Experimental hall in Japanese mountain site Y. Sugimoto 2012.5.22 ILD MDI/Integration 1.

Slides:



Advertisements
Similar presentations
Kitakami IR Access Discussions T. Markiewicz/SLAC 13 May 2014 SiD Meeting / AWLC Fermilab.
Advertisements

SiD Surface assembly Marco Oriunno (SLAC) MDI-CFS Meeting Sep. 4-6, 2014, Ichinoseki (Japan)
Manpower and space requirements for ILD 2015/1/13 Y. meeting at SLAC 1.
Assembly Hall in Hybrid-A’ and ILD 2014/9/6 Yasuhiro Sugimoto 1.
SiD assembly Marco Oriunno (SLAC), May. 14, 2014 ALCW 2014, Fermilab Infrastructures & Timeline for Hybrid Access.
DH in Hybrid-A and ILD 2014/9/5 Yasuhiro Sugimoto 1.
Construction and Installation of the CLIC Experimental Area
1 FD Support and Pacman for GLDc 27 Aug Yasuhiro Sugimoto KEK.
Global Design Effort - CFS for Asian Single Tunnel Configuration Design Progress Masanobu Miyahara KEK.
Tracking Integration Challenges Y. meeting 2013/9/25.
1 GLD Surface Assembly Y. Sugimoto KEK
1 ILD/CMS Engineering Meeting M. Joré – ILD integration philosophy Integration philosophy of ILD Matthieu Joré – January 21st Integration of the subdetectors.
SID Engineering Marco Oriunno (SLAC), Jan CLIC Workshop, CERN Toward the TDR.
LCC Linear Collider Collaboratio ILC - CFS 12 November 2013 LCWS13 Tokyo University 1 Site-specific CF design from TDR LCWS13, 12 November 2013 Atsushi.
Global Design Effort - CFS ILC CFS and Global Systems Meeting 1 ILC CFS AND GLOBAL SYSTEMS MEETING CONVENTIONAL FACILITIES AND SITING GROUP GENERAL.
1 Alternative assembly option of ILD Y.Sugimoto 2010/10/18 ILD Integration
Experimental hall in Japanese mountain site Y. Sugimoto 1.
ARUP Studies Update ILC Interaction Region Design Requirements John Osborne CERN, Yung Loo & Matt Sykes (ARUP) CFS-ADI Joint Meeting - University of Tokyo.
1 Discussion for basic options — engineering video conference July 12, 2006 Outline Water pool — advantages — issues, problems, engineering options Aquarium.
LCWS14 - Belgrade October 6-10, 2014 Conventional Facilities & Siting Working Group Summary V Kuchler, M Miyahara, J Osborne.
ILC experimental area - How to ‘develop’ CFS details for TDP (cavern size, number of shafts, HVAC, EL spec etc) ? - KEK site specific issues CFS V.Kuchler.
PD5: Detector Integration / Machine Detector Interface T. Markiewicz/SLAC 15 May 2014 SiD Meeting / AWLC Fermilab Summary.
LINEAR COLLIDER COLLABORATION Designing the world’s next great particle accelerator Detector Hall Configuration Overview New baseline (Hybrid A’) proposed.
Philip Burrows SiD Meeting, Paris 11/02/081 Machine Detector Interface Issues Philip Burrows John Adams Institute Oxford University Thanks to: Tom Markiewicz.
1 GLD and GLDc Sep. 12, 2007 Y. Sugimoto KEK. 2 Compact GLD Option Motivation –GLD and LDC will write a common LoI –The detector design should have common.
4366-ILD-T-Platform-and-environment.ppt A. Hervé Seoul workshop 17 February 2009 Concept of Platform and Environment A. Hervé / ILD-Webex meeting.
10/2010 IWLC2010 Global Design Effort 1 Brief Overview of Interaction Region Conventional Facilities in RDR Times Presenter Tom Lackowski.
1 BDS and Detector schedules for discussion at MDI meeting August 15, 2006 Andrei Seryi with input from Martin Gastal, Yasuhiro Sugimoto et al.
MDI DBD Editors Report Tom Markiewicz/SLAC SiD Collaboration Meeting, SLAC 22 August 2012.
