Pelletron Battle – Field Report All Experimenters’ Meeting August 15, 2011 L. Prost (for A. Shemyakin)

Slides:



Advertisements
Similar presentations
SNAP CIRCUITS TEACHER MANUAL
Advertisements

Inspection & Preventive maintenance of breakers
Focus Coil Update Roy Preece / Tom Bradshaw / Mike Courthold STFC – RAL VC 17 th Jan 2013.
Simple Pressure Control Valves
Proton Source Workshop Booster Downtime Wednesday, December 8, 2010 T. Sullivan.
"AIR COOLER" Heat Exchanger
The First Law of Thermodynamics
1 WP 10- High Voltage ’06 March 23 rd HV Trip studies  See previous meetings for the foreseen tests on LBC44  Started late by Clermont people when Clermont.
MICO 22 nd February 2010 Terry Hart (MOM) - Decay Solenoid and Target - MICE Machine Physics runs - User Run Plans.
XEC Hardware Status MEG Review Meeting 2010 Liquid Xenon Group.
MUID Status: General Detector Health In addition to two disabled HV chains there are four other chains (out of a total of 600) that are largely or totally.
¾-1/2” Red. Union 3/8”OD ACSM Inlet Configuration 0.1 lpm to ACSM with PM 1 passing thru aerodynamic lens 2.9 lpm to external Pump* Sheath Flow 6 lpm dry.
LAPPD status report. 6cm system status  System up and running since July –Temperature profile carefully mapped out in sealing and deposition chambers.
Hydronic Mechanical Controls
OZONE DRINKING WATER SYSTEM. CONTENTS Properties of Ozone Production of Ozone Water Treatment Plant – 25 m 3 /hr Ozone Generation System.
Hydraulics For The Long Term
Test of the high voltage strength of Pelletron’s gas insulation (18-Dec-2008) Recycler Meeting January 21, 2009 A. Shemyakin.
Proton Source Repairs Dan Bollinger 2/1/10. Cockcroft-Walton accelerators FNAL has 2 Cockcroft-Walton Pre-accelerators (Pre-acc) that provide beam to.
CURRENTS AND OHM’S LAW. What?  Electricity – flow of electric current  Electric current – the movement of an electrical charge.  In most cases, we.
Simple Electric Circuits
Domina PLUS B WORKING DIAGRAMS TROUBLESHOOTING INTERNAL VIEWS WIRING DIAGRAMS INSTALLATION 03 PREVIOUS MODEL.
01/07/08I. Ravinovich1 HBD Update Ilia Ravinovich DC Meeting, January 9, 2008.
Placing Vapor Distribution Systems and Appliances into Operation MODULE 8 System Tests.
Electric Components. Basics 1 Current: electrons moving together in same direction (electrons are always moving in materials like metals but in a random.
Experiment 9. Liquid-Vapor Equilibrium in a Binary System The vacuum manifold used in this experiment is shown here. The main stopcock isolates the system.
Ion Source Update. We now have 2 running sources Source B has been running since the first part of June Both sources have been modified extensively since.
August 05, Startup 2013 Machine Status:  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac Booster  Main Injector Startup.
Faculty of Physics, University of Belgrade General meeting 19 th of August, ToF-LR HV Upgrade Jovan Puzović, Faculty of Physics, Belgrade.
All Experimenters’ Meeting February 09, Accelerator Operation Summary Calendar Week # 06 NuMI Weekly Integrated Intensity 6.69 E18 protons Beam.
Stability of the electron energy Recycler department meeting April 5 th, 2006 A. Shemyakin, M. Sutherland.
Overview of Electron Cooling Activities at FNAL Thomas Kroc Fermilab – Electron Cooling EIC 2004 March 15-17, 2004 Jefferson Lab.
Electron energy stability: analysis from snapshot data and temperature stabilization Recycler Departmental Meeting May 21, 2008 A. Shemyakin 1.Analysis.
NuMI/MINOS Status All Exp. Mtg. June 2, 2008 Jim Hylen/FNAL Page 1 FAR DETECTOR: 98.0% live time (wall clock) There was a power outage on the morning of.
18 March 2002 All Experimenters’ Meeting Alan L. Stone Louisiana Tech University 1 DØ Status: 03/11 – 03/18 Week integrated luminosity –1.1 pb -1 delivered.
ABL-14d Able Elective Engines Instructors: George Crowl.
Target tests 1 st – 2 nd Nov. Chris Booth Sheffield 7 th December 2006.
Overview of the main events related to TS equipment during 2007 Definition Number and category of the events Events and measures taken for each machine.
Air Blast Circuit Breaker
2/17/2016 Recycler -Gattuso Recycler Shut Down Status  Flying Wire Status  Wire Vacuum Certified  Tunnel Bake Prep status Disconnection of BPM, Correctors,
PS/SPS Days Roberto Losito/Oliver Aberle 13th January 2004
19 January 2006 PS&SPS DAYS AD equipment tests and startup with beam Slide 1 AD and AD experimental areas: equipment tests and startup with beam Tommy.
NUMI MINOS MINOS Far Detector Installation & Commissioning Jeff Nelson MNHEP DoE Visit September, 2002.
Electron energy stability (observations after the HV regulation repairs) Recycler Meeting April 30, 2008 A. Shemyakin.
August 12, Machine Status: 2013  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac : Roof hatch installed Booster : Magnet.
To return to the chapter summary click Escape or close this document. glencoe.com Image Bank Foldables Video Clips and Animations Standardized Test Practice.
13 January 2005 PS&SPS DAYS How can we restart AD in 2006? Slide 1 How can we restart AD in 2006 ? Tommy Eriksson AB/OP/AD.
9 October 2003S. DeBarger PEP-II Vacuum Status PEP-II Machine Advisory Committee.
Recycler/Ecool Shutdown Planning Meeting (6/4/2010)
 Today's vehicles are much more complex and complicated than the cars of the 1960s, '70s, '80s, incorporating more computer electronics, silicon chips,
1 Top Level of CSC DCS UI 2nd PRIORITY ERRORS 3rd PRIORITY ERRORS LV Primary - MaratonsHV Primary 1 st PRIORITY ERRORS CSC_COOLING CSC_GAS CSC – Any Single.
BASIC AUTOMATIC CONTROLS UNIT 16 ADVANCED AUTOMATIC CONTROLS
5-year operation experience with the 1.8 K refrigeration units of the LHC cryogenic system G. Ferlin, CERN Technology department Presented at CEC 2015.
AIR CONDITIONING (COOLING)
Arnd Meyer (RWTH Aachen) Sep 8, 2003Page 1 Integrated Luminosity Total data sample on tape with complete detector > 200pb -1.
18/March/2008OP-days S.Mataguez / O.Hans1 Hardware Problems in the PS complex LINAC 2 BOOSTER PS AD Thanks to all that helped and provided information,
TROUBLESHOOTING ELECTRIC MOTORS
SF6 contamination by air in the Pelletron Recycler Departmental Meeting November 5, 2008 A. Shemyakin.
Pelletron status update Main Injector Departmental Meeting November 11 th, 2009 L. Prost.
GROUND SERVICING OF VARIOUS SUB SYSTEMS
University of Colorado – Boulder
Know Your Basic Car Care
02/08/ :35: Lost access chain in point 2 (PX24 PAD)  Dump after ~14.5 hours ~100 nb-1.
CHAPTER 45 Engine Lubrication.
How can we restart AD in 2006 ? Tommy Eriksson AB/OP/AD
Fri 29/7 – Sat 30/7 09:00 End of fill 1990, PC trip RCBXV3.R1 (likely SEU on QPS). Integrated Luminosity: 41 pb-1. Access for MKI2 main switch replacement.
Lithium lens and window tests
07/08/2010 Fill #1264 dump at 02:14:38.
0 Air Blast Circuit Breaker under the guidance of:- Presented By:- Mr. B.R.Reddy Anuj Kumar Pandey EN-3 rd year Roll No Unrestricted.
IOT operation in the SPS Long term experience TWC 800 MHz
Presentation transcript:

Pelletron Battle – Field Report All Experimenters’ Meeting August 15, 2011 L. Prost (for A. Shemyakin)

Terminology for the Pelletron HV regulation system (simplified) 2 Column current I Corona ≈ I Chain – I Column - I Needle Corona current Corona current ≡ Lost current

Chronology: onset of problems and 1 st access  July 29, 2011  Following a lightning strike, the entire beam line needed to be re-tuned for an unknown reason in order to pass the beam through. The Pelletron was left off (no pbars to cool).  Aug 1, 2011  Turning Ecool on in attempt to understand what went wrong, we found that we can’t operate because of a high corona current from the terminal.  Aug 2, 2011  Staying with HV on and conditioning did not help. Started tank opening.  Aug 3-4 access  Nothing special is found. Regular maintenance after 6-month operation (without opening) Included replacement of a water pump drive pulley  Because ~1 liter of water had to be added to the collector water system, the desiccant column (which removes water vapor from SF 6 ) was re-generated  At startup:  Very bad lost current 3

Chronology: 2 nd access  Aug 5  Second regeneration of desiccant (tank filled with SF 6 )  Noticeable improvement, but still below operational voltage  Needles stopped moving, triggering the second access  Aug 6-8 access  Needle motion problem disappeared in air Reset relevant connectors  Water pulley was found to be heavily damaged; plastic and aluminum chips everywhere A temporary spare was installed  Needles and the triode (part of a HV regulation system in the terminal) were replaced by new ones 4  At startup:  Very difficult conditioning  The new triode did not work at high current  Electronics at one of Pelletron levels stopped working, forcing an access (3 rd )  Intermittent readings of the column resistive divider

Chronology: 3 rd access  Aug 9-10 access  Electronics and the triode were replaced; divider contacts tightened; installed a permanent pulley  Made a HV test in air: very high lost current  Removed non-conductive residue from the tank walls  Second HV test in air: noticeable improvement  Startup (Aug 11)  Conditioning is better than any of previous times  A BPM in the tank stopped working Significantly complicated commissioning  Established cooling HV is less stable than usual; higher corona current; a full discharge  Addressing the issues  Activated Titanium Sublimation pumps near the Pelletron  Conditioned two top sections  Took SF 6 sample for analysis 5

SF 6 gas quality  All indicates that quality of SF 6 has significantly deteriorated  Partly compensated by regeneration of the desiccant and by cleaning the tank walls  Were not able to find any precedents 6 Vacuum limit Operating Voltage HV limitations at various gas pressure in the Pelletron tank. Blue line indicates maximum observed voltage at the given pressure. Brown dashed line is a rough extrapolation from the point with a full discharge based on the data for pure SF Dec-2008 Now, difficulties to maintain operational voltage with nominal tank pressure

Summary/Status  The long downtime was caused by a combination of several unrelated failures  Thanks to everybody involved  Present status  Ecool is operational to some extend Trips ~ once every 10 min ⇒ Getting better with time Requires cycling of HV (after a full discharge)~ once a shift  Will work with MCR to optimize performance in this state  Added SF 6 (~5%) to increase HV strength (proportional to pressure) More conditioning is taking place… right now! 7