1 Local Area Planning Update to TRANSAC – September 18, 2014.

Slides:



Advertisements
Similar presentations
Summary of Second Draft of the NERC Standard PRC Disturbance Monitoring and Reporting JSIS Meeting August 10, 2010 Salt Lake City, UT.
Advertisements

NERC TPL Standard Issues TSS Meeting #146 Seattle, WA August 15-17, 2007 Chifong Thomas.
NERC Footnote b / 12 – Load Loss
Industry Brainstorm on increasing Export Capacity From Alberta to B.C. January, 2006.
Power Grid Reinforcement Fall Presentation Team 9b: – Jon Brown – Kyle Reininger – Alan Myers – Karl Homburg – Dan Sinnott.
Company LOGO Cleco Planning Process. Models Cleco uses SPP’s annual series of models to determine the NERC reliability violations. Cleco uses SPP or VST.
Goshen Area Bus Reconfiguration
La Crosse 161 kV Capacitor Addition Northern MAPP Subregional Planning Group April 3, 2007 Daniel Kline.
NERC Lessons Learned Summary December NERC lessons learned published in December 2014 Three NERC lessons learned (LL) were published in December.
1 Local Area Planning Update to TRANSAC – December 16, 2014.
Cleco Transmission Planning Summit 2011 Coughlin Transmission Operations Center April 15, :00 – 11:00am.
Tucson Area Reliability Mike Flores Control Area Operations Tucson Electric Power May 2000.
1 1 Substation Asset Strategy Kevin Dasso, Senior Director Engineering and Operations IEEE/PES Annual Substations Committee Meeting April 7, 2008.
MARCH 31, 2014 Maine 2014 Outage Coordination CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE.
1. 11/26/2012: NERC Board of Trustees adopted CIP v5 CIP thru CIP CIP and CIP Version 5 Filing FERC requested filing by 3/31/2013.
System Voltage Planning Brian Moss PD / Transmission Planning Transmission Planning Overview October 30, 2007.
NOVEMBER 11, 2014 PUBLIC VERSION Maine 2014 Outage Coordination CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE.
ColumbiaGrid Planning Update to PCC Marv Landauer October 7, 2014.
Borah Mitigators Remedial Action Scheme for the Borah West Path Sponsored by: IDAHO POWER Team Members: Kyle Jones Mark Magee Jason Rippee.
1 Local Area Planning Update to TRANSAC – July 29, 2015 Mitigation Update, Uncertainty Scenarios, and Next Steps.
© 2000 PACIFICORP | PAGE 1 WYOMING WEST AREA STUDY DECEMBER 2013 Seongtae Kim/Jeremy Viula.
1 Green River Utah Area Transmission and Distribution System – January 16, 2009.
RTP Update RPG Meeting July 21, RTP update  Reliability analysis for the contingencies where load shed is not allowed is complete.
Entergy Transmission Planning Summit New Orleans, LA July 8, 2004
FRCC Seasonal Transmission Assessment & Operational Seasonal Study Winter 2012.
NW Transmission System Bottlenecks and Impacts of 2005 Summer Operation BPA Transmission Business Line Mike Viles January 2006.
1 Entergy Mississippi, Inc. Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 8, 2004.
ERCOT SOL Methodology for the Planning and Operations Horizons Stephen Solis 2014 OTS 1.
Recommendations from 2011 Southwest Outage Heather Polzin, FERC Office of Enforcement Dave Nevius, Senior Vice President, NERC Member Representatives Committee.
Applying the Distribution System in Grid Restoration/NERC CIP-014 Risk Assessment Srijib Mukherjee, Ph.D., P.E. UC Synergetic.
