31/10/2011LHC 8:30 meeting 1 Overview LHC Operation Week 43 Machine Coordinators: Barbara Holzer & Jan Uythoven.

Slides:



Advertisements
Similar presentations
8:16 SB 25ns dumped by RF; integrated lumi 0.6 nb-1. 9:14 BIC problem in TI8 and CMS recovering their tracker 10:09 Abort gap cleaning commissioning. 16:29.
Advertisements

Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
LHC progress Saturday 2 nd May 2015 Coordination: Mike Lamont, Wolfgang Hofle.
Wednesday 12 th September Pumping, removal of vacuum equipment from tunnel in the morning TOTEM & ALFA, RP movement tests: OK 11:50 pre-cycle started,
MD#2 News & Plan Tue – Wed (19. – 20.6.) DayTimeMDEiCMP Tue06: GeV  4 TeV: Ramp for chromaticity - missed A 08:00Ramp down 10: GeV: Large.
Lot’s of time lost due to cryo problem in IR8. Major impact, therefore review of MD program… Start discussion here, please let us know your input. Will.
21/05/2012LHC 8:30 meeting Overview Week 20 Injectors, LHCb polarity, Beam-Beam Coordinators: Bernhard Holzer, Jan Uythoven.
LHC 30 th and 31 st July :10 Finish scrubbing fill 25 ns trains by operator dump. –No XPOC data … 08:40 Inject for another scrubbing fill 09:09.
Tuesday 25 th October 08:22 Dump the 25 ns spaced 2100 x 1020 bunches 08:30 – 09:30 25 ns tests with different spacing between trains Until 12:00: Access.
5/11/2012LHC 8:30 meeting Summary of Week 44 Coordination: Mike Lamont & Jan Uythoven.
Weekly summary Summary Week /19.07 M. Lamont & J. Wenninger for the OP team and for all colleagues from the various groups 8:30 meeting 1.
Monday 29 October 08:48 V/dM scan CMS end of fill #3236. Check of “fast scan”. 10:06 V/dM scan finished, start of RF studies, reducing RF voltage. 11:10.
17/09/2012LHC 8:30 meeting LHC Summary Week 37 Coordination: Jorg Wenninger & Jan Uythoven.
CONTENT: Beam characteristics and parameters Filling schemes Operational settings OP procedure and COLL setting Planning Shift breakdown To define the.
:00: Prepared new fill B1: Q X =0.293, Q Y =0.269; lifetime = 25h ✔ B2: Q X =0.297, Q Y =0.267; lifetime = 5h ✗ Strong 50Hz and 100hz lines.
Summary of Week 30 G. Arduini, J. Wenninger Main aims: “Adiabatically” increase peak luminosity by emittance reduction Luminosity production.
LHC progress Report LHCC Wednesday 23 rd March 2011.
Nominal intensity bunches ● First ramp with nominal intensity bunches suffered from an instability appearing around 1.8 TeV. ● Nominal intensity bunches.
LHC 8:30 meetingEBH 11 Thursday 24 November 2011.
LHC Progress Friday 30 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
09:25 Operator dump fill #2178, integrated lumi 107/108/18 nb-1. Trip of RQ4.R6 (fire heaters discharged) just after the beam dump but the QPS gave no.
Saturday ● 06:00: Physics fill from the night shift ● 15:00: End stable beam mode: – problems with incorporation of settings for the squeeze ● 16:40:
LHC progress Sunday 3rd May 2015 Coordination: Mike Lamont, Wolfgang Hofle.
Goal of the week: Stable beams with trains of 200 & 248 bunches 1 OP summary of week 40 R. Bailey, J. Uythoven & J. Wenninger.
Tuesday 24 th July - morning 10:15 Operator dump of fill 2873  Initial luminosity: 5.83e33 cm-2s-1  12 hours stable beams  151 pb-1 delivered  Initial.
06:00 – Ongoing injection problems on beam 2  07:42 – Start of injection investigations  11:11 – Injection problem fixed. Resteering of transfer line.
