1 Voltage Stability and Reactive Power Planning Entergy Transmission Planning Summit New Orleans, LA July 8, 2004 Entergy Transmission Planning Summit.

Slides:



Advertisements
Similar presentations
2004 NERC, NPCC & New England Compliance Programs John Norden Manager, Operations Training, Documentation & Compliance August 31, 2003 RC Meeting.
Advertisements

Summary of Second Draft of the NERC Standard PRC Disturbance Monitoring and Reporting JSIS Meeting August 10, 2010 Salt Lake City, UT.
RES-E Impact on Transmission Grid and Power System Reserves
Company LOGO Cleco Planning Process. Models Cleco uses SPP’s annual series of models to determine the NERC reliability violations. Cleco uses SPP or VST.
Northwest Quadrant Joint Security Study Southern Company Headquarters Birmingham, Alabama August 12, 2002 Presented by Saeed Arabi.
Challenge of Large Scale Wind Power Integration - Introduction to the Workshop Pradeep Perera Principal Energy Specialist Asian Development Bank.
1539pk 2003 MAJOR POWER GRID BLACKOUTS IN NORTH AMERICA AND EUROPE Copyright © P. Kundur This material should not be used without the author's consent.
Arrowhead  Weston Transmission Line Project Dave Van House Minnesota Power.
Tucson Area Reliability Mike Flores Control Area Operations Tucson Electric Power May 2000.
1. 11/26/2012: NERC Board of Trustees adopted CIP v5 CIP thru CIP CIP and CIP Version 5 Filing FERC requested filing by 3/31/2013.
“Importance of Reactive Power Management, Voltage Stability and FACTS Applications in today’s Operating Environment” Sharma Kolluri Manager of Transmission.
System Operator Conference NERC Standards Review for: Simulator Drill Orientation 2014 System Operator Conferences Charlotte NC & Franklin TN SERC/SOS.
Dynamic VAR’s [D-VAR] What are D-VAR Devices? Dynamic VARs… Fully integrated modular STATCOM with proprietary 3X overload Instantaneously injects precise.
1 PS ERC Reactive Power and Voltage Control Peter W. Sauer Department of Electrical and Computer Engineering University of Illinois at Urbana-Champaign.
New Orleans, LA July 8, 2004 John Zemanek Vice President, Transmission Entergy Transmission Planning Summit.
OPERATING IN THE EAGLE FORD SHALE
ANCILLARY SERVICES THE NEXT STEP IN MARKET GRANULARISATION.
Presentation to WECC TSS May 8, 2015
1 Entergy Louisiana, LLC (South) & Entergy New Orleans, Inc. Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans,
Voltage Collapse And Sympathy Trips.
1 Blackout 2003 See:
Generator Data Submittals 5/8/ Transmission Customer Forum Bob Jones Transmission Planning Southern Company Transmission 5/8/ Transmission.
Entergy Transmission Planning Summit New Orleans, LA July 8, 2004
Review of BPA Voltage Control Conference
1 Entergy Mississippi, Inc. Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 8, 2004.
ERCOT SOL Methodology for the Planning and Operations Horizons Stephen Solis 2014 OTS 1.
Houston Area Dynamic Reactive Project March 11,
“Reactive Power Management and Voltage Stability” Sharma Kolluri, IEEE Fellow Manager of Transmission Planning Entergy Services Inc Presentation at 2012.
2006 Reliability Study Scope Name Date. DRAFT 2 Purpose of Study Assess the PEC and Duke transmission systems’ reliability Develop a single reliability.
Voltage Collapse M. H. Sadeghi Winter 2007 KNTU. Power System Stability IEEE: Power system stability is defined as the capability of a system to maintain.
