FACULTY OF ENGINEERING DEPARTMENT OF CIVIL ENGINEERING 2014-2015 SPRING SEMESTER ASSOC.PROF.DR. İBRAHİM YİTMEN CIVL 493 CONSTRUCTION MANAGEMENT.

Slides:



Advertisements
Similar presentations
MAINTENANCE PLANNING AND SCHEDULING
Advertisements

Project Management Techniques and tools Move mouse over arrow to enter presentation End Show.
WBS: Lowest level OBS: Lowest level
DISTRICT FIVE CONSTRUCTION CONTRACT ADMINISTRATION UPDATE TRAINING Submission of Working Schedule Specification SP A.
TIME MANAGEMENT 641 Topic 03 Activity Sequencing.
Work Breakdown Structures
CIVL202 Construction Engineering I Tutorial 8 T1Mon11:00 – 11:50 T2Wed09:00 – 09:50.
1 Lecture by Junaid Arshad Department of Engineering Management Abridged and adapted by A. M. Al-Araki, sept WBS: Lowest level OBS: Lowest level.
Scheduling The Project  Scheduling Planning, budgeting and scheduling are all part of the same process Planning a project, developing a budget for it,
Management & Development of Complex Projects Course Code - 706
Chapters 8, 9, and 10 Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out.
Copyright 2012 John Wiley & Sons, Inc. Chapter 8 Scheduling.
Project Time Management
1 B. SW Project planning & scheduling Recap from previous slide: It is important to decide on who is responsible for each activity. See Yeates & Cadle.
Engineering Design Development. Turner College and Career High School.
Types of Drawings University of Palestine Eng. Nagham Ali Hasan
Gantt Chart Engineering Design Development. Turner College and Career High School.
Chapter 6 Introduction to Microsoft Project
Copyright © 2009 T.L. Martin & Associates Inc. Chapter 3 Requirements of a realistic CPM schedule.
PLANNING ENGINEERING AND PROJECT MANAGEMENT By Lec. Junaid Arshad 1 Lecture#10 DEPARTMENT OF ENGINEERING MANAGEMENT.
5.1 Principles of Project Management. So what is Project Management? Definition: Is the process of planning, organizing, and managing tasks and resources.
CONTROLLING TIME. ”Remember that time is money” Benjamin Franklin 1748.
Chapter 6: Project Time Management
~ pertemuan 6 ~ Oleh: Ir. Abdul Hayat, MTI 03-Apr-2009 [Abdul Hayat, Project Time Management, Semester Genap 2008/2009] 1 PROJECT TIME MANAGEMENT.
Information Technology Project Management, Seventh Edition Note: See the text itself for full citations.
Cost and Time Control. Project completed on time and on budget –Want to get done early –Lower costs –More profit.
Time Planning and Con trol Time-Scaled Network. Processes of Time Planning and Control activities 1.Visualize and define the activities. Job Logic 2.Sequence.
1 L U N D S U N I V E R S I T E T P rojektledning och Projektmetodik.
Chapter 15 Construction Scheduling. Objectives After reading the chapter and reviewing the materials presented the students will be able to: Identify.
Project Time Con trol. Control = Monitor + Compare + Analysis + Action  Definition: Controlling  Controlling involves making sure that the results achieved.
Linear Scheduling Method Definition A simple diagram to show location and time at which a certain crew will be working on a given operation.
Geog 469 GIS Workshop Project Management.
Work Systems and the Methods, Measurement, and Management of Work by Mikell P. Groover, ISBN ©2007 Pearson Education, Inc., Upper Saddle.
ECCS5209 Project Planning & Control Faculty of Applied Engineering and Urban Planning Civil Engineering Department Lect. 1 2 nd Semester 2008/2009 UP Copyrights.
11/9/2015 9:42 AM 1 Project Time Control. 11/9/2015 9:42 AM 2  Controlling involves making sure that the results achieved are in line with the planned.
1 8. I MPLEMENTING THE P LAN Objective: To understand the principles of successfully implementing a plan, by communicating the plan to key site personnel,
PROJECT MANAGEMENT Approaches
12/2/2015 2:45 AM 1 PROJECT TIME PLANNING Process and Bar Chart Technique.
PROJECT PLANNING AND SCHEDULLING
P ROJECT M ANAGEMENT. Case study Assumptions Methodology Discussion.
Lecture 61 Project planning tool Lecture 62 Objectives Understand the reasons why projects sometimes fail Describe the different scheduling tools, including.
1 EASTERN MEDITERRANEAN UNIVERSITY FACULTY OF ENGINEERING DEPARTMENT OF CIVIL ENGINEERING CIVL 493 Construction Management Assoc. Prof. Dr. Ibrahim YITMEN.
CON 2001 Construction Methods Tool #1 - Construction Scheduling Presented by Elia Twigg, P.E. (Prof. Ralph V. Locurcio, P.E.)
Project Time Management
Dr. Hany Abd Elshakour 2/18/ :27 PM 1. Dr. Hany Abd Elshakour 2/18/ :27 PM 2 Time Planning and Control Activity on Arrow (Arrow Diagramming.
CE 366 PROJECT MANAGEMENT AND ECONOMICS Robert G. Batson, Ph.D., P.E. Professor of Construction Engineering The University of Alabama
Fundamentals of Project Control Chapter 11 Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project.
Project Scope, Time and Cost IT Project Management PM Knowledge Areas:
Time Planning and Control Time-Scaled Network
Estimating Project Costs
Project Planning and Scheduling
ENGINEERING MANAGEMENT (GE 404)
CHAPTER 6 PROJECT TIME MANAGEMENT
ENGINEERING MANAGEMENT (GE 404)
ENGINEERING MANAGEMENT (GE 404)
PLANNING ENGINEERING AND PROJECT MANAGEMENT
CIVL 493 CONSTRUCTION MANAGEMENT
Time Planning and Control Time-Scaled Network
Activity on Node Approach to CPM Scheduling
THE HIERARCHY OF SCHEDULES
PROJECT MANAGEMENT (BSBI 622)
Project Planning By Phaik San Liew.
LINEAR BALANCE METHOD & MATRIX SCHEDULE
Importance of Project Schedules
6th. Semester Schedule: 1st. Week
CHAPTER 6 PROJECT TIME MANAGEMENT
FACULTY OF ENGINEERING CONSTRUCTION AND BUILDING DEPARTMENT
CHAPTER ONE: RESOURCE ALLOCATION AND SCHEDULING
Presentation transcript:

FACULTY OF ENGINEERING DEPARTMENT OF CIVIL ENGINEERING SPRING SEMESTER ASSOC.PROF.DR. İBRAHİM YİTMEN CIVL 493 CONSTRUCTION MANAGEMENT

PROJECT PLANNING, SCHEDULING & CONTROL 2

OBJECTIVES OF PROJECT PLANNING & SCHEDULING Planning & scheduling a project is an administrative process. The objectives of planning & scheduling are: To forecast the resource requirements of people, material and equipment. To forecast the financial requirements. To provide a suitable control tool against which progress can be measured. To minimize the unproductive time of both men and machine. To find the time required completing the project. To establish the time for delivering the materials required. 3 CIVL 493 CONSTRUCTION MANAGEMENT

PRINCIPLES OF PROJECT PLANNING & SCHEDULING Planning & Scheduling techniques range from simple bar charts to computerized network analysis. However all techniques are based on certain principles such as: i.The plan should provide information in a readily understood form. ii.The plan should be realistic. There is no point, for example, in planning a building to be completed in six months, if the delivery period for cement is five months. iii.The plan should be flexible. It should be possible to alter certain elements without disrupting the entire plan when circumstances change. iv.The plan should serve as a basis for progress monitoring and control. v.The plan should be comprehensive. It should cover all the stages from briefing to commissioning. 4 CIVL 493 CONSTRUCTION MANAGEMENT

PLANNING & SCHEDULING TECHNIQUES The most common and widely used project planning & scheduling techniques are: 1.Bar charts and linked bar charts. 2.Network analysis, either activity on the arrow or on the node. 3.Line of balance, for repetitive construction work. 5 CIVL 493 CONSTRUCTION MANAGEMENT