:00 meetingEBH 11 Saturday :00 meetingEBH 2  7:58 Fill 2483 (264 bunches) dumped by reference orbit set to zero in.
Saturday 11.9 ● From Friday – Minimum required crossing angle is 100  rad in 2010 – Plenty of aperture at triplets: > 13  (n1 > 10) – Can stay with 170.
CONTENT: Beam characteristics and MP concerns BI configuration Operational settings Collimators Planning Shift breakdown Thanks to: P.Baudrenghien, G.Bellodi,
Cryo back at 17:30 Beam back at 19:00 IR2 aperture until ~03:00 Since then no beam from the SPS:  Connector problem on MKD  Connector eroded, needs to.
Production running 1 pb-1Lost to Mon h2062e32EOF studies Tue h17.152e32UFO Q8.L5 Tue h e32OP request Thu h e32OP.
Thursday 27 th October 00:57 fill 2257 dumped during squeeze (RQTF.A67B1) 03:52 stable beams fill #2258 4:33 Dumped, problem of LBDS dilution kicker power.
07:00 Dump fil #2219, 123 pb -1 delivered. Trim TDI parking position to +/- 55 mm in the collimator BP trimmed the temperature kicker limit to 62 degrees.
28/01/2013LHC 8:30 meeting Summary of Week 4 pPb physics Machine Coordination: Mike Lamont & Jan Uythoven Ion coordination: John Jowett.
Monday 19 th March 07:33 Lost (another) beam in the squeeze, beyond 2 m, B2 hits 1/3 resonance. 08:30 Start (another) ramp  Try to correct coupling and.
Ralph Assmann, Giulia Papotti, Frank Zimmermann 25 August 2011
MD Planning Fri – Sat (26. – 27.8.)
Saturday Coordinators weekend: Mike Lamont, Eva Barbara Holzer
Cryo Problem MD Planning Tue (1.11.) C B Day Time MD MP Tue 01:00
Machine Coordinators: G. Arduini, J. Wenninger
Saturday 21st April 00:33 Interlock during ramp on BLM HV
Monday :00 Stable beams 9_6_6_6 13:40 Access.
Summary Friday h38: Ramp down and pre-cycle.
MD Report 24 June 2012 Machine coordinators: Barbara Holzer, Mike Lamont MD Coordinators: Ralph Assmann, Giulia Papotti, Frank Zimmermann MD#2 News & Plan.
Friday 07:00 Power glitch on the EDF network. Point 8 affected.
MD25 ns - 14/12/2012 G. Arduini, H. Bartosik, G. Iadarola, G. Rumolo
Saturday 09:40 Stable beams #1369 (56 bunch scheme)
Fill 1410 revisited Peak luminosity 1.4e32 Beam current 2.68/2.65 e13
Wednesday /Thursday 09-11:00 Verification of the LSS6 interlocked BPMs: took longer to fill due to some problems with RF cavities in the PS. In the mean.
LHC Morning Meeting - G. Arduini
Summary of Week 11: 14 – 21 March
Summary of week 44 Aims of week 44 J. Wenninger & J. Uythoven
Wednesday Morning 8: :30 end of fill study - octupole polarity inversion (Elias, Tatiana, Alexey, Georges, …): Goal: study the effect of the.
MD#4 Progress MD Coordinators: Giulia Papotti, Frank Zimmermann
Week 35 – Technical Stop and Restart
04-05/08/2010 End of physics at ~11:00 after 18.5 hours ~120 nb-1.
Friday morning 10:30 Optics measurements and corrections.
Thursday :00: Physics fill from the night shift
Saturday 7th May Sat – Sun night
Monday 24 October hours of 25ns MD
MD#2 News & Plan Tue – Wed (19. – 20.6.)
Monday morning 09:40 Dump fill 2838, integrated ~130 pb-1.
Thursday 22 September 2011.
Friday 28 October 2011.
Wednesday h18: 228b fill lost just before start of ramp.
Monday 26th September 7:30 Beam dump, QSP on RQX.R1, lost cryo in ITR1, 91 pb-1. Cryo recovery, needed about 1.5 h. Setting of TI2 collimators to 5 sigma.
Another Immortal Fill….
Wednesday 26 October 2011.
HI2011 Commissioning Status
Saturday 29th October Friday during IP2 1 m squeeze test
Presentation transcript:

