DELIVERY PROGRAMME Ian Hardwick Head of Engineering - Gallagher 28th January 2015
Contents Where Are We At Phasing Summary
Where are we at? Reserved Matter Approval Technical approvals / Legal Agreements Ecology Issues addressed Archaeology underway Contactor Appointed
Phasing Anticipated Start Feb/March 2015 Infrastructure Delivery over 5 years Timing respects delivery of Phase 2
Phasing 2015 B1050 First Phase of Primary Roads Secondary Road Access to Primary School Excavation of Water Park, attenuation pond and land raising Foul water pump station and rising main to Uttons Drove Primary School Gateway Open Space
Phasing 2016 Hattons Road Ponds and Completion of Land Raising Strategic Landscaping to waterpark and Greenway A
Phasing 2017 Primary Road to Phase 2 Boundary – access to secondary school Laying out of Sports Pitches
Phasing 2018 Primary Road to Phase 2 Boundary – Western Link Strategic landscape to Greenway B Dedicated Busway to Phase 2 Boundary
Phasing 2019 Completion of Primary Roads
Phasing Plans
2015
2016
2017
2018
2019
2020
Phasing / Next Steps Secure Final Technical Approvals Legal Agreements in place Construction and Environmental Management Plans approved
Phasing / Next Steps B1050 & first phase of Primary Roads – Feb/March 2015 On-Site Attenuation – Phase 1a Earthworks – June 2015 Hattons Road Ponds – Phase 1b Earthworks –March 2016 Next Phase of Primary Road –2017/18
Conclusion Culmination of many years work. Significant major infrastructure project. Extensive consultation and approval process.