Rocky Mountain Power Sub Transmission Five Year Study Findings and Kick Off Attachment K Meeting September 10, 2015.
2006 Reliability Study Scope Name Date. DRAFT 2 Purpose of Study Assess the PEC and Duke transmission systems’ reliability Develop a single reliability.
Long Term Study Task Force Update Transmission Study Practices and Methodologies April 5th,2011 LTS.
December 7, 2012 ERCOT Planning Horizon SOL Methodology Update Jeff Billo RPG.
1 Local Area Planning Update to TRANSAC – March 11, 2015.
Electric Transmission Planning Local Area Planning Update Presentation to TRANSAC January 24, 2013.
1 Local Area Planning Update to TRANSAC – Sept 16, 2015 Mitigation Update, Uncertainty Scenarios, VAR Margin Study.
ERCOT PUBLIC 4/21/ RTP: Cascade Analysis April 21, 2015.
Local Area Study Local Area Study Mitigation Plan Update and Uncertainty Scenarios
1 Stability Issues in Entergy System Entergy Transmission Planning Summit New Orleans, LA July 10, 2003.
Current Export Initiatives Jerry Mossing Exports Workshop February, 16,2006, Metropolitan Center, Calgary.
Big Stone II – Delivery Study Phase 6 and Supplemental #2 For Northern MAPP SPG Meeting 4/3/07 Elk River Richard Dahl Missouri River Energy Services.
Operating Guide and Planning Guide Revision Requests Blake Williams, ROS Chair September 13, 2012.
TRANSMISSION CONSTRAINTS KENNETH A. DONOHOO, P.E. Manager of System Planning, Technical Operations
Transmission Capital Project Updates. Transmission Expansion Plan Sigurd to Red Butte 345 kV line in-service May, 2015 Permitting activities continue.
Current Operational Challenges Computing the West – North Limits Potential IROLs Local Voltage & Thermal issue (OOME) High Voltage Outages.
WECC-0100 Scope, Content & Status Update Rikin Shah, PAC Orlando Ciniglio, IPC WECC TSS Meeting, Salt Lake City, UT January ,
OPSTF – Issue 7 Long-term unavailability of autotransformers.
1 Entergy Mississippi, Inc. Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 10, 2003.
2006 Reliability Study James Manning Bryan Guy May 12, 2006.
1 Entergy Arkansas, Inc. Proposed Transmission Projects Entergy Transmission Planning Summit New Orleans, LA July 29, 2008.
1 Entergy Arkansas, Inc. Proposed Transmission Projects Entergy Transmission Planning Summit New Orleans, LA July 31, 2007.
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N 1 5/09/2011 West of Cascades – North (WOCN) Path BPA Studies Path Definition (for studies) 
Local Area Planning Update – TRANSAC Base Case Status Base case study models representing the base scenarios will be completed as follows for.
Freeport Area Master Plan Project -
Barrilla Junction Area Transmission Improvements Project
Local Area Planning Update to TRANSAC – December 21, 2016
Local Area Planning Update to TRANSAC – September 15, 2016
Local Area Planning Update to TRANSAC – June 29, 2017
Local Area Planning Update to TRANSAC – March 15, 2017
Local Area Planning Update – TRANSAC
DEC System Voltage Planning - June 2018
Naughton RAS (Southwest Wyoming Generation Tripping Scheme) – LAPS
Local Area Planning Update to TRANSAC – September 26, 2018
Review of Distribution Network Protection
Naughton RAS (Southwest Wyoming Generation Tripping Scheme) – LAPS
TONBRIDGE POWER GREEN LINE
Palo Verde-COI RAS Retirement
Palo Verde-COI RAS Retirement
Presentation transcript:

1 Local Area Planning Update to TRANSAC – September 18, 2014

2 Base case study models representing the base scenarios have been completed for all four seasons: –Heavy Summer (HS) –Heavy Winter (HW) –Light Autumn (LA) –Light Spring (LSP) for the present (2014/15). Future cases over the 15 year planning horizon…2019, 2024, and 2029, for 16 total cases, will be completed shortly. Base Case Status

3 Existing system configuration has been modeled in 2014 HS and LA, HW cases and a 2015 LSP case; completed projects and other projects under construction, as well as budgeted and approved system improvements are included in 2014 and later cases. All cases were based on a 1-in-10 load forecast. Base Case Status

System normal (N-0), single segment or element outage (N-1), and selected credible double segment or element outage (N-2) contingency files have been developed/updated to facilitate simulation runs of the same system conditions through each base case. Outages include: –Lines –Transformers –Buses –Plants (Generation) Contingencies to Study 4

System normal and outage conditions were modeled and studied for adequacy and system security. Segment or element thermal loads >85% were noted under these conditions; loads above 100% were noted as overloads (in winter, lines and transformers were allowed up to 125% continuous load). –Overloaded segments will be tripped per standard relaying practice ( % thermal on lines 1, 125% minimum thermal on transformers) to check for ‘cascading’ outages except as noted below: o 230 kV lines are not tripped below 150% thermal per requirements of NERC PRC-023. o May apply to path lines or other system lines and elements deemed critical. 1 Thermal relay settings on lines will be reset to permit 125% thermal load per new Business Practice. Study Criteria 5

Voltages outside of NWE planning criteria were noted – 90% to 95% low voltage limit depending on line voltage and system conditions (N-0, N-1, or N-2); 105% high voltage limit – per NWE FERC Form 715 criteria. –Load-serving bus voltages may fall above or below these limits if conditions allow a higher/lower voltage without harm to NWE or customer equipment. –Certain equipment ratings may dictate different limits. Existing OMS or RAS schemes were considered. Study Criteria 6

System Normal and Outage runs have been completed on all seasons of the 2014 and 2015 base cases to determine the present “state of the system” as it exists today. N-0, N-1, and N-2 study results have been analyzed for the 2014 and 2015 models. Study results show several previously known issues are now resolved, and little to no new problems have been observed in the current studies. State of the System Studies 7

Summary Results and Findings for 2014 Cases: Heavy summer conditions govern for voltage and thermal conditions on most normal and outage scenarios. Heavy winter governs in some other conditions; some high voltage problems are observed under light load conditions. Almost all higher voltage bulk system segments and elements meet criteria under all operating conditions and scenarios (500, 230, and 161 kV). –Loss of such elements may increase load on underlying system such as auto transformers and lower voltage lines, or produce low voltage problems. State of the System Studies 8

Summary Results and Findings for 2014 Cases: Most problems are observed on lower voltage system segments or elements (50 and 69 kV)…older, smaller conductor or transformers, or auto transformer ties to lower voltage systems. Low voltage problems remain in some areas under outage conditions with some minor problems becoming worse. –Dillon – Sheridan 69 kV system –Lewistown Area 50 kV system –Columbus/Stillwater Area 100 & 50 kV system –Big Timber Area 50 kV system State of the System Studies 9

Summary Results for 2014 Cases: N-0 Thermal Issues No system elements illustrate thermal overload under system normal (N-0) conditions. State of the System Studies 10

Summary Results for 2014 Cases: N-1 Thermal Issues Several system elements can become thermally overloaded under N-1 conditions during heavy loading: –Loss of the Clyde Park 161/50 kV auto transformer overloads the Melville – Big Timber 50 kV line and Big Timber Auto. –Loss of the Ennis – Lone Mountain 69 kV line overloads the Jack Rabbit 50/69 kV auto transformer. Mitigation is in progress. –Loss of 100 kV facilities in the Columbus area may cause additional element overloads, low voltages, and cascading outages on the 50 kV system in the Columbus and Stillwater areas. Mitigation is in process. State of the System Studies 11

Summary Results for 2014 Cases: N-1 Thermal Issues Several system elements can become heavily loaded under N-1 conditions: –Loss of the Dillon – Ennis 161 kV line overloads the Dillon-Salmon 161/69 kV auto transformers. Mitigation is currently underway. –Loss of the Hardin Auto auto transformer overloads the Hardin – Colstrip 115 kV line due to a current limited device. Mitigation is planned. State of the System Studies 12

Summary Results for 2014 Cases: N-1 Thermal Issues Several substations have two auto transformers operated in parallel (in-service, side-by-side). In some cases, loss of one transformer will cause the sister unit to overload. –Loss of one of the Dillon-Salmon 161/69 kV auto transformers causes the other auto transformer to overload. Mitigation is currently underway. –Loss of the Assiniboine 161/69 kV auto transformer or Rainbow 100/69 kV auto transformer heavily loads its sister unit under heavy loading conditions (the Rainbow auto issue is currently being mitigated by the Crooked Falls project). In many of these N-1 cases, problems had been discovered previously, and mitigation plans are already in process. State of the System Studies 13