American Electric Power Service Corporation Jan 26, Coordinating Controls across CREZ  What dials are available to the operators?  What are the.
United States Grid Security and Reliability Control in High Load Conditions Christopher Lanclos—Mississippi Valley State University Research Alliance in.
Generator Test Data, Generator Capability Curve, and NPRR 366 Terms March 14, 2012 Mike Noth & Bracy Nesbit 1.
1 TRANSMISSION SYSTEM OVERVIEW NETWORK OPERATING COMMITTEE April 17, 2007 New Mexico Transmission System Overview.
Reliability Requirements Bill Blevins Manager of Operations Support ERCOT.
1 Mid-Continent Area Power Pool Wind Integration Studies Edward P. Weber August 16, 2007.
LAREDO PLANT RMR EXIT STRATEGY Presentation to Board of Directors March 16, 2004 Transmission Services Operations.
August 17, 2012 Solar PV Inverters Anuj Dixit Planning Engineer Resource Integration RPG Meeting.
Application and Implementation of State Estimator at Idaho Power Company S. Kincic and M. Papic.
SPP.org 1. ICT Construction Plan Evaluation and Reliability Assessment Part 1 Entergy Transmission Summit July 29, 2008 Astor Crown Plaza New Orleans,
ERCOT PUBLIC 4/21/ RTP: Cascade Analysis April 21, 2015.
1 Stability Issues in Entergy System Entergy Transmission Planning Summit New Orleans, LA July 10, 2003.
Jones Creek Project Submitted to RPG on July 7, 2014 July 22, 2014 Regional Planning Group Meeting.
Current Export Initiatives Jerry Mossing Exports Workshop February, 16,2006, Metropolitan Center, Calgary.
1 Entergy Louisiana, Inc. (South) & Entergy New Orleans, Inc. Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans,
© ABB Group August 23,2010 | Slide 1 MBPC Study – 1 st Load Pocket Preliminary Results for Discussion only Entergy Regional State Committee (ERSC) Southwest.
Grid Reliability Metrics by Jim Dyer Electric Power Group, LLC January 29, 2004 Washington, DC Transmission Reliability Research Review.
Steady-State Working Group: Resource Modeling Discussion Wes Woitt September 27 th, 2011.
Transmission Voltage Management Ross Owen Oncor Electric Delivery.
Steve Rueckert Director of Standards TPL Discussion – PCC Steering Committee March 25, 2014.
ERCOT Transmission Planning Process Overview and Recommendations November 6, 2002.
Voltage Control Brad Calhoun Consultant, Sr. Trainer Spring 2016.
©2003 PJM 1 Presentation to: Maryland Public Service Commission May 16, 2003.
SEMINAR PRESENATATION ON WIDEAREA BLACKOUT (AN ELECTRICAL DISASTER) BY:Madhusmita Mohanty Electrical Engineering 7TH Semester Regd No
Remedial Action Scheme Workshop RAS Workshop May 9, 2016.
1 NPCC – A-2 Dr. Mayer Sasson Transmission Planning Consolidated Edison of New York June 1, 2006 Presented to the NYSRC-RRS.
Barrilla Junction Area Transmission Improvements Project
IG BASED WINDFARMS USING STATCOM
Reactive Power Task Force
Team Members: Kyle Jones Mark Magee Jason Rippee
Proposal to Remove from Service the PV-COI RAS
Reactive Power and Voltage Control
Project WECC-0100 Update Load Modeling Task Force
DEC System Voltage Planning - June 2018
Mid-Continent Area Power Pool
TONBRIDGE POWER GREEN LINE
Palo Verde-COI RAS Retirement
Project WECC-0100 Update Load Modeling Task Force
Proposal to Remove from Service the PV-COI RAS
Palo Verde-COI RAS Retirement
Presentation transcript:

1 Voltage Stability and Reactive Power Planning Entergy Transmission Planning Summit New Orleans, LA July 8, 2004 Entergy Transmission Planning Summit New Orleans, LA July 8, 2004

2 Reactive Power/Voltage Issues from the Northeast Blackout NERC Recommendations Background on Voltage Stability Reactive Power Requirements for Generators Voltage Stability Concerns in Entergy Summary Presentation Outline

3 Voltages decay to almost 60% and initiates loss of load Slow recovery leads to generators tripping 60% voltage level also observed in 1995 Phoenix-area blackout Voltage Profile During Aug 14 th Blackout

4 East Lake 5 Exciter Operation Exciter trips to manual Exciter trips completely

5 Power System Outage Task Force Strengthen Reactive Power and Control Practices in all NERC Regions “Reactive power problem was a significant factor in the August 14 outage, and they were also important elements in the several of the earlier outages” -Quote from the outage report

6 #7.Evaluate reactive power and voltage control practices. Evaluate the effectiveness of existing reactive power and voltage control standards and how they are being implemented in the NERC regions Recommend revisions to standards or process improvements to ensure voltage control and stability issues are adequately addressed #14.Improve system modeling data and data exchange practices. Establish and begin implementing criteria and procedures for validating data used in power flow/stability models by benchmarking model data with actual system performance Validated data shall be exchanged on an inter-regional basis NERC Recommendations Pertinent to Reactive Power Planning

7 What is Voltage Instability/Collapse? A power system undergoes voltage collapse if post- disturbance voltages are below acceptable limits: –Less than 0.8 PU –voltage collapse may be due to voltage or angular instability Main factor causing voltage instability is the inability of the power systems to maintain a proper balance of reactive power and voltage control

8 Voltage Instability/Collapse The driving force for voltage instability is usually the load. The possible outcome of voltage instability: –loss of loads –loss of integrity of the power system Voltage stability timeframe: –Short term/transient voltage instability: seconds Motor dynamics/stalling OEL’s –long-term voltage stability: 1 – 60 minutes Tap changers/Voltage regulators OEL’s

9 Power-Voltage (P-V) Curve

10 Power – Voltage (P-V) Curve

11 Possible Solutions for Voltage Issues Install/Operate Shunt Capacitor Banks Add dynamic Shunt Compensation in the form of SVC/STATCOM to mitigate transient voltage dips Add Series Compensation on transmission lines in the problem area Implement under-voltage load shed (UVLS) program Construct transmission/generation facilities

12 MW Stator Winding Heating Limit - Per unit MVAR (Q) pf line Under-excitation Limit Lagging (Over-excited) Leading (Under-excited) Normal Excitation (Q = 0, pF = 1) Over-excitation Limit Stability Limit Generator Capability Curve

13 Reactive Power Requirements for Generators The facility should generate reactive power in accordance with the voltage schedule prescribed by the system dispatcher. Above 230 kV: 1.02 PU 230 kV: 1.01 PU 69 kV – 161 kV: 1.00 PU The facility shall have a reactive power capability to maintain a power factor between 0.95 lagging and 0.97 leading. Units must be operated with the voltage regulator in auto mode. Generator may be required to operate at its maximum reactive capability to meet required voltage schedules. Ensure that adequate reactive reserves are available so that the system can be restored satisfactorily.

14 Areas of Voltage Stability Concern West of the Atchafalaya Basin (WOTAB) North Arkansas Southeast Louisiana Western Region Amite South/DSG Mississippi

15 Reactive Power Projects Implemented in Entergy Down Stream of Gypsy (DSG) Area:  300 MVAR Shunt Capacitor Banks  Automatic Under Voltage Load Shedding Program  Static exciter at Ninemile 4 Unit  200 MVAR Shunt Capacitor Banks – 2005  300 MVAR SVC at Ninemile 230 kV – 2005 Western Region:  Automatic Under Voltage Load Shedding Program – 1998/modified 2004  Series Compensation on China-Jacinto 230 KV line – 2001  300 MVAR SVC at Porter 230 kV – 2005  Series Compensation on China – Porter 230 kV line

16 Summary The increasing need to operate the transmission system at its maximum safe transfer limit has become a primary concern at most utilities. Reactive power supply or VAR management is an important ingredient in maintaining healthy power system voltages and facilitating power transfers. Inadequate reactive power supply was a major factor in most of the recent blackouts.

17 QUESTIONS ???