LHC status and commissioning plans. LHC in 4 slides Lest we forget Progress to date Present schedules Consequent plan for 2008.

Slides:



Advertisements
Similar presentations
1 RHIC – p+p and p+Au projections for March 2014 STAR meeting.
Advertisements

Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
PEP-II B Factory Machine Status and Upgrades John T. Seeman for the PEP-II Staff SLAC DOE Site Review April 9, 2003.
A. Bay Beijing October Accelerators We want to study submicroscopic structure of particles. Spatial resolution of a probe ~de Broglie wavelength.
Status of the LHC Project L.Evans - C.Wyss Riunione CSN1 INFN Napoli, 21 Settembre 2005.
LHC status and commissioning plans Gianluigi Arduini, CERN, AB/ABP 10 th September 2007 Acknowledgements: R. Bailey, M. Lamont.
The LHC: an Accelerated Overview Jonathan Walsh May 2, 2006.
LHC progress with beam & plans. Of note since last time Transverse damper Beta beating in the ramp Collimation set-up at 450 GeV & validation LBDS – systematic.
MQXF Cold-mass Assembly and Cryostating H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia 4 th Joint HiLumi LHC-LARP Annual Meeting November 17-21, 2014.
1 Luminosity monitor and LHC operation H. Burkhardt AB/ABP, TAN integration workshop, 10/3/2006 Thanks for discussions and input from Enrico Bravin, Ralph.
Preliminary design of SPPC RF system Jianping DAI 2015/09/11 The CEPC-SppC Study Group Meeting, Sept. 11~12, IHEP.
LHC status & 2009/2010 operations Mike Lamont. Contents Consolidation – brief recall Splices Operational energies Potential performance Present status.
LHC Status - SUSY Bonn 1 Drawing by Sergio Cittolin Status of the LHC 6 months of beam operation in 2010 J. Wenninger CERN.
Stefano Redaelli Beam Department - Operations Group Operational Aspects of the Phase II Crab Cavity System LHC-CC09 3 rd LHC Crab Cavity Workshop European.
ION COMMISSIONING REVISITED 1 Thanks to: John Jowett, Walter Venturini. Matteo Solfaroli.
Partikeldagarna, Göteborg 21 September 2007 LHC: Status and Plans Lyn Evans.
R.Bailey, LHCCWG, January 2007 LHC Commissioning Working Group 2006 Presented to LTC in November and MAC in December Presented to LTC in November and MAC.
LHC progress Report LHCC Wednesday 23 rd March 2011.
The Large Hadron Collider Contents: 1. The machine II. The beam III. The interaction regions IV. First LHC beam [R. Alemany] [CERN AB/OP] [Engineer In.
Brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Inner Triplet Review Q1, Q2, and Q3 Mechanics T. Nicol April 24-25, 2007.
14 Aug. 2008John Huth Harvard DOE Review Introduction: Harvard ATLAS Group John Huth.
EPPOG - LHC Machine LHC machine (and some outreach) Mike Lamont.
ILC MDI workshop January 6-8, 2004 PEP-II IR M. Sullivan 1 Interaction Region of PEP-II M. Sullivan for the ILC MDI workshop January 6-8, 2005.
P. 1K. Eggert – Early TOTEM Running with the  * =90m Optics Karsten Eggert on behalf of the TOTEM Collaboration Politecnico di Bari and Sezione INFN Bari,
C. Garion Presentation Outline  Overview of the inner triplet interconnections  Q1/Q2, Q2/Q3 interconnections  General view  Working conditions  Compensation.
4/27/06 1 US LHC ACCELERATOR RESEARCH PROGRAM brookhaven - fermilab – berkeley - slac US LARP Inner Triplet Cryogenics and Heat Transfer LARP Collaboration.
M. Gilchriese LHC Startup Luminosity Planning July 29, 2005.
1 RHIC II – Ion Operation Wolfram Fischer RHIC II Workshop, BNL – Working Group: Equation of State 27 April 2005.
CONTENT: Beam characteristics and MP concerns BI configuration Operational settings Collimators Planning Shift breakdown Thanks to: P.Baudrenghien, G.Bellodi,
LHC Machine Operational Status and Plans LHCC, 22nd September 2010 Steve Myers (On behalf of the LHC team and international collaborators)
R.Bailey, Chamonix XV, February 2006 Staged commissioning plan for protons Hardware commissioning Machine checkout Beam commissioning 43 bunch operation.
Steve Playfer University of Edinburgh 15th Novemebr 2008 Large Hadron Collider at CERN.
Progress with Beam Report to LMC, Machine Coordination W10: Mike Lamont – Ralph Assmann Thanks to other machine coordinators, EIC’s, operators,
LHC Commissioning Status Gianluigi Arduini CERN – AB Department For… 23/10/20081LHC Commissioning Status - G. Arduini.
Joint LHC Machine-Experiments Workshop on Very Forward Detectors Summary D. Macina (CERN) Joint LHC Machine-Experiment Worshop on the Luminosity Monitoring.
The Large Hadron Collider The 19 th Sep 2008 incident [R. Alemany] [CERN AB/OP] [Engineer In Charge of LHC] NIKHEF Seminar ( )
Accelerator system Activity 1 Activity 2 Activity n LTC Dec 14 th 05 : LHC commissioning organisation Machine Coordinator Weekly responsibility 3 needed.
Inner Triplet Review 1 H. Prin AT/MEL Activities on the triplets at CERN Reception and Acceptance Triplet String Assembly in Building 181 Handling and.
NIKHEF Annual Meeting, December 18, The LHC Project Status report to the NIKHEF annual meeting Jos Engelen Based on last week’s reports to CERN.
Status of the LHC Project
Luminosity monitor and LHC operation
LHC Commissioning with Beam
MPI-ATL Calor Meeting 7-Sep-2009 H. Oberlack MPI für Physik, Munich
LHC schedule.
Status of design and production of LEP connection cryostat
A. Vande Craen, C. Eymin, M. Moretti, D. Ramos CERN
The LHC - Status Is COLD Is almost fully commissioned
Long Shutdown for the LHC: Vacuum Beam Pipes
Powering the LHC Magnets
Lecture 2 Live Feed – CERN Control Centre
Status of the BLHC ….work in progress! Mike Lamont CERN/AB 18/01/2008
The Status of the LHC machine
Machine plans - Alignment workshop
Status of the LHC December 2009
Fill 1410 revisited Peak luminosity 1.4e32 Beam current 2.68/2.65 e13
Tue :25 Beams dumped due to RF vacuum interlock
Mike Lamont 4th HERA and the LHC workshop 26th May 2008
CEPC-SppC Accelerator CDR Copmpletion at the end of 2017
J. Uythoven, W. Venturini Delsolaro, CERN, Geneva
Overall commissioning strategy for protons (estd. 2005)
LHC Beam Operations Past, Present and Future
Summary Thursday h21: Stable beams fill #1303.
Machine plans - CMS startup workshop
Thursday 04/11 - Morning Access until ~13:00 Pre-cycle Proton checks:
SLHC-PP kick-off meeting, CERN 9 April 2008
Another Immortal Fill….
Hardware Commissioning
Beam commissioning plans, 2007 and 2008
LS 1 start date 12th June Schedule Extension 2012 run Extension of 2012 run approved by the DG on 3rd July 2012.
LHC Machine Advisory Committee, CERN 12th June 2008
Presentation transcript:

LHC status and commissioning plans

LHC in 4 slides Lest we forget Progress to date Present schedules Consequent plan for 2008

R.Bailey, DESY, December 2007 LHC dipoles (1232 of them) operating at 1.9K 7TeV 8.33T 11850A 7MJ

R.Bailey, DESY, December 2007 And plenty more magnets besides … Several thousand magnets Thousands of Interconnects Electrical Fluids Vacuum

R.Bailey, DESY, December 2007 And plenty of power circuits … Several hundred Power Circuits

R.Bailey, DESY, December 2007 Lest we forget – QRL Installation started in sector 7-8 in July 2003 Installation started in sector 7-8 in July 2003 Geometry, weld quality, procedures, leaks, support tables … Geometry, weld quality, procedures, leaks, support tables … Installation finished November 2006 (sector 78 by CERN) Installation finished November 2006 (sector 78 by CERN)

R.Bailey, DESY, December 2007 Lest we forget – Main magnets First magnet installed March 2005 First magnet installed March 2005 Peak of ~1000 dipoles stored, allowed magnet sorting Peak of ~1000 dipoles stored, allowed magnet sorting Last dipole lowered April 26 th 2007 Last dipole lowered April 26 th 2007 Cryostating425 FTE. years Cryostating425 FTE. years Cold tests640 FTE. years Cold tests640 FTE. years Transport30’000 km underground at 2 km/h! Transport30’000 km underground at 2 km/h!

R.Bailey, DESY, December 2007 Lest we forget – Triplets – Heat exchanger problem During the pressure test of Sector 7-8 (25 November 2006) the corrugated heat exchanger tube in the inner triplet failed by buckling at 9 bar (external) differential pressure. During the pressure test of Sector 7-8 (25 November 2006) the corrugated heat exchanger tube in the inner triplet failed by buckling at 9 bar (external) differential pressure. The inner triplet was isolated and the pressure test of the whole octant was successfully carried out to the maximum pressure of 27.5 bar, thus allowing it to be later cooled down. The inner triplet was isolated and the pressure test of the whole octant was successfully carried out to the maximum pressure of 27.5 bar, thus allowing it to be later cooled down. Reduced-height of corrugations and annealing of copper near the brazed joint at the tube extremities accounted for the insufficient resistance to buckling. Reduced-height of corrugations and annealing of copper near the brazed joint at the tube extremities accounted for the insufficient resistance to buckling. New tubes were produced with higher wall thickness, no change in corrugation height at ends, and e-beam welded collars to increase distance to the brazed joint. New tubes were produced with higher wall thickness, no change in corrugation height at ends, and e-beam welded collars to increase distance to the brazed joint. Installation of these tubes was made in situ. Installation of these tubes was made in situ.

