
Thursday 22nd March 00:20 – 02:40 on longer squeeze function, orbit and chroma correction at 4 TeV 2:40 – 5:30 second cycle with long squeeze 5:46 – 7:00.
Wednesday 23/2 Thanks CRYO!!!.
LHC Morning Meeting - G. Arduini
Another Immortal Fill….
15/12/2009 Vacuum interlock in sector 78 understood  out-gassing of a Penning gauge ignited as a result of ionization or dust arcing In conclusion: NO.
Daniel, Gianluca and Belen (for the Collimator team)
Saturday 29th October Friday during IP2 1 m squeeze test
Presentation transcript:

The ATS MD part III (Achromatic Telescopic Squeezing scheme) Participants: Any (active) volunteers Goal: 1)MD1 (S. Fartoukh & R. Assmann  10h): “Pre-squeeze’’ IR1 and IR5 to  * = 40 cm in view of a direct application for the LHC with tight collimator settings 2)MD2 (S. Fartoukh  6h): Squeeze IR1 and IR5 to  * = cm to validate the ATS scheme with two low-  IRs pushed to the HL-LHC  * or below Type of beams: 1)MD1:  <1.5-2  m with a fat pilot (1E10) for the first ramp & squeeze, and 1 nominal bunch per beam for the second ramp & squeeze (details in next slides) 2)MD2:  ~1-1.5  m with a fat pilot (1E10). Machine conditions: see details in next slides 1S. Fartoukh, LSWG 11/10/2011

2 Beam size [mm] and dispersion at 3.5 TeV (for  =3.5  m) Tunes vs  p Montague functions Triplet aperture compared to TCP tight settings (4 sigmas) Squeezing IR1 and IR5 to  * =10 cm … on paper S. Fartoukh, LSWG 11/10/2011

Activity (and comments)Time estimate [h] Recycling the machine from 3.5 TeV to new injection settings 0.5 Load the ramp, ramp, and arm the squeezed functions 0.5 Pre-squeezed down to  * = 40 cm with a few stops (e.g. 6m, 2m and 1m) to validate the new smoothing procedure for the sextupole currents 0.5 Test the standard and specific ATS knobs at  * =40 cm 0.5 Squeeze IR1 and IR5 down to  * =10 cm 0.5 Test the standard and specific ATS knobs at  * =40 cm 0.5 3S. Fartoukh, LSWG 11/10/2011 Procedures Dry run : 3h (floating MD)  Injection and ramp does not change w.r.t. previous ATS MDs  New squeeze sequence ready and checked, available under /afs/cern.ch/eng/lhc/optics/ATS_V6.503/OPTICS_round_IR1_40-10_IR5_40-10  New ATS squeeze hypercycle in preparation

Activity (and comments)Time estimate [h] Recycling the machine from 3.5 TeV to new injection settings before MD start (2.0) First fill with a fat pilot & Ramp down (5h) 1) ADT on only for damping injection oscillations 2) TCP, TCS, TCT remains to injection setting during the ramp, 3) Octupole off 4) Beam1/2 injected in bucket 1/2001 5) flat machine but parallel separation on in IR1/5 Injection, correction of orbit, tune, coupling and Q’ 0.5 Ramp, rough optics measurement/correction at 3.5 TeV ( closed orbit, tune, coupling, Q’) & manual adjustment of the TCPH/V to 6.5  in IR7 and TCTH/V to 8.5  in IR1 and IR5 1.0  0.5 Pre-squeeze IR1 and IR5 down to  * =1m (with a few stops e.g. 4m and 2m) and -Measurement/correction of closed orbit, tune, coupling, Q’ + incorporation -Measurement of the  -beating, dispersion and Montague function at 1m only 1.0 Pre-squeeze IR1 and IR5 down to  * =40 cm (with a few stops e.g. 80 cm and 60 cm) and -Measurement/correction of closed orbit, tune, coupling, Q’ + incorporation -Measurement of the  -beating, dispersion and Montague function at 40 cm only -Calculate a correction, send it and remeasure 2.0 If time permits and still some beam, manual adjustment of the TCPH/V to 4  in IR7 and TCTH/V to 4.5  in IR1 and IR5, then squeeze to 10 cm (… if still some beam) 0  0.5 Dump & Ramp down 0.5 4S. Fartoukh, LSWG 11/10/2011 MD1 (10h): Pre-squeeze to 40 cm & tight collimator settings

Activity (and comments)Time estimate [h] Second fill with 1 nominal bunch /beam (5 h) 1) ADT on (with new settings) 2) TCP, TCS, TCT follow the tight settings during the ramp (taking care of the absence of crossing angle for the TCT) 3) Octupole ON, 4) Beam1/2 injected in bucket 1/1, 5) flat machine but parallel separation on in IR1/5 Injection, correction of orbit, tune, coupling and Q’ 0.5  0.25 Ramp & rough optics measurement/correction at 3.5 TeV ( closed orbit, tune, coupling, Q’) 0.5 Pre-squeeze IR1 and IR5 down to  * =1m and then 40 cm with Measurement/correction of closed orbit, tune, coupling, Q’ + incorporation 1.0  0.5 Collimation related studies: finding the collision, establishing safe settings & alignment, loss maps. 3.0  S. Fartoukh, LSWG 11/10/2011 MD1 continued

6S. Fartoukh, LSWG 11/10/2011 MD2 (6h): Squeeze to 10 cm Activity (and comments)Time estimate [h] Recycling the machine from 3.5 TeV to new injection settings before MD start (2.0) Fat pilots only (6h) 1) ADT on only for damping injection oscillations 2) TCP, TCS, TCT remains to injection setting during the ramp, 3) Octupole off 4) Beam1/2 injected in bucket 1/2001 5) Machine stricly flat (no X-angle, no parallel sep in any IR) Injection, correction of orbit, tune, coupling and Q’ 0.5 Ramp, rough optics measurement/correction at 3.5 TeV ( closed orbit, tune, coupling, Q’) & manual adjustment of the TCPH/V to 6.5  in IR7 and TCTH/V to 8.5  in IR1 and IR5 0.5 Pre-squeeze IR1 and IR5 down to  * =1m and then 40 cm with -Measurement/correction of closed orbit, tune, coupling, Q’ + incorporation - Specific  -beat measurement and fine correction (if needed) at 40 cm 1.0 Squeeze down to  * =10 cm with stops and optics measurement at 30 cm, 20 cm and 15 cm & step by step manual adjustment of the TCPH/V down to 4  in IR7 and TCTH/V down to 4.5  in IR1 and IR5 - Measurement/correction of closed orbit, tune, coupling, Q’ + incorporation - Measurement of the  -beating, dispersion and Montague function - Eventually  -beating correction if this owrks with the ATS optics 4.0