31/10/2011LHC 8:30 meeting 1 Overview LHC Operation Week 43 Machine Coordinators: Barbara Holzer & Jan Uythoven

Weekend 29 th and 30 th October Friday  19:53 beams dumped fault transformer Point 1 Cryogenics lost in sector 12 Saturday  11:00 Cryo recovered.  Spent the rest of the day and part of the night on IP2 1 m  * optics checks and aperture measurements in preparation of the ion run Sunday  02:40 Transverse damper checks for p+: OK  04:00 Some injection steering  07:27 Stable beams with enhanced satellites, fill #2266  09:49 Vacuum spike at point 4 around the BGI dumped the beam All BGIs switched off  12:57 Stable beams fill #2267 (fast refill, although BQM problems!)  17:17 Last proton physics beam dump of 2011  18:00 Start MD - ATS optics dry run  22:00 Start MD on tune working points, one hour ahead of time Monday  07:00 Start of Proton – Lead MD. 2 LHC 8:30 meeting 31/10/2011

Week 43 overview 3 LHC 8:30 meeting 31/10/2011 BCTs Lumi’s 2e14 8e30 cm-2s-1 (Alice) (ATLAS, CMS) ns test High pile-up Enh. satellites Cryo BPMs Lost Cryo IP2 squeeze Transformer-> Cryo IP2 Squeeze

Physics fills 4 LHC 8:30 meeting 31/10/2011 Fill #LengthPeak lumi [e33 cm-2s-1] Integrated lumi [pb-1] Reason for dump 22674h12min Operator dump 22662h22min BGI vacuum 22615h20min Cryo maintain MSR h02min3.58.2PC dilution kicker LBDS 22560h09min3.61.8PC, RCS.A34B h11min3.534Cryo, sector 12, most likely SEE 22523h16min Operator, end of high pile-up h26min3.595Trip RCBX Total29h58min216.4

Last physics fill The average bunch intensity was changing between 1.43 and 1.5e+11 in the SPS. LHC vacuum has been fine for the last fills (not counting the BGI one) Enhanced satellites seem to work well To take into account for 2012 Just before last dump separated beams in ATLAS, (3sigma V, 1sigma H per beam) 5 LHC 8:30 meeting 31/10/2011

End of Proton Physics LHC 8:30 meeting 31/10/2011

CMS, Atlas & LHCb 7 LHC 8:30 meeting 31/10/2011 CMS record peak lumi this week:

Alice – enhanced satellites Running with enhanced satellites % intensity of nominal bunches Peak lumi between 5 and 8e30 cm-2s-1 Normal detector running at 0.5e30 cm-2s-1 8 LHC 8:30 meeting 31/10/2011 8e30 cm-2s-1

LDM picture of satellites Sunday morning fill 9 LHC 8:30 meeting 31/10/2011 Satellites around 2 – 3 % of nominal bunch intensity Enhanced 25 ns satellites from the PSB

Fill with enhanced satellites for Alice Wall current profile SPS beam Average over sequential 10 turns, 20 ms before extraction 144 bunches with satellites 10 LHC 8:30 meeting 28/10/2011 T.Bohl, S.Hancock Satellites going up to about 8 %, average of few %

LHC 9:00 meetingEBH 11  Satellite distribution for fill The satellite near the bunches range between 1.5% and 6% with an average of 3%. Satellites Fill #2261 (Enrico Bravin)

First injection of 144 bunches with satellites, B1 Losses on ring BLMs factor 6.5 above dump level! Most likely due to injection problems in the SPS, blowing up the beams, and “corrected” by reduced scraping. Subsequent injections with satellites were very clean 12 LHC 8:30 meeting 28/10/2011

The SEE “Quench” of dipole magnet B8.L2 The magnet quench is indeed due to a spurious self- trigger of a quench heater discharge power supply. Such an event has not been observed so far in LHC, also not during radiation test campaigns. This type of power supply has been successfully tested in the TCC2 area (year 2000 campaign) up to 380 Gy (sub-circuits including the trigger circuit were operational up to 1.1 kGy). To my best knowledge a spurious trigger can only be explained by substantial losses. 13 LHC 8:30 meeting 28/10/2011 That’s what we had.... Reiner Denz

QPS signal dipole magnet B8.L2 14 LHC 8:30 meeting 28/10/2011

On October 28 th at 19:53 A fault in the voltage regulation circuitry of the transformer supplying LHC Point 1, LHC Point 18 and the Meyrin Site The circuit was switched off The autotransfer mechanism correctly switched in the alternative supply lines 9 seconds later On October 29 th at 01:15 The electronics was replaced and the nominal network configuration had been re-established On October 28 th at 19:53 A fault in the voltage regulation circuitry of the transformer supplying LHC Point 1, LHC Point 18 and the Meyrin Site The circuit was switched off The autotransfer mechanism correctly switched in the alternative supply lines 9 seconds later On October 29 th at 01:15 The electronics was replaced and the nominal network configuration had been re-established 31/10/2011 Gérard Cumer / EN-EL

31/10/2011 Gérard Cumer / EN-EL

25 ns Finally managed to inject 2100 (B1) against 1020 (B2) bunches with spacing of 925 ns between trains of 72 bunches. Blow-up and losses are still observed along the bunch trains but there is a trend to improvement of the lifetime Heat load data have been collected as well as vacuum data and they indicate an improvement when normalized to current but they must still be analyzed in detail The injection of the beam was strongly hampered by the pressure rise on MKI8 and in particular by magnet D. Because of that the filling scheme had to be adapted to minimize the pressure rise and therefore the impact on the filling rate. During a soft-start of kicker MKI8 a pressure spike has occurred and it required an extended conditioning  Electrical breakdown in MKI8-D kicker magnet during SoftStart (54.3kV, 1200ns). This followed an extended period of 25ns beam and vacuum of ~9e-9mbar in the MKI8 tanks as well as high pressure in the nearby beam pipes.  SIS vacuum interlock, and reluctance to further increase the limit, is justified  ALL electron cloud solenoids were turned off around the MKI8 kickers resulting in the high pressure – this did not help. 17 LHC 8:30 meeting 31/10/2011

