FINAL PROJECT CVE 4073 – Construction Cost Engr. Prof. Locurcio 12/04/2014
Group Members Aline Franqui Bianca Farias Gabriel Silva (PM) Gilberto Pierozan Julian Miyamoto Junior Badziak Lara Barroso
Outline Introduction Technical approach Tasks Responsabilities Bid Breakdown by major components Bid Summary
Introduction Since the past to our current age, mankind have always tried to let a legacy behind. In construction, we can make this wish last for ages. But nothing of it would have happened if there were no planning or management skills. In this project we could taste how the real world is, and how to be prepared to challenges to come.
Technical Approach We divided the work by lottery! As PM I assumed that since everyone have done all the homeworks, nobody would have problem. We’ve scheduled meetings twice a month So, as a group, we could see the progress of our work. After all the work was done, we revised the work from our collegues, to make sure it was correct
Task Responsabilities
Concrete
l Footing l Slab
l Footing
Footing
l Footing l Slab
Slab and Final Cost
#5 Rebars
Wood & Plastic
Dimensions of the elements used for Wood & Plastic and Thermal & Moisture
Studs
Headers
Blocking / OSB - CDX Total price for Wood & Plastic = $7,084.90
Thermal & Moisture
Total price for Thermal & Moisture = $1,570.34
Plumbing
VTR – vent tub riser LAV – lavatory WC – water closet TUB – tub shower CO – cleanout adapter KIT SK – kitchen sink
Plumbing 8’ 11.5’ 10.5’ 11.5’ 5’ 8’
Plumbing Hot water line: pass through tubs, lavatories and kitchen. Cold water line: pass through tubs, lavatories, water closets and kitchen. For tubs and wc: 1” pipe For lavatories and kitchen: ½” pipe
Roof
Roof main dimensions Calculate the area on the plane, and then use the following to have the inclined area: (1+slope 2 ) 0.5
Roof Materials
Roof Calculation
HVAC
Electrical
Electrical Wiring and Fixtures Take-off
Openings
Finishes
Finishes Calculation
Bid Summary
Summary Sheet Description Material cost Equip. Cost Labor cost Total Cost Earthwork $3, $4, $3, $12, Concrete (Foundation) $6, $14.18 $2, $8, Wood, plastics and composites $2, $ $2, $5, Openings $2, $- $ $2, Plumbing and fixtures $ $- $1, $1, Roof (with truss package on total cost) $5, $- $3, $11, HVAC System $4, $- $ $5, Electrical $6, $- $8, $15, Fire Suppression $52.00 $- $29.00 $81.00 Thermal, moistures protection $ $- $ $1, Finishes $11, $8, $19, Specialties $2, Documentation $2, Labor Taxes (25%) $8, Sales Taxes (6%) $2, Subtotal $98, O&P (10%) $9, TOTAL COST $108,044.32
Questions?