BAR CHARTS AND LINKED BAR CHARTS Bar charts are the easiest to understand. Most widely used form of planning tool. Even when the more sophisticated techniques like network analysis are used the eventual schedule of work is usually presented in bar chart form. In the bar chart technique, the list of activities is given and the duration of activities are shown as bars corresponding to each activity. The length of the bar determines the duration of activities in a time scale system. The unit of time on construction projects are normally days or weeks or months. See Fig CIVL 493 CONSTRUCTION MANAGEMENT

7 Activity Description Duration (weeks ) TIME SCALE (weeks) Exc. to founds and basement ST 2 Exc. To founds and basement CO 6 Waterproof lining to basement 6 Breakout old Sub structure 1 Conc. Founds ST 3 Conc. Founds CO 3 Conc. Basement walls 2 Figure 5.1- Typical Bar Charts TIME NOW CIVL 493 CONSTRUCTION MANAGEMENT

PROGRESS CONTROL CHARTS Bar Charts can be used as a progress control chart. The bars are drawn in two sections, the upper section showing the planned time, the lower section left blank for recording progress. At the end of each time period the amount of work done in each activity is recorded by shading the lower section. Figure 5.1 shows time now as being end of week 7, the shading on the chart shows activities ‘Exc. To founds and basement ST’ and ‘Conc. Founds ST’ are 100% complete. Activity ‘Exc. To founds and basement CO’ is shown as being four-sixths or 67% complete whereas, to be on programmed, it should be 83% (five- sixth) complete. This means that this activity is unlikely to finish at the end of week 8 as planned. Lower section could be extended to show the new time of finishing. The effect on the other activities would need to be calculated. This effect would be more easily studied by using an extension to the simple bar chart such as the linked bar chart. 8 CIVL 493 CONSTRUCTION MANAGEMENT

LINKED BAR CHARTS The linked bar chart, (shown in Fig. 5.2) shows the links between an activity and the preceding activities which have to be complete before this activity can start. Similarly the links are shown between the activity and the succeeding activities, which are dependent on the activity being completed. This illustration of dependency between activities has the advantage that the effects of delays in any activity are easily seen. The time available for each activity is also displayed: for example, in Fig. 5.2 activity ‘Conc. Founds ST’ is shown as starting on week 3 and finishing on week 5, but it can be seen that the absolute deadline before it interferes with the next succeeding activity, ‘Conc. Founds CO’, is end of week 9. This activity has some ‘float’ or extra time available before any delay affects other activities. Activity ‘Exc. to founds and basement CO’ for example has no float and must be completed by week 8; this is usually called a critical activity. 9 CIVL 493 CONSTRUCTION MANAGEMENT

10 Activity Description Duration (weeks ) TIME SCALE (weeks) Exc. to founds and basement ST 2 (4) Exc. To founds and basement CO 6 (4) Waterproof lining to basement 6 (2) Breakout old Sub structure 1 (2) Conc. Founds ST 3 (3) Conc. Founds CO 3 (3) Conc. Basement walls 2 (3) Figure 5.2- Linked Bar Charts RESOURCE (DIAGRAM) HISTOGRAM

RESOURCE HISTOGRAMS The bar chart is also useful for calculating the resources required for the project. To add the resources, say laborers, to each activity and total them as in Fig. 5.2 is called resource aggregation. A resource aggregation chart similar to the one produced in Fig. 5.2 for laborers can also be done separately for other resource types such as carpenters or steel fixers, or cranes. The bar chart and the resource aggregation charts are useful for estimating the work content in terms of man-hours or machine hours. Similar calculations done on site may be used to check the work content implied by the estimate, so as to determine whether the chosen construction methods will result in a profit or loss. Cost control is more effectively based on such assessment of construction method than on simple historical cost checks. Bar charts as mean of communication between engineers and foreman are particularly useful and can be improved by color coding the activities, for example blue for carpenters, yellow for steel fixers etc. The vertical links indicate dependency between activities; the broken lines indicate ‘float’. Laborers required shown in brackets. 11