R.Bailey, DESY, December 2007 Lest we forget – Triplets – Supports problem Q1 supports at IP 5L On Tuesday March there was a serious failure in a high-pressure test at CERN of a Fermilab-built “inner-triplet” series of three quadrupole magnets

R.Bailey, DESY, December 2007 Lest we forget – Triplets – Supports solution Requirements for repair Requirements for repair Must be implemented in situ Must be implemented in situ Does not displace the fixed points of the assembly Does not displace the fixed points of the assembly React loads with sufficient stiffness to limit deflection at 150 kN design load React loads with sufficient stiffness to limit deflection at 150 kN design load Acts at any temperature between 300K and 2K Acts at any temperature between 300K and 2K To be implemented in Q1 and Q3 To be implemented in Q1 and Q3 Solution adopted Solution adopted Affixed at Q1 non-IP end and at Q3 IP end Affixed at Q1 non-IP end and at Q3 IP end Transfer load at all temperatures Transfer load at all temperatures Limits support deflections Limits support deflections Compound design with Invar rod and aluminium alloy tube Compound design with Invar rod and aluminium alloy tube Attached with brackets to cold mass and cryostat outer vessel Attached with brackets to cold mass and cryostat outer vessel Status Status All triplets repaired by September All triplets repaired by September Problem solved Problem solved

R.Bailey, DESY, December 2007 Commissioning of the power converters PC 18kV for the dipole circuits 400V for the others Water UPS for all converters above 4 kA DCCT Short Circuit UA, UJ, RR tunnel, UJ 1720/1720 installed Commissioning campaign on short circuit From mid 2006 to late % commissioned

R.Bailey, DESY, December 2007 Machine commissioning without beam is by sector 8 distinct sectors for cryogenic and powering Picture today Order was originally determined by installation sequence

R.Bailey, DESY, December 2007 Shielded bellows on the cold interconnects (PiMs)

R.Bailey, DESY, December 2007 Plug in Module in equivalent cold position

R.Bailey, DESY, December 2007 RF mole Polycarbonate shell Diameter 34mm exterior 30mm interior Total weight ~15 g (ball 8g) RF characteristics 40MHz resonantcircuit Generates 20V between copper electrodes Battery powered Over 2hr lifetime Capacitive coupling to BPM electrodes 1V ⇒ ~5mV -45db Coupling BPM trigger threshold at ~3mV

R.Bailey, DESY, December 2007 Commissioning of sector 45 (without triplet) Water in the oil of Compressor station Leak to insulating vacuum Stop for repair Leak to insulating vacuum Stop for repair Almost ready for powering

R.Bailey, DESY, December 2007 Beam tests October 2004 October 2007

R.Bailey, DESY, December 2007 Performance goals Nearly all the parameters are variable Nearly all the parameters are variable Number of particles per bunch  Number of particles per bunch  Number of bunches per beamk b Number of bunches per beamk b Relativistic factor (E/m 0 )  Relativistic factor (E/m 0 )  Normalised emittance  n Normalised emittance  n Beta function at the IP  * Beta function at the IP  * Crossing angle factorF Crossing angle factorF Full crossing angle  c Full crossing angle  c Bunch length  z Bunch length  z Transverse beam size at the IP  * Transverse beam size at the IP  * “Thus, to achieve high luminosity, all one has to do is make (lots of) high population bunches of low emittance to collide at high frequency at locations where the beam optics provides as low values of the amplitude functions as possible.” PDG 2005, chapter 25

R.Bailey, DESY, December 2007 Overall commissioning strategy for protons (est d. 2005) Hardware commissioning Machine checkout Beam commissioning 43 bunch operation 75ns ops 25ns ops I Install Phase II and MKB 25ns ops II Stage A BC No beamBeam D I.Pilot physics run First collisions First collisions 43 bunches, no crossing angle, no squeeze, moderate intensities 43 bunches, no crossing angle, no squeeze, moderate intensities Push performance Push performance Performance limit cm -2 s -1 (event pileup) Performance limit cm -2 s -1 (event pileup) II.75ns operation Establish multi-bunch operation, moderate intensities Establish multi-bunch operation, moderate intensities Relaxed machine parameters (squeeze and crossing angle) Relaxed machine parameters (squeeze and crossing angle) Push squeeze and crossing angle Push squeeze and crossing angle Performance limit cm -2 s -1 (event pileup) Performance limit cm -2 s -1 (event pileup) III.25ns operation I Nominal crossing angle Nominal crossing angle Push squeeze Push squeeze Increase intensity to 50% nominal Increase intensity to 50% nominal Performance limit cm -2 s -1 Performance limit cm -2 s -1 IV.25ns operation II Push towards nominal performance Push towards nominal performance

