Reliability Pricing Model (RPM) Overview Andrew Ott PJM Senior Vice President, Markets.

Slides:



Advertisements
Similar presentations
In the Post 06 Environment November 9, 2006 Jim Eber Demand Response.
Advertisements

Proposal For Improvement to the Current ICAP Market Markets Committee October 12, 2004 Ken Bekman Con Edison Energy.
PJM ©2008 Regional Round-up of Demand Response Developments Susan Covino PJM Interconnection A National Town Meeting on Demand Response Washington, DC.
Standard Market Design (SMD) in New England Federal Energy Regulation Commission Conference on Standard Market Design January 22, 2002 David LaPlante Vice.
Update on Demand Resource Participation in New Englands Forward Capacity Market Henry Yoshimura Demand Resources Department ISO New England, Inc. Holyoke,
© 2013 Day Pitney LLP Overview and Update on the Ever-Evolving New England Wholesale Capacity Market presentation to Boston Bar Association May 23, 2013.
Brookfield Renewable Energy Group. Focusing on Renewable Power Generation and Transmission Conceptual discussion how to integrate renewable resources under.
1 Capacity mechanisms - IFIEC position June 12 th 2012.
Wholesale Markets and How Efficiency Has Financial Value Dan Griffiths KEEA Energy Efficiency Conference September 21, 2010.
Gloria Godson VP, Federal Regulatory Policy Reliability Pricing Model Part 2.
New Base Load Generation in RTOs-- Time to Get Real Susan N. Kelly VP, Policy Analysis and General Counsel American Public Power Association NARUC Summer.
Enhancing Capacity Markets to Improve Resource Performance and Investment Pay For Performance: New England’s Capacity Market OPSI 10 TH ANNUAL MEETING.
California Energy Commission Retail Electric Rate Scenarios: Key Drivers and Structure 2015 Integrated Energy Policy Report California Energy Commission.
PJM©2014www.pjm.com Winter 2014 Overview & Recent and Upcoming Market Rule Changes Adam Keech Director, Market Operations.
Resource Adequacy in PJM
1 NBS-M017 – 2013 CLIMATE CHANGE: GOVERNANCE AND COMPLIANCE Electricity Market Reform Aims to integrate both the Wholesale and Low Carbon Electricity Markets.
Kansas Renewable Energy and Energy Efficiency Conference Wind 2007 RFP Update John Grimwade - Sr. Director Strategic Planning and Development September.
1 Presentation to the Wisconsin Industrial Energy Group (WIEG) T. Graham Edwards President & CEO August 9, 2007.
Ontario Electricity Industry : Planning Ahead Amir Shalaby VP, Power System Planning Ontario Power Authority Presentation to Canadian Nuclear Society The.
Susan Covino Senior Consultant, Emerging Markets March 31, 2015
1 Resource Adequacy and Market Power Mitigation via Option Contracts Hung-po Chao and Robert Wilson EPRI and Stanford University Presentation at POWER.
G 200 L 200 ISO NEW ENGLAND T H E P E O P L E B E H I N D N E W E N G L A N D ’ S P O W E R. COLD SNAP Overview of Proposed Options for Winter 2004/2005.
Utility Regulation March 10, 2011 Raj Addepalli Deputy Director, Electric, Office of Electric,Gas and Water New York State Department of Public Service.
The Convergence of Market Designs for Adequate Generating Capacity Peter Cramton and Steven Stoft 24 March 2006.
Overview of LMP Markets Features of ISOs / RTOs David Withrow Senior Market Economist Fall 2007 Meeting of the NARUC Staff Subcommittee on Accounting and.
North American Electricity Markets APEX Paris, France October 15-16, 2007 Kenneth Laughlin, PJM.
BOSTON CHICAGO DALLAS DENVER LOS ANGELES MENLO PARK MONTREAL NEW YORK SAN FRANCISCO WASHINGTON Governors’ Wind Energy Coalition November, 2011 Competitive.
Power Utilities in the Telecom Business in the USA: Past Failures and Future Trends Mike Oldak Vice President & General Counsel Utilities Telecom Council.
Progressive Energy Solutions, LLC July 28, 2010 NYMEX N. Illinois Hub Electric Prices 12-Month Forward Prices Through July 15, 2010 * NEU Electric and.
Gas & Power Coordination: Growing Pains in Time of Transition Mark Stultz, BP Natural Gas Supply Association OPSI Annual Meeting Chicago, Illinois October.