Summary Results for 2014 Cases: N-2 Thermal Issues A loss of the East Gallatin 161 kV bus puts Bozeman at risk and could result in significant loss of the Bozeman 50 kV system due to another transformer overload, and resulting in cascading outages. Mitigation is planned. The Colstrip – Sarpy Auto 115 kV line can overload for certain double contingency outages. The line rating is now limited by in-line wave traps; planned communications upgrades mitigates the problem. Mitigation is planned. Loss of the Ennis Auto 161 kV bus can create voltage and thermal problems in the Big Sky area. Mitigation is underway. State of the System Studies 14

Summary Results for 2014 Cases: N-2 Thermal Issues Loss of the Missoula 4 – Hamilton Heights 161 kV ‘A’ and ‘B’ transmission lines (common corridor) could cause segments of the Missoula 4 – Hamilton 69 kV ‘A’ and ‘B’ lines to overload. Mitigation is planned. Loss of the Harlowton or Glengarry 100 kV buses results in low voltage in the local 50 kV systems. Loss of the Mill Creek 100 kV Bus could overload the Anaconda and Drummond 100/50 kV auto transformers. Mitigation is already planned (convert the Anaconda – Drummond 50 kV line to 100 kV). State of the System Studies 15

Summary Results for 2014 Cases: N-0 Voltage Issues Under normal system operating conditions, minor high voltage under light loading conditions is observed on the: –Bridger area 50 kV system. –Bozeman/Livingston area 50 kV system. –Hi-Line 69 kV system. –The study results are being verified; transformer tap changes or capacitor bank setting changes may correct the problem. No voltage problems are present on the NWE BES for normal operating conditions. State of the System Studies 16

Summary Results for 2014 Cases: N-1 Voltage Issues Low Voltage is produced under N-1 conditions during heavy loading in the following events: –Loss of the Columbus-Rapelje – Alkali Creek 161kV line produces low voltage in the Columbus-Chrome area 100 & 50 kV systems under heavy summer conditions. Mitigation is planned. –Loss of the Lower Duck Creek – Columbus-Rapelje 161 kV line produces low voltage in the Big Timber/Melville area 50 kV system during HS conditions. Mitigation is planned. –Loss of the Dillon-Ennis 161 kV line produces low voltage in the Dillon-Sheridan area 69 kV system during HS conditions. Mitigation is planned. State of the System Studies 17

Summary Results for 2014 Cases: N-1 Voltage Issues Loss of other auto transformers around the system may produce low voltage problems. High voltage links to low voltage systems are more critical today. –Loss of the Sheridan Auto 161/69 kV auto transformer results in low voltage in the Dillon area 69 kV system. Mitigation is planned. –Loss of the Glengarry 100/50 kV auto transformer results in low voltage in the area 50 kV system. –Loss of the Clyde Park 161/50 kV auto transformer or a bus fault, will result in widespread low voltage across the area 50 kV system under HS or HW conditions. A spare transformer is on-site; mitigation is planned. State of the System Studies 18

Summary Results for 2014 Cases: N-1 Voltage Issues The Anaconda Mill Creek 161 kV bus outage presents low voltage, overloads and widespread outage risks to the Butte/Helena/Bozeman areas. Mitigation is near completion. No low voltage problems are present for LA or LSP conditions. Summary Results for 2014 Cases: N-2 Voltage Issues Most buses met N-2 voltage criteria. N-2 thermal issues often include voltage issues as well that are corrected with the mitigation of the thermal issue. State of the System Studies 19

Summary Results for 2014 Cases: Stability Problems Stability (dynamics) runs have not yet been performed on the 2014 base cases, or any others. These runs should be completed later this year. No major problems are anticipated. State of the System Studies 20

Analysis of 2014/2015 cases for N-0, N-1, and N-2 conditions is complete. Complete the analysis of 2019, 2024, and the 2029 cases. –Verification of new problems Prioritize problems using Decision Rules. Begin or continue Mitigation Studies. Additional progress and next steps 21

Questions? 22

23