R.Bailey, DESY, December 2007 LHCb during Stage A Displace bunches in one ring (n on m) Displace bunches in one ring (n on m) 4 per SPS cycle in 43 bunch, 16 per SPS cycle in 156 bunch mode 4 per SPS cycle in 43 bunch, 16 per SPS cycle in 156 bunch mode Dedicated runs for LHCb (n on n) ? Dedicated runs for LHCb (n on n) ? Squeeze in point 8 (2m limit for ‘bad’ LHC dipole polarity) Squeeze in point 8 (2m limit for ‘bad’ LHC dipole polarity) All values for All values for nominal emittance nominal emittance 7TeV 7TeV Parameters Rates in 8 kbkbkbkbN  * 8 (m)Luminosity (cm -2 s -1 ) Events/crossing 1 on << 1 4 on << 1 4 on on on on on

R.Bailey, DESY, December 2007 Stage B physics run Parameters Beam levels Rates in 1 and 5 Rates in 2 and 8 kbkbkbkbN  * 1,5 (m) I beam proton E beam (MJ)Luminosity (cm -2 s -1 ) Events/crossingLuminosity Events/crossing << Relaxed crossing angle (250  rad) Relaxed crossing angle (250  rad) Start un-squeezed Start un-squeezed Then go to where we were in stage A Then go to where we were in stage A All values for All values for nominal emittance nominal emittance 7TeV 7TeV 10m  * in points 2 and 8 (will not be like this) 10m  * in points 2 and 8 (will not be like this) Protons/beam ≈ few Stored energy/beam ≤ 100MJ

R.Bailey, DESY, December 2007 Stage C physics run Parameters Beam levels Rates in 1 and 5 Rates in 2 and 8 kbkbkbkbN  * 1,5 (m) I beam proton E beam (MJ)Luminosity (cm -2 s -1 ) Events/crossingLuminosity Events/crossing << Nominal Nominal crossing angle (285  rad) Nominal crossing angle (285  rad) Start un-squeezed Start un-squeezed Then go to where we were in stage B Then go to where we were in stage B All values for All values for nominal emittance nominal emittance 7TeV 7TeV 10m  * in points 2 and 8 (will not be like this) 10m  * in points 2 and 8 (will not be like this) Protons/beam ≈ Stored energy/beam ≥ 100MJ

R.Bailey, DESY, December 2007 Stage A: routes through the commissioning phases Circulating beam Injection First turn 450GeV initial 450GeV optics 450GeV 2 beams 450GeV Increase I Circulating beam Injection First turn 450GeV initial 450GeV optics 450GeV Increase I Snapback Ramp Top energy checks Top energy Collisions Snapback Ramp Top energy checks Squeeze Pilot physics Ramp both beams Squeeze both beams Beam 2 Beam 1 2 beams 450GeV Collisions Experiment magnets OFF Dipoles OFF

R.Bailey, DESY, December 2007 Beam commissioning to 7 TeV collisions Rings Total [days] 1Injection and first turn2 4 2Circulating beam GeV – initial commissioning GeV – detailed optics studies GeV increase intensity GeV - two beams GeV - collisions1 2 8aRamp - single beam2 8 8bRamp - both beams TeV – top energy checks2 2 10aTop energy collisions1 1 TOTAL TO FIRST COLLISIONS (beam time) 30 11Commission squeeze2 6 10bSet-up physics - partially squeezed1 2 TOTAL TO PILOT PHYSICS RUN (beam time) 44

R.Bailey, DESY, December 2007 Stage A: First collisions Approx 30 days of beam time to establish first collisions Approx 30 days of beam time to establish first collisions Un-squeezed Un-squeezed Low intensity Low intensity Approx 2 months elapsed time Approx 2 months elapsed time Given optimistic machine availability Given optimistic machine availability Continued commissioning thereafter Continued commissioning thereafter Increased intensity Increased intensity Squeeze Squeeze

R.Bailey, DESY, December 2007 Staged commissioning plan for protons Hardware commissioning 450 GeV and 7TeV 2008 Machine checkout Beam commissioning 450 GeV Machine checkout Beam commissioning 7TeV 43 bunch operation Shutdown BC No beamBeam Shutdown Machine checkout Beam Setup 75ns ops25ns ops IShutdown 2009 No beamBeam A

R.Bailey, DESY, December 2007 First beam Beam 2 Beam 1