LHC 8:30 meetingEBH 18 BSRT bunch by bunch transverse beam size (Fill 2249) Horizontal Vertical

High pile-up run 19 LHC 8:30 meeting 31/10/2011 Injected 11 high intensity bunches ( e11ppb, ~2um at the SPS) to give IP1/5 10 high pile-up colliding pairs (+1 colliding pair for IP8 and IP2) Minimized the time at injection by a semi-dedicated SPS supercycle (LHC4+CNGS only) Observed emittance blow up at the LHC: ~3-3.5um in collisions from wire scanners Achieved a peak pile-up of about 35 Observed once again the impact of number of HO collisions of loss pattern (lower losses for lower number of HO collisions) Separation scans to reduce the pile-up in steps for both CMS and ATLAS (~20% reduction per step) At the end, turned off ADT with head-on colliding beams to observe possible coherent modes Additionally, acquired orbit data which will be looked at offline.

Transverse damper Friday 8:30 – 16:30 update of ADT: D. Valuch, F. Dubouchet, W. Hofle : “We have installed new front end computers, new drivers, new fesa classes and upgraded firmware in the signal processing units.” No problems with subsequent physics fills on Sunday To be set-up again for ions ! 20 LHC 8:30 meeting 31/10/2011

IP2 squeeze 1 m, in prep. of ion run Checked coupling and other optics corrections applied yesterday that were incorporated The coupling correction was increased from a knob value of 0.8 to 1.1. Resulting coupling about , both beams Beta-beat correction was calculated for beam 1 and beam 2. Only 20 correctors, for both beams, around IP2 are used. This resulted in a reduction of the beta-beat from 20% to a peak 10%. betastar was measured with the K-modulation 21 LHC 8:30 meeting 28/10/2011

Measured beams at IP2 with apertures 22 LHC 8:30 meeting 28/10/2011 B1 B2

Triplet Aperture Checks in IP2 We performed the local IR measurements with the technique used already in IP1 and IP5: Local crossing bumps are added to the reference orbit in the crossing and separation planes. An alignment of the TCTs of IR2 was performed to establish reference centres and accurate 12sigma gaps. Starting configuration: -80urad crossing angle; squeezed beams (1m) and separated by 2 x 700 um. For IP2, we immediately noticed that the strength of the standard lumi angle knobs was not sufficient to probe the aperture. So, we had to add on top of them additional crossing knobs generated with the correctors upstream (separated knobs for B1 and B2). For the vertical planes, we found some puzzling results because we saw indication of aperture restrictions upstream of the TCTVB collimators. We did not manage to reach the aperture of the triplets. The minimum aperture for the vertical case were found to be (but not at the triplet!):  B1-V -> 15.5 to 16.0 sigmas  B2-V -> 16.0 to 16.5 sigmas  Due to the uncertainties, the V measurement was only made on one side – other side to be done (for polarity inversion). For the horizontal planes, the measurements were cleaner. We found:  B1-H -> 16.0 to 16.5 sigmas  B2-H -> 15.5 to 16.0 sigmas Note that these results are given in terms of TCT aperture corresponding to the opening that "exposes" the triplet aperture. These results depend slightly on the shape of the bumps used to probe the aperture and therefore detailed offline analysis is required for precise quantitative estimates. Parasitically, we also measured tune shifts versus orbit amplitude. The results will be analysed. 23 LHC 8:30 meeting 28/10/2011 According to Joerg it is likely that the apertures will be revisited after the MD block during the ion set-up period More slides from Joerg on “Latest News” page

H plane B1 Observed aperture limit consistent with triplet AP! 24 LHC 8:30 meeting 31/10/2011 J.Wenninger et al.

From 80 to 140 urad 25 LHC 8:30 meeting 31/10/2011 Operation at 140 urad requires 2.8 mm more orbit margin (peak) in the triplet. Beam size with  =3.5 um is 1.5 mm at beta* 1 m. We need additional 2  to accommodate the 140 urad crossing angle (wrt situation for the AP measurement). >> minimum triplet aperture of 16 sigma with 80 urad to ensure that the triplet is >= 14 sigma with 140 urad. Presently under discussion if the ion run can be done at  * = 1 m at IP2, or if one has to back off slightly

MD Program & Following MD coordinators: Ralph, Frank & Giulia Machine coordinators: Ralph & Gianluigi 26 LHC 8:30 meeting 31/10/2011 Slides Frank