John Dumas Director of Wholesale Market Operations ERCOT Operating Reserve Demand Curve.
New England’s Power System: At a Crossroads – Again! Stephen Rourke VICE PRESIDENT, SYSTEM PLANNING NECPUC Symposium: Governors’ Infrastructure Initiative.
ISO New England Regional Update Wholesale Electricity Markets & State Energy Policy Seminar Connecticut Business & Industry Association December 14, 2010.
Electric Generation Reliability Remarks Before the Pennsylvania Public Utility Commission 2011 Summer Reliability Assessment Meeting June.
1 PRR 776 in the Context of the ERCOT Market Design Eric S. Schubert Regulatory Affairs Advisor BP Energy Company.
Overview of the North American and Canadian Markets 2008 APEX Conference in Sydney, Australia October 13, 2008 Hung-po Chao Director, Market Strategy and.
For discussion purposes only Financial Transmission Rights: Design options Presentation to Electricity Commission 2 September 2009.
Overview of the Capacity Markets in the United States 2008 APEX Conference in Sydney, Australia October 13-14, 2008 Hung-po Chao Director, Market Strategy.
EPSA REGULATORY AFFAIR CONFERENCE 2006 Washington, DC October 25, 2006 Garry Brown Vice President, External Affairs New York ISO.
1 Capacity Markets Investment in Generation Capacity Payments October 31, 2005 J. W. Charlton.
Bulk Power Transmission System
1 Electricity System and Energy Market Basics David J. Lawrence Manager, Auxiliary Market Products Prepared for: RGGI I&L Workshop June 15, 2006.
Attachment to Testimony of Joseph Bowring Ohio Energy Mandates Study Committee April 16, 2015.
PJM©2012www.pjm.com PJM’s Experience with Capacity Markets Terry Boston President & CEO PJM Interconnection Power Across Texas September 21, 2012.
1 Market Evolution Program Long-Term Resource Adequacy Regulatory Affairs Standing Committee Meeting May 14, 2003.
October 6, 2006 Public Stakeholder Review Portland, Oregon Conditional Firm.
©2005 PJM 1 STATE OF THE MARKET REPORT 2004 Joseph E. Bowring Market Monitor FERC Briefing April 13, 2005.
PJM © 2006 The Institute for Regulatory Policy Studies Illinois State University Conference May 12, 2006 Jeff Bladen PJM Interconnection.
Demand Response: What It Is and Why It’s Important 2007 APPA National Conference San Antonio, Texas June 26, :00 a.m. to Noon Glenn M. Wilson Director.
PJM©2013www.pjm.com Demand Side Working Group Loads in SCED Angelo Marcino Real-Time Market Operations – PJM April 14, 2014.
S PIEGEL & M C D IARMID New England’s Forward Capacity Market: How Did We Get Here and Where Are We Going? Scott H. Strauss APPA Legal Seminar Cambridge,
Energizing you, powering our communities. Dynegy Energy Services September 18, 2015.
1 NAUSCA Summer Meeting Boston June 30, 3009 David W. Hadley Vice President State Regulatory Relations Midwest ISO.
June 2008 Windsor-Essex Electrical Service Needs and Solutions.
Texas Nodal Team Cost Benefit Group Background to Standard Market Design in New England March 2, 2004 Michael Taniwha Manager, Market Administration ISO.
Conference on Standard Market Design Issues Alice Fernandez, FERC Staff January 22-23, 2002.
G 200 L 200 ISO NEW ENGLAND T H E P E O P L E B E H I N D N E W E N G L A N D ’ S P O W E R. Southwest Connecticut RFP Markets Committee November 14, 2003.
Programs/Products that ERCOT Does Not Presently Offer ERCOT Demand Side Working Group New DR Product Options Subgroup Jay Zarnikau Frontier Associates.
AB 32 Update December 6, Outline Cap and Trade Program 2013 Update to Scoping Plan Looking ahead to
Status Report on 2007–2016 Long-Term Reliability Assessment Mark Lauby August 16, 2007.
Allegheny Power Residential Demand Response Program
Affordable Energy Production from Renewable Fuel
Duquesne Light Company Makes Heads or Tails of “PJM Market Design Proposals Addressing State Public Policy Initiatives Capacity Repricing” OPSI 2017.
Flexible Forward Contracts for Renewable Energy Generators
The Future of Demand Response in New England
Mass Government Finance Officers Assoc
Benefits of New England’s Proposed Capacity Market
Long-term Capacity Market
Alternative ICAP Proposal
Presentation transcript:

Reliability Pricing Model (RPM) Overview Andrew Ott PJM Senior Vice President, Markets

©2008 PJM 2 Reliability Pricing Model (RPM) Methods to satisfy capacity obligation within PJM 1.Self Supply or Bilateral Contract –Self schedule supply into RPM –Unit-specific bilateral contract 2.RPM Auction –Residual auction –Accommodates flexible self-supply 3.Alternative Capacity Plan –utilities submit long term supply plan (5 years) with specified self-supply or long-term contracts

©2008 PJM 3 Reliability Pricing Model Rationale for key aspects Locational Signals –Integration with transmission planning Forward Auction –Need forward information for reliability –Permits planned generation and DSR to participate Sloped Demand Curve –Reduces volatility –Set shortage price cap –Quantifies value of excess capacity

©2008 PJM 4 Highlights of RPM Auction Design PJM invites resource-specific sell offers for planning each year, three years in advance. Products that may be offered include: existing and planned generation; planned transmission upgrades; and existing and planned demand resources New generation, new demand response alternatives, and new transmission solutions can compete directly with existing resources

©2008 PJM 5 Timing of RPM Auctions Base Residual Auction Planning Year 3 Years Incremental Auction June May 4 months 13 months Incremental Auction 23 months EFORd Fixed Self- Supply & Bilateral Designation Ongoing Bilateral Market – (shorter-term reconfiguration) ILR

RPM Auction Results

©2008 PJM 7 RPM Results – Capacity Prices

©2008 PJM 8 RPM Results - Reliability Target Trends

©2008 PJM 9 Cumulative Increases in Capacity Committed to PJM In RPM Auctions

©2008 PJM 10 Demand Response in Capacity Market RPM Implemented

©2008 PJM 11 Increase in Capacity Resource for 2011/2012 RPM Auction Total Increase = 4238 MW

©2008 PJM 12 Cumulative Increase in Capacity Resources over First Five RPM Auctions (2007 – 2011) Total Increase = MW

©2008 PJM 13 Cumulative Increase in Capacity Resources by Fuel Type over First Five RPM Auctions (2007 – 2011) Total Increase = MW Note: Other Renewable includes landfill gas and solid waste

©2008 PJM 14 Proposed timeline for RPM Performance Evaluation ActivityDate Brattle group report posting Informational filing to FERC June 30, 2008 Brattle Presentation to Stakeholders with Q&A July 11, 2008 Wilmington, DE Stakeholder Forum to Discuss Brattle Report Recommendations July 31, AM Wilmington, DE Stakeholder Discussion to develop ongoing stakeholder process timeline, set scope and priorities July 31, PM Wilmington, DE

©2008 PJM 15 High Level Comparison of PJM RPM and New England Forward Capacity Market FeaturePJM RPMNew England FCM Marginal PricingYes Locational RequirementsYes Demand CurveSlopedVertical Auction FormatOptimizationDescending Clock Demand Response as Resource Yes Energy Efficiency as Resource No (In stakeholder discussion) Yes Forward Auction Timeframe3 Year Commitment Period1 Year (3 year optional for new resource) 1 Year (5 year optional for new resource) Energy Revenue OffsetEstimate based on 3 yr. historical average for reference unit Based on calculated revenue in DY for reference unit