FasTracks Moving Forward: Regional Transportation Plan (RTP) Amendment Staff Recommendation Phillip A. Washington and Team August 7, 2012.

Slides:



Advertisements
Similar presentations
Planning and Development Committee West Corridor Update May 10, 2007.
Advertisements

County of Fairfax, Virginia Department of Transportation Proposed Transportation Funding Policy Changes Fairfax County Department of Transportation March.
“A P3 Success Story” RTD’s EAGLE P3 Project. 2 East Corridor 22.8 miles of commuter rail between Denver Union Station and Denver International Airport.
National Utility Contractors Association of Colorado Wings Over the Rockies Air and Space Museum March 19, 2015.
RTD FasTracks Overview ColoRail Winter Meeting
DENVER UNION STATION  $500M Public Transportation Infrastructure Project with 5 Public/Private Partners, and 9 financing Sources.
Northwest Rail Update Nadine Lee, Northwest Rail Project Manager Regional Transportation District March 21, 2012.
Denver RTD and Its Role in TOD ULI Cleveland - Moving the Needle: A National and Local Perspective on Transit Oriented Developments June 26, 2013.
Colorado Rail Passenger Association Spring Meeting June 1, 2013.
Chicago Transit AuthorityJune, 2007 Chicago Transit Authority Regional South Metro Transportation Summit June 16, 2007 Matteson, Illinois.
Gilbert Road Light Rail Extension Transportation Project Advancement Agreement City Council Study Session December 4, 2014.
Federal Transit Administration New Starts Project Development Process
Learning from Denver’s FasTracks Experience June 20, 2011.
RTD Procurement and Construction Management Oversight for FasTracks Larry Hoy RTD Board Member, District J 1.
North Metro Rail Line FasTracks Citizens Advisory Committee September 18, 2013.
HRA Self-Financing Update What it means & what we’ve done Housing Briefing 19 January 2012.
Citizens Advisory Committee Quarterly Meeting Rick Clarke, Assistant GM – Capital Programs June 20, 2012.
CDOT Resource Allocation for DRCOG’s 2030 Regional Transportation Plan Adams Arapahoe Denver Broomfield Boulder Gilpin Clear Creek Jefferson Douglas.
October Prop K Strategic Plan & 5-Year Prioritization Programs Presentation to the Citizens Advisory Committee October 24, 2007.
Community Development & Planning Grant Pre-Application Meeting April 17,
North Metro Rail Line Request for Proposals (RFP) Commerce City Council August 19, 2013.
The FY 2006 New Starts Report Responding to the Demand for Transit.
2006 Annual Report on the Status of the Implementation of Proposition 400 Management Committee 9/6/06.
Public-Private Partnership Program 2015 Update 2015 American Council of Engineering Companies ACEC – Los Angeles Chapter Luncheon, July 8, 2015.
Citizens Advisory Committee Quarterly Update Bill Van Meter, Assistant General Manager, Planning September 19, 2012.
Jefferson Parkway Public Highway Authority Bidder Information Conference December 14, 2010.
February 24, “Moving Transit Forward”  A fiscally responsible, community-driven vision for restoring, enhancing, and expanding the Metro Transit.
Getting on the Ballot… and Getting the Ballot Right June 25, 2013.
Tom Norton, Executive Director Colorado Department of Transportation American Association of State Highway and Transportation Officials September 9, 2003.
Transportation Investment Act of 2010 AASHTO/MTAP Conference December 6-9, 2010 Savannah, Georgia Steve Kish, Transit Program Manager Georgia Department.