ILD Magnet & calorimeters integration meeting Questions to be addressed 01-02
ILD requirement for assembly space and time 2015/11/3 Yasuhiro 1.
Strategy of detector solenoid construction Yasuhiro Sugimoto KEK 1.
ILC D RAFT P ROJECT S CHEDULE K LYCLUSTER 500GeV K Foraz & M Gastal ILC Mechanical & Electrical Review and CFS Baseline Technical Review Many thanks to.
Access Yard Assembly Marco Oriunno (SLAC), November 13, 2013 LCWS13, TOKYO.
9/17/07IRENG071 Cryogenic System for the ILC IR Magnets QD0 and QF1 K. C. Wu - BNL.
GLD experimental hall and detector assembly Y.Sugimoto KEK 27 Sep
Construction Schedule for Baseline and Hybrid A’ Configuration 1 5 th September, 2014 J-POWER MDI-CFS Meeting - Ichinoseki City, JAPAN.
March 22, –  Design Concept & Hall Layout  Access Tunnel  Top heading Tunnel  Displacement of detector hall by push-pull operation.
Assembly scenario of ILD Si trackers 2015/4/21 Yasuhiro 1.
Philip Burrows MDI Panel Meeting 15/08/06 Philip Burrows John Adams Institute Oxford University SiD and IR/MDI Issues.
FCC-hh MDI 5 th Meeting Friday 13 th March 2015 Civil Engineering Layouts for Experimental Caverns – First Draft Charlie Cook (GS), John Osborne (GS)
ILD and SiD in Japanese site (from discussions in SiD/ILD E/D Interface Working Meeting) Yasuhiro Sugimoto, Marco Oriunno 2011/12/15 SiD
1 May 22, Y.Sugimoto Update of detector hall in mountain region.
SiD MDI Issues Tom Markiewicz/SLAC Beijing ACFA/GDE Meeting 05 February 2007.
Experimental hall in Japanese mountain site 2011/11/30 Yasuhiro CFS Webex meeting 1.
MEA Machine and Experiment Assembly Norbert Meyners, MEA 12. July 2007ILC IRENG07 WG-A1 LDC Engineering Design (Status) Introduction General Design Detector.
SuperB Integration SuperB Experimental hall. Related topics of Slac D&D activities.
1 Cryogenic System of Interaction Region (SiD, ILD, QD0, QF1, Crab Cavity) in the Japanese Mountain Site WebEx meeting : June 19 th, 2012 IPNS/Cryogenic.
Octobre LAL Orsay Report from the IRENG07 workshop at SLAC W. Lohmann, DESY from Septembre 17 – 21, ~ 100 participants - plenary and parallel sessions.
An idea of ILD general assembly plan 2015/10/8 Yasuhiro Integration Meeting 1.
Kitakami Side AHCAL Assembly or anywhere in any detector.
M.Oriunno, SLAC 1 SiD installation with horizontal access shafts Marco Oriunno, SLAC SiD/ILD Engineering Meeting SLAC, December 2011.
1 Update of detector hall in mountain regions Y.Sugimoto in Granada.
Experimental Hall in Mountain Regions
SiD Collaboration Meeting SLAC, December 2011
2016/9/30 Yasuhiro Infra/CFS mini-ws
Detector Hall Design and Cost Information CONVENTIONAL FACILITIES
Introduction and Meeting Objectives
Detector Utility/Service Cavern
Yasuhiro Sugimoto 2012/2/1 ILD integration meeting
FCC Civil Engineering John Osborne, Jo Stanyard, Matt Stuart(SMB - Site Engineering - FAS Section) Cost & schedule Phase 3 - specification 10th May 2017.
Marco Oriunno (SLAC), March 12, 2014 MDI WG
Experimental hall design in Japanese site
BDS Cryogenic System RDR Status and EDR Plans
Update of experimental hall in Japanese mountain site
Detector Service Cavern for ILC
Detector hall in mountain regions
Sub-Detector Assembly Area Summary of discussion at ALCW2015
ILD-0 overall dimensions C.Clerc ILD meeting, Seoul 17/02/09
Detector hall in mountain regions
Presentation transcript:

