Barrel Maintenance Scenario for LS1 MUON-IB CMS week 11 December 2012 A. Benvenuti (INFN Bologna)

Slides:



Advertisements
Similar presentations
Davide Piccolo INFN Napoli Muon Annul Review Cern 15 September 2003 Chamber Production QA/QC MUON ANNUAL REVIEW On RESISTIVE PLATE CHMABERS CERN, 15 September.
Advertisements

Winter shutdown 08/09 Summary of HV interventions Barrel Muon Workshop, 02/09 Jesús Puerta-Pelayo, CIEMAT 17-February-2009.
Year End Technical Stop DT work Mu Barrel Workshop 13 October 2011 A. Benvenuti (INFN Bologna)
Il sistema di HV del sottorivelatore DT S. Braibant, P. Giacomelli, M. Giunta, E. Borsato Bologna, 20/01/2007.
M.PEGORARO Grounding Workshop 24th Jan 08 DT GROUNDING & SHIELDING Presented by A. BENVENUTI.
1 Installation of Delphi Frame  ITS Installation.
Saverio MINUTOLITIG meeting, 10 February Report on T1 installation activities and achievements made during this shutdown.
Experimental Area Meeting V. Bobillier1 Good connection to earth (in many points) of every metallic parts to be installed in the cavern is very.
Experimental hall in Japanese mountain site Y. Sugimoto ILD MDI/Integration 1.
ISR Work Progress Report Muon Week April 10 th 2003 A. Benvenuti INFN Bologna.
Upgrade news and Proposed interventions during YETS for the Muon Barrel Alignment Szillási Zoltán, Béni Noémi (ATOMKI ) This project is supported by Hungarian.
The MINER A Operations Report All Experimenters Meeting Howard Budd, University of Rochester July 8, 2013.
Experimental hall in Japanese mountain site Y. Sugimoto 1.
Endcap Integration Workshop: June 11-14, CSC Commissioning Andrey Korytov.
V. Bobillier1 Long distance cable installation status Calorimeter commissioning meeting.
1 5 December 2012 Laurent Roy Infrastructure / Electronics Upgrade -Cabling (long distance) -Rack and Crate (space, electrical distribution, cooling) -Detector.
1 Discussion for basic options — engineering video conference July 12, 2006 Outline Water pool — advantages — issues, problems, engineering options Aquarium.
Fabio Montecassiano INFN PD & CERN PH/CMM1 Status of cabling on YB Fabio Montecassiano INFN PH/CMM.
Installation and Commissioning Planning Leslie Camilleri Calorimeter Commissioning Meeting 5 th September 2006.
Tariq J. Solaija, NCP Forward RPC EDR, Tariq Solaija Forward RPC EDR The Standard RPC for low  regions Tariq J. Solaija National Centre for.
09/03/2010 ADO-PO section meeting Beam Pipe Extraction/Insertion R. Vuillermet.
Installation Review March ‘03 TPC Thomas C. Meyer/EP-AIT 1 Pre-installation and Functional Tests StartFinish  Certification of field cage…………………
r1Fabio Montecassiano INFN PD & CERN PH/CMM1 Status of cabling YB+2 and YB+1, extension to minus wheels and YB0, cables between UXC55 and USC55.
STATUS OF HO Sudhakar Katta TIFR, Mumbai India-CMS meeting, Delhi 27 th Sept 2007.
Technical Support Activities in PH-ADO-PO
C. F. Bedoya. C. F. Bedoya May 13th, * The goal was to establish a baseline plan for DT in Phase 2, (although some aspects of phase 1 also needed.
1 DT critical items status: HVBoards Control and Trigger Boards Assembly in Torino fgasparini june 2004.
Test beam setup: status report 31/03/2009 M. Alfonsi (CERN)
Run 12: STAR Status and Schedule Update RHIC Coordination Meeting October 18, 2011 Bill Christie BNL Outline Status update Schedule update and issues Summary.
All CMS 30 May07 TSV1 All CMS 3 30 May 2007 LHC machine CMS Progress Overall Schedule.
TAS at IP5 Present situation and plans François BUTIN TS/LEA.
From Bare Chambers to Installable Chambers Muon Barrel Week Bologna April 11 th 2003 Alberto Benvenuti INFN Bologna.
Activities related to Experiments during TS3 and YETS th November, 2015 M. Bernardini, M. Barberan With the support of S. Chemli and Experiments.