Silver Line Phase 1 – Status Report Status Overall Phase 1 Construction – 99% complete All Station at 98% complete except Wiehle – Reston East at 99% complete.
Regional Transportation Council Mobility Plan Workshop North Central Texas Council of Governments November 12, 2015.
Metropolitan Council 1 Twin Cities Region Transportation Policy Plan Nacho Diaz Metropolitan Council Evaluating Economic and Community Impacts of Transit.
Freight Mobility Strategic Investment Board. Making the Case… – Freight community educated legislators - developed champions Creation of.
Office of Major Project Development (OMPD) Overview November 2015.
North Metro Competitive Procurement RTD Board FasTracks Monitoring Committee October 8, 2013.
North Metro Rail Line Design/Build Contractor Staff Recommendation FasTracks Monitoring Committee November 5, 2013.
TIF 9 (Trinity River Vision) Expansion and Updated Project and Financing Plans Jay Chapa, Director Housing and Economic Development.
2016 REQUESTED BUDGET RTD Financial Administration and Audit Committee October 20, 2015.
Next Steps.  To begin Planning Council discussion about the MPO’s Next Steps. Now that the 2035 Regional Transportation Plan has been updated and adopted,
BUS RAPID TRANSIT (BRT) PLANNING EFFORTS STATUS 1 Planning & Development Committee April 5, 2016.
Real Property Policy Update Planning and Development Committee August 4, 2015.
NORTH AREA TRANSPORTATION ALLIANCE (NATA) Our Mission towards better transportation and economic development.
RTD FasTracks Projects for the DRCOG 2040 RTP (Baseline Report) FasTracks Monitoring Committee July 8, 2014.
Counties Transit Improvement Board: Program of Projects & Transit Investment Framework Workshop 3 Board Workshop October 16, 2013.
Review of 2016–2021 Strategic Budget Plan Development Process and 2016 Budget Assumptions Financial Administration and Audit Committee April 14,
2014 Annual Program Evaluation (APE) Status Update April 1, 2014.
2015 – 2020 Strategic Budget Plan Financial Administration & Audit Committee June 10, 2014.
Southeast Rail Extension FasTracks Monitoring Committee July 14, 2015.
Southeast Rail Extension Update RTD Board of Directors FasTracks Monitoring Committee March 3, 2015.
2015 Annual Program Evaluation (APE) Status Update July 14, 2015.
Update: Reports to DRCOG RTD Baseline Report to DRCOG on FasTracks RTD SB 208 Report to DRCOG Planning & Development Committee June 3, 2014.
2018 – 2023 Strategic Budget Plan
Update of Transportation Priorities Plan
Northwest Area Mobility Study FasTracks Monitoring Committee
Review of 2018–2023 Strategic Budget Plan Development Process and
2016 POP Investment Strategy: Funding Options
Heather Copp – CFO and AGM of Finance and Administration
Mobility Choice Blueprint
2017 Annual Program Evaluation Update
Future Construction FasTracks Corridors Federal Funding Analysis
Regional Railroad Authority (WCRRA)
RTD Procurement and Construction Management Oversight for FasTracks
RTD Procurement and Construction Management Oversight for FasTracks
Briefing to HRTAC re: HRBT Expansion Project Cost Estimates, Funding Mechanisms, and Next Steps December 13, 2018.
Durham and Orange Transit Plan Funding Needs
February 2017 New Starts Financial Plan
2014 Annual Program Evaluation (APE) Status Update
2020 RTP Update - Proposed Changes to Transit Projects
Northeast Area Transit Evaluation (NATE) II Update FasTracks Monitoring Committee August 5, 2014.
Presentation transcript:

FasTracks Moving Forward: Regional Transportation Plan (RTP) Amendment Staff Recommendation Phillip A. Washington and Team August 7, 2012

2 FasTracks Guiding Principles Staff relied heavily on our Guiding Principles to develop our approach for the RTP Amendment –Ensure every step contributes to the full vision –Focus money available to the greatest good –Spend public money wisely –Maximize outside funding before going to taxpayers –Deliver key investments in all corridors Build As Much As We Can As Fast As We Can Until It Is All Done!

3 RTP Amendment Overview RTD’s current assumption is to complete all of FasTracks with the existing 0.4 percent sales and use tax –RTD Board and stakeholders determined timing is not right to pursue a 2012 election; Board has not identified a future election year Due to this decision, RTD needs to update DRCOG’s Regional Transportation Plan (RTP), which identifies transportation projects that can be funded through 2035 –The RTP must be fiscally constrained to keep the entire region in line for federal funding –RTD, CDOT, and the region’s cities and counties must submit specific project lists and construction timeframes for all projects to be completed prior to 2035 to ensure the RTP remains fiscally constrained

4 RTP Amendment Overview (cont.) RTD must submit an RTP Amendment in August 2012 –This submittal will represent a snap-shot in time, and will change as new opportunities arise –A full SB 208 report will be submitted in early 2014 The projects identified for completion by 2035 are based on their ability to leverage public/private funds and/or receive federal grants The project list and placeholder schedule can be revised through future RTP Amendments Staff requests formal recommendation tonight from the FasTracks Monitoring Committee on the proposed content of the RTP Amendment

5 Recommended List of Projects for RTP Amendment and Rationale Currently committed projects: Covers projects under construction and those funded through the $305 M I-225: RTD Board has approved construction of the entire line North Metro DUS to 72nd: Completing this segment positions North Metro for a future New Starts grant for the rest of the project US 36 Bus Rapid Transit to Table Mesa (remaining commitment): Allows RTD to continue partnering with CDOT and HPTE to leverage state funding and toll revenues Southeast Extension: Allows RTD to begin the New Starts grant application process –Process takes several years to complete; no Board decision on local match for 15 – 18 months

6 RTP Amendment: Financial Plan Results Assuming No Additional Revenues 2013 – – – 2035POST RTP 2035 – 2044 West Rail Line (2013) Central Corridor Planning Study (2012/2013) Central Extension US 36 Bus Rapid Transit: $120 M for Managed Lanes to 88 th Street (2012 – 2014) and $15M for Managed Lanes to Table Mesa (2014 – 2015) US 36: Remaining RTD Commitment Denver Union Station (2015) Northwest Rail: Longmont Station (2015) Northwest Rail: Westminster to Longmont Southwest Corridor Extension: UP Rail Line Relocation (2015) Southwest Extension Eagle Project (2016) I-225 (2016) Southeast Extension: Completion of New Starts Application (2016) Southeast Extension North Metro: Construction to Stock Show (2017) North Metro: Stock Show to 72 nd North Metro: 72 nd to 162 nd

7 Opportunities for Schedule Acceleration Successful future sales tax election –Potential RTD initiative –Potential RTD/CDOT initiative Better than expected sales tax revenues Additional grants, unsolicited proposals or public-private partnerships Current construction projects completed under budget Partnering with our stakeholders to make every dollar count through –Early agreement on project scope and no additional changes during construction –Timely reviews and permit approvals –Maximizing opportunities for local match

8 Looking Ahead August 2012: Formal RTD Board action on RTP Amendment and financial plan; submittal of RTP Amendment to DRCOG February 2013: RTP Amendment approval by DRCOG Ongoing: Regional dialogue on implementation of the entire FasTracks program February 2014: RTD submittal of a new SB 208 report

9 Marking Off Milestones

10 Southeast Corridor Extension – New Starts Grant Application RTD will request “Entry into Preliminary Engineering (PE),” the first of three major milestones in the New Starts grant process, in September 2012 –The full New Starts process will take a minimum of 2 ½ years to complete As part of this initial submittal, RTD needs to demonstrate a “reasonable assumption” for when local match funding will be available for this project –Final RTD Board decision about the allocation of local match funding will not be required for another 15 – 18 months –RTD has initiated discussions with local stakeholders about the potential for external sources of local match funding for this project A financial plan will be submitted to FTA as part of RTD’s request to enter PE that will: –Be consistent with the RTP amendment, except that RTD would assume some sort of placeholder financing in 2015/2016 that could accelerate the Southeast Corridor Extension project to be completed by This placeholder financing could ultimately be filled through an external source of local match funding.

11 Questions?