Experimental hall in Japanese mountain site Y. Sugimoto ILD MDI/Integration 1

Outline Recent progress Design criteria Underground detector assembly –Assembly area –Timeline Cryogenic system for ILC central region Comparison with RDR design 2

Recent progress Updated design has been presented at CFS BTR meeting at CERN in March –Longer main cavern –Larger alcoves At the CFS BTR meeting, someone said it is too large to keep const-containment, and someone said it is still too small to integrate ILD underground At KILC2012 workshop, Y.S. made a presentation showing that the new design is large enough for ILD integration and small enough for cost-containment This talk is based on the presentation made at KILC2012 3

Design criteria Experimental hall in Japanese mountain site could be quite deep (>100m)  Horizontal access tunnel instead of vertical shafts Since “CMS style assembly” is not applicable, we need enough space in the cavern for detector assembly Enough size of alcoves is necessary for assembly and maintenance (opening) of detectors Good geology of granite allows bullet shape cavern rather than egg shape cavern Horizontal access tunnel should be large enough (~11m) in order to let large solenoids (  ~8m) go through 4

Design shown at CFS BTR 5

6

7

Underground detector assembly A possible detector assembly scenario for ILD has been drawn to see if the underground cavern area is large enough 8

Detector assembly area Area 1: Platform –YB0 assembly –Barrel detectors installation/cabling –Endcap calorimeters installation Area 2/3: Alcoves –Endcap calorimeters cabling –QD0 support tube assembly –FCAL install/cabling Area 4: Tentative platform on beam line side –YE, YB+, YB- (iron yoke and muon detector) assembly/install/cabling Area 5: Loading area side –HCAL rings assembly –Tooling assembly –Storage area 9

Boundary conditions Cranes –250 ton crane for each detector on beam line side –30 ton crane for each detector on loading area side –2.8 ton crane in each alcove In order to minimize the size of alcoves, the crane rails should be supported from the arch part  Only small cranes can be used The height of alcoves have to be increased from 19.6m to 20.5m (for ILD) to let the crane girder pass over the detector Work conflicts –In order to avoid conflicts of parallel works, first few hours of each working day should be dedicated to transportation to each assembly area 10

Step 1 Tentative platform is assembled in Area4 using a crawler crane Central barrel yoke YB0 is assembled on the platform using 250 ton crane HCAL modules are assembled to a ½-z ring in Area5 using 30 ton crane Cradle for coil installation is assembled in Area5 using a crawler crane 11

Step 2 Solenoid coil is moved to the platform using two sets (one from SiD) of 250 ton crane 12

Step 3 Endcap iron yoke (YE+) is assembled in Area 4 Solenoid coil installation to the YB0 in Area 1 13

Step 4 Muon detector installation to YB0 14

Step 5 YE+ is moved to platform using air- pads after muon detector installation HCAL barrel ½-z ring is assembled in Area 5 15

Step 6 Endcap yoke YE- is assembled in Area4 Muon detector of YB0 cabling HCAL barrel ring assembly in Area5 16

Step 7 YB0 shifted in z direction Endcap HCAL installation in Area 1 Scaffold for endcap cabling is assembled in Area 5 17

Step 8 YE- is moved to platform ½ of barrel HCAL is moved to platform using two 250 ton cranes, and installed Endcap yoke (+) is pushed into Area 2 Endcap HCAL cabling in Area 2 Scaffold for barrel cabling is assembled in Area 5 18

Step 9 Another barrel yoke ring YB+ is assembled in Area 4 Central barrel YB0 is shifted in z direction Barrel HCAL (+) cabling in Area 1 Endcap HCAL (-) installation in Area 1 19 Transport of iron yoke block

Step 10 Endcap yoke (-) is pushed to Area 3 ½ of barrel HCAL is moved to platform using two 250 ton cranes, and installed 20

Step 11 YB+ muon detector installation and cabling in Area 4 Endcap ECAL (+) installation using 30 ton crane in Area 1 Barrel HCAL (-) cabling in Area 1 Endcap HCAL (-) cabling in Area 3 21