Muon Tracking Meeting SOR issue First priority Diagnostic: MCH DetectorScriptError Arriving at the initialization stage: the whole or part.
RICH1 Gas Enclosure Installation. Experimental Area Meeting at CERN on 21st June 2006 Bill Cameron (Imperial College London) on behalf of the RICH1 team.
DT Shifter Training Infrastructure A. Benvenuti, M.Giunta 07/07/2010.
18 June 20031Integration Review B. Schmidt Outline: Overview of the support structures Requirements –Some details on electronics, cabling and piping Constraints.
G.Barber Mice Tracker Integration Harbin Jan Mice Tracker Integration Installation requirements & Procedure.
SLHC Engineering Upgrade FCAL Remove-Install step by step procedure. Mircea Cadabeschi-University of Toronto March 01,
TC Straw man for ATLAS ID for SLHC This layout is a result of the discussions in the GENOA ID upgrade workshop. Aim is to evolve this to include list of.
CMS consolidation activities of detector cooling system Detector cooling project P. Tropea.
February 14, Comprehensive Review B. Schmidt Outline: Status and overview of activities: –Platforms and staircases –Muon Filters and beam plugs.
Michel RAYMOND – July 1 st, 2013 Technical Support Activities in PH-ADO-PO Summary of 2013 activities.
Tracker 1. Status 2. Expected delivery date of system to RAL 3. Required support infrastructure needed for setup and initial debug. Things like vacuum,
RRB scrutiny Report: Muons. Internal scrutiny group for RRB report Internal scrutiny group composition – J. Shank, G. Mikenberg, F. Taylor, H. Kroha,
Tracker Goals o Main issue is to be able to run cold as more radiation is accumulated. o Due to “uncontrolled” humidity behavior, our present limit is.
M1 Central Part Cable Routing R3 FAR R2 CLOSE R2 FAR + GEM A3 B From chain GEM R2 CLOSE R2 FAR A1 20 A1 A1 A2 A CHAIN Access Front Dané.
Additional muon stations for the Upgrade of the Elevator Regions in the ATLAS Muon Spectrometer. Installation scenario, status on the installation tools.
Trigger efficicency on double tracks Trigger efficiency on isolated tracks Final results of the Trigger Test on the 25ns beam Bx NUMBER Fraction of Triggers.
DT UPGRADE STRATEGY M.Dallavalle for the DT Collaboration 6/26/12 Muon IB1.
TOF status and LS1 plansTOF status and LS1 plans 27/06/2012.
1 hcal installation and commissioning status pawel de barbaro, vitali smirnov, june 11, 2007.
February 26 th 2013Muon LS1 operation meeting1 Muon LS1 Status Outline Recap of last week P1 weekly schedule Muon related activities Open issues and discussions.
1 Drift Tubes TC activities up to LS2 1.Implement remaining Phase 1 upgrades :  in USC ⁻ TwinMux ⁻ microROS 2.Refurbish HV & LV Power Supply Systems ⁻
Atlas status report. LHC Cooldown Status LHC is proceeding with the cooldown and the hardware commissioning L.Evans is asking the experiments to close.
Arnd Meyer (RWTH Aachen) Sep 8, 2003Page 1 Integrated Luminosity Total data sample on tape with complete detector > 200pb -1.
Kitakami Side AHCAL Assembly or anywhere in any detector.
Technical Coordination Parallel Session November 2011, FNAL
09/02/2006 Muon week HV and LV systems status for Magnet Test S. Braibant, P. Giacomelli, M. Giunta.
Pre-installation and Functional Tests
CMS Area Working Group Meeting
LHC Experimental Vacuum Systems Status October ‘07
CMS November Upgrade Week
Update of experimental hall in Japanese mountain site
LumiCal mechanical design, integration with LDC and laser alignment
DT Infrastructure: LV, HV, Gas
Initial BIS installation
BaBar IFR Upgrade Mark Convery SLAC 7 Jun 06.
Installation plans from mid 2005
Limited Streamer Tube Project Summary
Presentation transcript:

Barrel Maintenance Scenario for LS1 MUON-IB CMS week 11 December 2012 A. Benvenuti (INFN Bologna)