ACTIVITY DEFINITION Activity definition involves identifying and documenting the specific activities that must be performed in order to produce the deliverables and sub-deliverables identified in the work breakdown structure (bill of quantity) as shown in below table. 12 CIVL 493 CONSTRUCTION MANAGEMENT

ItemActivity Description A1Excavation A2Sand under Footing A3Compact Soil A4Hardcore B11Plain concrete for footings B12Plain concrete for slabs on grade B13Plain concrete for roof grading B21Reinforced concrete for footings B22Reinforced concrete for ground beams C1Reinforcement For Footing C2Reinforcement For Columns ACTIVITY DEFINITION 13

ACTIVITY DURATION ESTIMATION (CONTINUED) If the work is expressed in terms of quantity (m2 of formwork, ton of steel, m3 of concrete etc) then activity duration is estimated as: D ij = Duration of activity in units of time Q ij = Quantity (m2, m3, ton, pieces etc) P ij = Average productivity of standard crew N ij = Number of standard crew assigned to activity 14 CIVL 493 CONSTRUCTION MANAGEMENT

A small formwork subcontractor is awarded to erect 1000 m2 of formwork. The daily production rate of one crew is 25 m2. a. Calculate the number of days required to complete the job if the subcontractor has 4 crew. b. Calculate the number of days required to complete the job if the subcontractor has 8 crew. ACTIVITY DURATION ESTIMATION (CONTINUED) 15

A small formwork subcontractor is awarded to erect formwork. It has been estimated 80 labor-days is required to complete the job. b) Calculate the number of days required to complete the job if the subcontractor has 8 crew, each crew made up of two workers. a) Calculate the number of days required to complete the job if the subcontractor has 4 crew, each crew is made up of two workers. ACTIVITY DURATION ESTIMATION (CONTINUED) 16

BEGINNING-OF-DAY OR END-OF-DAY In scheduling there are two conventions for describing days. Beginning of day End of day in this course, we follow the end-of-day convention: any date mentioned for an activity means the end of that day. in beginning of day convention, projects start at the beginning of day 1, which becomes the end of day CIVL 493 CONSTRUCTION MANAGEMENT

Activity A B C A D A B C A D End-of-day Convention : Beginning-of-day Convention : 18 CIVL 493 CONSTRUCTION MANAGEMENT

19 CIVL 493 CONSTRUCTION MANAGEMENT RELATIONSHIP TYPES

BAR CHART EXAMPLE 5.1 Anadol Construction Company is awarded a contract to construct a medium sized residential building. Project’s activity list and their relationships are given in table 5.1 below. Draw linked bar chart. Find project completion time. Find critical path(s). 20 CIVL 493 CONSTRUCTION MANAGEMENT

21 ActivitiesActivity DescriptionDuration (days)Preceding AOrganize1- BSite layout1- CExcavation2A, B DFoundation4C EFloor slab1D FStructures6E GRoof construction2F HBrick work4F IMasonry1F JPlumbing & electrical work2H KPlastering4H,I LDoor and windows1K MRoof covering1G NPainting2G,J,L OGlazing1L PClearing1M, N, O TABLE 5.1 – Activity Table

22 SOLUTION OF EXAMPLE 5.1 a) Linked Bar Chart A b) Project completion time is 26 days. c) Critical Path(s) are : (1) A-C-D-E-F-H-K-L-N-P : (2) B-C-D-E-F-H-K-L-N-P

BAR CHART EXAMPLE 5.2 A company is bidding on a work. There are significant liquidated damages if it can not be completed within the scheduled 20 days. The activities, their durations, and relationships are as listed in table 5.2 Draw linked bar chart. Find project completion time. Find critical path(s). 23 CIVL 493 CONSTRUCTION MANAGEMENT

24 ActivityPrecedingDuration(days)RelationshipLag A-2-- BA4FS2 CA3 1 DA2SS1 EB, C4FS,FS2, 0 FC3FS0 GD5 0 HE, F4FS, SS2, 2 IF2FS0 JG2 2 TABLE 5.2 FOR EXAMPLE 5.2

25 SOLUTION OF EXAMPLE 5.2 a) Linked Bar Chart b) Project completion time 20 days c) Critical path(s) is : A-B-E-H