Step 12 Endcap yoke (+) pushed into area2 Endcap ECAL(+) cabling Endcap ECAL(-) installation in area1 using 30 ton crane 22

Step 13 YB+ is moved to Area 1 Another barrel yoke ring YB- is assembled and muon detectors installed in Area 4 Endcap ECAL (-) cabling in Area 3 Barrel ECAL is installed in Area 1 23

Step 14 Barrel ECAL cabling in Area 1 24

Step 15 Detector is closed and field mapping is performed QD0 support tubes assembly in Area 2/3 QD0 and BCAL installation/cabling in Area 2/3 After removing the tentative platform in Area 4, beam line shield is constructed 25

Step 16 Detector is opened again TPC installation in Area 1 Lumical installation using 2.8 ton cranes in Area 2/3 26

Step 17 Si inner trackers are installed in Area 1 27

Step 18 Detector is closed again and ready for detector pre- commissioning 28

A possible timeline Assumptions –YB rings: 50d each –YE: 100d each including muon detector installation/cabling –Muon detector: 20d+20d for each barrel ring –Liquid He becomes available 8 months after the cavern gets ready –Field mapping will be done after ECAL installation and cabling: 20d for cool down, 60d for mapping, 20d for warm up –Others Estimation by calorimeter groups Rough guess for other detectors 29

A possible timeline 30

A possible timeline 31

A possible timeline Detector can barely be ready for physics run within 8 years from the ground breaking If GDE intends to change the schedule of accelerator construction and commissioning, it should be discussed with physics groups 32

GDE Timeline (Flat site) 33

Cryogenic system Compressor cavern common to damping ring and detector solenoids (+ QD0 + QF1 + Crab cavity) at the center of damping ring Cold box in the detector cavern Two plans; –Plan A: One cold box for all –Plan B: 3 cold boxes: ILD, SiD, BDS Detailed design will be presented by Takahiro Okamura on Friday After ILD decides our preferable design, we have to discuss with SiD (early June by Webex?: dead line of the draft of the DBD common part is June 15) 34

Cryogenic system 35

Cryogenic system Plan A –Flexible transfer tube for 4K He above the detector Plan B –Flexible tube for high pressure He gas in the cable pit 36

Cryogenic system SiD design –SiD design is based on the egg-shape cavern which has 5m larger space near the wall than Japanese cavern design –US cavern design does not have such large space, either 37

Comparison with RDR RDR design 38

Comparison with RDR Cavern cross section for excavation 39 RDR New m m 2

Comparison with RDR Cost consideration for experimental cavern 40 RDRNewDifference Main cavernEgg shapeBullet shape Nominal size (m)120(L)x39(H)x25/36(W)142(L)x42(H)x25(W) Excavation cross section (m 2 ) Excavation volume (m 3 ) Alcoves(ILD/SiD) Size (m)40(L)x15(H)x15/18(W)12.5(L)x19.6/18(H)x20(W) Quantity12/2 Excavation cross section (m 2 )211361/329 Excavation volume (m 3 ) / Cavern total Excavation volume (m 3 ) Cost (Oku-Yen)~+x

Comparison with RDR Cost consideration for access shaft/tunnel and utility cavern 41 RDRNewDifference Access routeVertical shaftsHorizontal tunnel Size (m)  16x100(L) 1000(L)x11(H)x11(W) + branches Quantity2 1+  Total cost (Oku-yen)~xy*zz**-17 Utility cavern Size (m)--77.5(L)x13.5(H)x15(W) Cost (Oku-yen)--z**(+z***) * RDR estimation x 117yen/ILCU ** Estimation by J-Power *** Utility cavern is mainly used for accelerator utilities

US design 42

Summary The 142m option of the cavern in Japanese mountain site looks OK for detector installation of ILD without extending the original schedule (8 years from ground breaking to physics run) GDE should clarify the timeline for accelerator construction and commissioning, if there is some change from RDR –when the beamline area in the cavern should be cleared –when the detector can be rolled in Rough design of cryogenic system should be decided in this meeting Cost of the new design of experimental hall would be less than that of RDR 43