LS1 Barrel Schedule 26-nov-12  In spite of long shutdown, access to inner wheels, YB0 YB±1 is rather short  Main challenge is the large number of activities with conflicting requirements especially in YB0

DT Upgrade: TRB replacement in Theta SuperLayers Outline of LS1 Activities Plan has evolved on the basis of: Difficulty of intervention in YB0 Accessibility considerations for repairs Better estimate of the TRBs mortality rate  New TRBs will be installed only in MB1 (and MB2) of YB±2  “Easy” operation in the absence of the Beam Pipe

 12 OF trunk cables UX-USC are required for each wheel Central cabling team of 4-5 people required for 3 days each wheel  Increased granularity of SC power distribution in UX racks requires re- arranging LVDS cables from MC 2 persons from central cabling teams needed for 2 days each rack Final crate cabling done by DT personnel  Rearrangement of USC racks S1D08-S1D07 and S1D15 to S1D13 for Trigger and Readout Crates  SC Relocation can be done only after completion of ordinary maintenance and TRB replacement in a given Wheel DT Upgrade: Sector Collector Relocation

Ordinary Maintenance: RPC: Electronics replacement: FEB, LV DB (13 Chambers Gas leak search HV connectors replacement DT: HV problems (14 chambers) MiniCrates repairs (~39 ) Alignment: MAB maintenance, upgrade Preventive maintenance: leak detection cables, outer MB4s shielding, gas leaks, check flexible pipes, quick connectors on thermal shields, additional Hall probes, … Interleaved with:  HO refurbishment in YB0, YB±1 and YB±2  Strips, Pixel, HB cables on YB0 and access inside Solenoid Outline of LS1 Activities Typically, 6 days/wheel

DT HV Phi DT HV Theta RPC Extract Problems in DT or RPC MC Repair No access to YB0, YB±1 since February 2009 YB±2 MC maintenance in YETS 2009 DT HV problems: 2 chambers lowered to the floor, 4 extracted, 8 in place Fixed from IP side “easy” Uncabling, extraction on YB Usually only moving cables

days (24 if EB cables are already removed) The schedule is very tight for standard maintenance: gas leaks, HV connectors, ….. Some contingency can be achieved during Tracker YB0± access from: 1)Removing EB LV cables 2) HO SiPm replacement trial run on YB0+ S06,S07 DT HV Phi DT HV Theta RPC Extract MC Repair  Many activities in a very short time, S04 is the most complex sector Time estimates based on DT/RPC HO parallel work assume priority access to 2 SL (+1 small) and 1 CP Crane usage required for mounting/removing the chamber extractor (2hours/ 1 h) and for removing/installing 2 chambers in S04 (2hours/2h)

Cradle positioned as for MB1S04 but Large MB4 shown YB0 MB1S04 is easy to remove/install: Cradle is mounted above MB1 and is removed after MB1 is posed on support table Cradle insertion with ~1m extension rails requires 3m clearance in front of table times cradle size 4m  Cradle insertion footprint 6m x 4m  HV intervention+ test footprint 3m x 3m required for 2-3 days Crane needed to configure the cradle for MB4 and to rotate it upside down

MB4S04 Main difficulty in attaching cradle to YB0 Requires working under suspended weight (cradle) but secured to the iron. 3m x 4m floor footprint  HV repair with chamber on cradle  2-3 days required including testing + contingency MB4 S04 Removal (YB0-)

MB1S04 Two separate problems: 1)HV Board disconnected in SL1 L4 giving a loss of 16 channels (67 cm) 2)Front End Board in SL3 giving a loss of 4 channels in all layers HVBs and FEBs are inside the gas volume MB4S04 There is a short since 23/08/2009 in a strip channel of SL1 L4, most probably in the HVB. Enrico Borsato mitigated the problem at the level of the JunctionBox  It is important to understand what happened

Crane required for handling support pieces, 2 hours for mounting 1hour for dismounting Special extractor for RPC interventions can be mounted without the crane MB3 S08 Maintenance in December 2008

YB0- Workflow

/09/13 – 03/10/13 09/10/13 – 21/11/ HO RBX YB-1 must be aligned with VacTank to allow easy access to chambers Access scaffolding must be removed during S04(most problematic) and S10 work, 3m clearance between YB-1,YB-2 to pull MB2 S04 Crane usage required for mounting/removing the chamber extractor (2hours/1 hour) 2-3 SL required at all times to allow parallel work, YB-2 HO RBX are on IP side. YB-2 DT HV repairs done from IP side  YB-1 MABs survey before closing YB-2, 5m clearance required

The CHALLENGE

2 Bundles / side 1 bundle = 4 vacuum insulated pipes. One pipe split in 3 sections Check 3D models with mock-up 8 weeks manufacturing  Bottleneck for YB0-  Blocks work on YB-1 PIXEL CO 2 Cooling Pipes

Summary Main concern is the large assortment of different activities on YB0, hopefully the number and scope has finally stabilized. Last chance to fix DT/RPC problems on YB0 until LS2 or beyond (and it will not be any easier) Parallel work requires adequate resources, manpower and tooling. We cannot duplicate the crane but there should be enough scissor lifts and cherry pickers to go around. Interference between Barrel and EndCap Muon is primarily with crane access. But it is limited to few instances and mostly for short (~2 hours) periods. In the present schedule, DAQ1 and TTC availability severely affects YB+2 commissioning and SC relocation due to the late start of the Barrel activities.

Additional Material

TRB replacement and MiniCrate maintenance are the main activities VacTank access scaffolding prevents the efficient plan envisioned. It should be removed during the work on S03-S05 and S09-S11 2 SL required all time to allow parallel work for DT-RPC standard maintenance Crane usage required for mounting/removing the chamber extractor (2hours/1 hour) 2-3 SL required all time to allow parallel work, YB-2 HO RBX are on IP side /10/13 – 14/11/13

 Major concern is the impact of YETS13 and the availability of needed infrastructure: gas, cooling, power, DAQ..)  Few DT/RPC problems to be fixed but  S10 EB, TRACKER LV cable removal is laborious  Position of additional cable trays to be checked ASAP  DT HV problems in YB+1 must be fixed from IP side  VacTank access scaffolding should be replaced for YB+1 MB3S04 HV repair 18/11/13 – 14/01/14 16/01/14 – 11/02/ HO RBX

/02/14 – 19/03/14 16/01/14 – 11/02/ HO RBX YB+1 must be aligned with VacTank to allow easy access to chambers Access scaffolding must be removed during S04, S10 work, it is a barrier for SL displacement N-F 2-3 SL required at all time to allow parallel work, YB+2 HO RBX are on IP side. YB+2 DT HV repairs, MB4S04, MB4S12, done from IP side  YB+1 MABs survey before closing YB+2, requires 5m clearance

TRB replacement and MiniCrates maintenance are the main activities VacTank access scaffolding prevents the efficient plan envisioned. It should be removed during the work on S03-S05 and S09-S11 2 SL required all time to allow parallel work for DT-RPC standard maintenance Crane usage required for mounting/removing the chamber extractor (2hours/1 hour) /02/14 – 19/03/14

YB0- HO-DT-RPC Work Flow Remove MABs Remove vacuum tank Thermal Shields Remove “Removable services”  Disconnect/remove RPC/DT cables and services as needed  HO upgrade interleaved with DT/RPC maintenance: 2 days of HO Priority access to a bi-sector 2 days of parasitic access  DT maintenance on YB-1 (IP side) Lifting platforms (2-3 SL and 1 CP) should be available at all times to allow working on both sides of YB0 or on YB-1 Intermittent crane usage for chambers handling  Final tests (several days) after intrusive interventions are completed (DT-RPC preventive maintenance in parallel) Mount vacuum tank Thermal Shields interleaved with “Removable Services” installation Install MABs and test connectivity Survey MABs (5m clearance in front of YB0)  YB-1 can be moved on vacuum tank

Additional cable trays can be installed with CMS closed. Before interventions, remove: MABs, 1-2 VacTank TS ECAL LV cables, cable trays RPC DT cables as needed  In YETS08-09 YB0 was open on Z± => efficient conditions  Many activities in LS1: HO, DT, RPC, Tracker  Coexistence => inefficiency  But we all have to work  Careful, realistic planning mandatory for success

Opportunity for: Tuning HO SiPm procedures on YB0+ S6, S7 Removing DT/RPC cables where needed Fix MC problems  As scaffolding design allows