Magellan Associate Director Report Personnel Observing Statistics Commissioning of Instruments Facility instruments User (P.I.) Instruments Clean Room.

Slides:



Advertisements
Similar presentations
Ironwood Remote Observatory (IRO) Kenneth Archer July 2007 Ironwood Observatories.
Advertisements

First Light at Prompt7 (Chart32) Chilean Advanced Remote Telescope 32“ operating at Cerro Tololo/Chile (CTIO) March 04, Johannes Schedler.
LBT Q Eng/SW Review SFWG – Software Group General Norm Cushing.
MMIRS 1 MMIRS MMT and Magellan Infrared Spectrograph Brian McLeod.
GSMT Control Workshop Tucson, September 11-12, 2001 Pointing Control for a giant segmented mirror telescope Patrick Wallace Rutherford Appleton Laboratory.
Highly Efficient Operations Keck Scientific Strategic Planning 2009 Hilton Lewis T. Armandroff, S. Adkins, R. Goodrich J. Johnson, K. Kinoshita, R. Matsuda.
Relocation of the Operations Control Center Oil Movements May 4, 2007 For RCAC Board Meeting.
Surveying I. Lecture 2..
Sz. Rózsa: Surveying I. – Lecture 2
Return to Hubble: Servicing Mission 4 Dr. Frank Summers Space Telescope Science Institute April 2, 2009.
Magellan Associate Director Report Personnel Observing Statistics Commissioning of Instruments.
Keck I Cassegrain ADC: Preliminary Design Overview UCO/Lick Observatory 15 October 2003.
Magellan Associate Director Report Personnel Observing Statistics Telescope Operations.
1: Operating Systems Overview
NGAO Alignment Plan See KAON 719 P. Wizinowich. 2 Introduction KAON 719 is intended to define & describe the alignments that will need to be performed.
MMT AO run Jan Timeline: –Night 1: Install hardware during MMT engineering –Nights 2-4: AO engineering with fast-framing H camera (Indigo) –Nights.
LBC-Blue pre-commissioning LBC-Blue LBC-Blue –E Giallongo (PI) Rome: diPaola, Pedichini, Speziali, Testa, Gallozzi Rome: diPaola, Pedichini, Speziali,
LIGO-G D 1 Requirements Environment and constraints Performance requirements Functional requirements.
PLATO kick-off meeting 09-Nov-2010 PLATO Payload overall architecture.
PALM-3000 Instrument commissioning schedule Antonin Bouchez Team Meeting #7 27 February, 2008.
Micro and Nano Characterization Facility
December 3-4, 2007Earthquake Readiness Workshop Seismic Design Considerations Mike Sheehan.
Technical manager’s report September Telescope activities Primary mirror hardpoint repair New mirror actuator controls Collimation analysis F/5.
Commercial Database Applications Testing. Test Plan Testing Strategy Testing Planning Testing Design (covered in other modules) Unit Testing (covered.
The Michigan/Magellan Fiber System (M2FS): An MRI Instrument Development Proposal to NSF.
Magellan Associate Director Report Personnel Observing Statistics Commissioning of Instruments Committees.
SALT Technology Development Lisa Crause India-South Africa Astronomy Workshop – SAAO 6 August 2012.
MCAO Adaptive Optics Module Mechanical Design Eric James.
18/19 January 2003IMACS SAC meeting update1 IMACS: Inamori-Magellan Areal Camera and Spectrograph Magellan SAC Status Report 18/19 January 2003 OCIW, Pasadena,
LOGO OPERATING SYSTEM Dalia AL-Dabbagh
Operating System Review September 10, 2012Introduction to Computer Security ©2004 Matt Bishop Slide #1-1.
Magellan F/5 System Status A.Szentgyorgyi/SAO/30 Apr 2005.
Computer Operations Group Data Centre Facilities Hitendra Patel June 2015.
Magellan Director Report Personnel Observing Statistics Instrument Commissioning Instrument Development Fast Internet Connection Publications (A. Uomoto)
17/18 May 2003IMACS SAC meeting update1 IMACS: Inamori-Magellan Areal Camera and Spectrograph Magellan SAC Status Report 17/18 May 2003 Univ. of Michigan,
Magellan F/5 System Status A.Szentgyorgyi/SAO/25 Sept 2004.
The Observations of LAMOST Jianrong Shi NAOC 1/
Magellan Telescopes Observatory Report Accomplishments Problems Work in Progress Network f5 mirror coating.
Magellan F/5 System Status A.Szentgyorgyi / Ann Arbor 25 Sept 2005.
6-7 October 2001Inamori-Magellan Areal Camera & Spectrograph 1 IMACS: Inamori-Magellan Areal Camera and Spectrograph Magellan SAC Status Report 6-7 October.
January 2008: Subaru Users' Meeting Current status of Subaru Telescope Summary –Some glitches are expected while leased computers are being replaced (February.
Magellan Associate Director Report Personnel Observing Statistics Commissioning of Instruments Existing instruments Future Instruments.
13-14 April 2002Inamori-Magellan Areal Camera & Spectrograph 1 IMACS: Inamori-Magellan Areal Camera and Spectrograph Magellan SAC Status Report April.
Magellan Telescopes Instrumentation: A Critical Assessment of Current Status.
A Detector Upgrade for LDSS3 Mike Gladders Jacob Bean (on the phone) with Andreas Seifart, Josh Frieman, John Carlstrom.
Magellan F/5 Status Eavesdropping PISCO Andrew Szentgyorgyi 25 Apr 2011/Pasadena 4/25/111Magellan SAC/Pasadena.
SAC Report Povilas Palunas 2/23/ Primary Mirrors Primary Aluminizing Schedule back on track –Baade aluminized in Jan after 4 years. 3% gain over.
MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.
Magellan SAC April 7-8, 2006 Pasadena, CA. Personnel New hires: –None Open positions: –Programmer –Scientists (two, through AAO) Changes –Pasadena EE.
Magellan Telescopes Observatory Report Personnel Network/Systems Administration Observing Statistics.
Pasadena Updates March February 2009 PFSMegacam MMIRS FourStar Some of the instruments arriving at Magellan in the next year.
Magellan Telescopes Observatory Report Personnel Accomplishments Observing Statistics Common Problems Work in Progress.
Incoming instruments. New instruments IMACS MOEMultiobject echellette LDSS upgradeMultiobject optical spectroscopy CorMASSLow-res visiting NIR spectrograph.
FourStar Status SAC Meeting 13mar2010 Persson, Murphy, Birk, Monson, Kelson, Uomoto.
J. H. Burgea,b, W. Davisona, H. M. Martina, C. Zhaob
MMIRS 1 Harvard-Smithsonian Center for Astrophysics Magellan SAC 9/05 MMIRS Status Upate Presented by A. Szentgyorgyi P.I. B. McLeod.
LBT Q Eng/SW Review DIMM – Differential Image Motion Monitor.
Operations Good –Telescope downtime is low –Important repairs accomplished –Observer satisfaction is high Bad –Maintenance is deferred –Unfinished work.
MagIC Upgrade for High-Speed Photometry Jim Elliot, MIT Magellan SAC
Communication Tools Used For Commissioning the 12 GeV CEBAF Accelerator Brian Freeman WAO (Mainz, Germany) October 2014.
Blanco Telescope and DECam Alistair Walker ACTR meeting 22 March 2013
Telescope Assembly, Integration and Verification (AIV) WBS 04C. 14 J
MICE Computing and Software
Alistair Walker Version 3 December
Gingin Advisory Committee Meeting 08 Dec 2009
Magellan Status Report March 19, 2016 Carnegie Observatories
Magellan Telescopes Observatory Report
COSMOS Status David Sprayberry, Sean Points & Jay Elias
FourStar 4K x 4K JHK imager
LGS Project Meeting December 21, 2006 Agenda SWIFT update - A. Bouchez
Presentation transcript:

Magellan Associate Director Report Personnel Observing Statistics Commissioning of Instruments Facility instruments User (P.I.) Instruments Clean Room Operations Earthquake

Personnel‏ Ricardo Covarrubias (Magellan Fellow) departed in early December No other personnel changes during this reporting period Search underway for Mechanical Engineer Job ads run in both Chile and the USA 21 applications (deadline was 1 March) 5-6 interesting Goal is to make an offer by the end of April

Observing Statistics Baade + Clay Telescopes Instrumentation Usage: 23 Feb Aug Aug Feb 2010 IMACS37%41% MIKE23%16% LDSS-38%11% PANIC8%11% MagE16%11% MIKE fibers1%4% MagIC7%3% PFS--3%

Observing Statistics: Instrument Usage

28 Aug Feb 2010: Observing Statistics 2.1% 0.2% 1.0% 0.9% 11.5% 86.4% Baade 0.7% 0.3% 0.1% 0.3% 9.8% 89.5% Clay % Lost to Computer % Total Downtime % Lost to Instrument % Lost to Telescope % Lost to Weather % Open

Observing Statistics: Downtime

Instrument Downtime: Observing Statistics 23 Feb Aug Aug Feb 2010 IMACS1.6%0.5% MIKE0.1%0.0% LDSS-30.1%0.0% PANIC0.0%2.8% MagE0.2%0.0% MIKE fibers0.0% MagIC1.3%2.2% PFS--1.2%

Commissioning of Facility Instruments Successful commissioning run in October Image quality as good as 0.37 arcsec across the full 0.5 degree FOV was obtained First real test of support system for f/5 secondary First science runs are scheduled for April Megacam:

Commissioning of Facility Instruments (cont.) Successful commissioning run in early-December Both imaging and spectroscopic modes were tested First science runs are scheduled for the March and April bright runs MMIRS:

Commissioning of Facility Instruments (cont.) Passed pre-ship review in late-January Instrument arrived at LCO without mishap and was assembled and tested in the new clean room Commissioning to begin in late this month FIRE: FourStar: Detector problems slowed progress Pre-ship review to be held in May? Commissioning likely to begin in 2010B semester

Clean Room Clean room tent was installed by Alan Uomoto in early-December Air conditioning system was finished in January New transformer for ASB will be installed in March or April to handle increased load of clean room HVAC system Thanks to the efforts of Magellan and LCO staffs, the clean room was readied (just) in time for the arrival of FIRE in late-February Being used again right now by Harvard/SAO group to carry out work on MMIRS

Operations Clay primary mirror was aluminized in January 80.6% reflectivity at 530 nm before washing 90.1% reflectivity after washing 91.6% after coating Baade primary mirror was washed in March 76.5% reflectivity at 530 nm before washing 90.1% reflectivity after washing Why the 4% lower reflectivity of the Baade mirror before washing? Had ~2 months more exposure than Clay mirror CO 2 cleaning had also been temporarily suspended (2.5 months) due to suspicions of grounding problems

Operations The M1 server to correct the primary mirror for aberrations as a function of elevation, is in regular use at both Clay and Baade. This was successfully deployed for MegaCam commissioning and proved itself with the excellent delivered image quality. Collimation Two probe is used for checking f/11 collimation. Tests show scaling errors in off axis astigmatism and coma corrections and probe position dependent focus errors. More extensive sampling of the focal plane and guider positions is required to deal with these errors. These issues affect performance of the guiders under normal operation. Megacam extra-focal-image-based alignment yields very rapid and very accurate collimation for f/5 as evidenced by the 0.37" imaging achieved across the field during commissioning.

Operations Computers/Software The Magellan operations computers have been upgraded to the CentOS operating system. The upgrade will mitigate various situations that froze the computers and will make possible upgrades to the telescope interface and active optics system that were difficult under the old Red Hat system. Operations efficiency has been improved by setting up simultaneous initialization of all guider axes and simultaneous initialization of the ADC prisms. Work has begun on improving rotator reliability and troubleshooting capabilities. Testing of the fast tip/tilt secondary has begun at Baade. The initial work done has been to improve data logging to characterize guide errors. The telescopes do very well with standard guiding.

Operations MagE The cryotiger failed and was replaced. The camera read noise occasionally rises and is fixed by a power cycle. MMIRS We are exploring contracting of MMIRS mask cutting through CTIO. Prospects look very good.

Operations IMACS Flexure compensation became unstable do to a failed connection. It was repaired after extensive diagnosis. A slow leak of the Cargil oil in the F2 camera was discovered. No obvious source of the leak was found. Some mitigating repairs were done. The system needs to be monitored. Adjustment of SO9 lens has improved imaging at f2. There have been some overheating problems in the electronic racks. Following an extensive investigation, the primary culprit for noise on the IMACS f/2 camera was isolated to noise from the shutter signal line. A loose SH guider was found to be the cause of poor rotation guiding. The stage was modified by Tyson Hare.

Earthquake At 3:30 am on February 27, Chile was rocked by a powerful (8.8 mag on the Richter scale) earthquake Epicenter was located 120 km north of Concepción and 320 km south of Santiago Damage was wide-spread and > 500 lives were lost Although the quake was felt strongly at LCO, the observatory installations were unaffected Power was lost initially both at LCO and El Pino, but within 24 hours operations were back to normal Biggest problem was transportation of observers to and from the USA due to the closure of the Santiago airport which suffered significant damage 8 days passed before the first visitors were able to make it to LCO, and those who were stranded were able to make it back to the USA

GPS Measurements Showing Movement of South American Plate in Maule Earthquake Las Campanas moved 3 cm to the west Central and Southern Andes Project

Damage at Santiago Airport

Earthquake Preparedness We have been slowly pursuing a number of events designed to better protect the Magellan installations at LCO from future strong earthquakes: TCS monitors were changed to LCDs and have been bolted down in Baade and Clay control rooms. Hardware to secure the electronics racks located in the control room and the equipment room has been purchased and is being installed. Seismic retro fit to reinforce the air and glycol tank mounts has been completed. New collars and anchor bolts and restraints were added. Two seismic accelerometers were purchased and installed into the telescope and enclosure emergency stop control systems. All telescope and enclosure motion is now stopped when a significant earthquake occurs. This installation required a change in the emergency stop control PLC systems.

Earthquake Preparedness (cont.) Other measures that we have identified but not yet implemented: Suspended ceilings and light fixtures in Baade and Clay control rooms, lounges, kitchen, and the ASB need to be either secured or replaced. (El Pino as well) Structural analysis for the GMT indicates that seismic accelerations may be significantly amplified at both the secondary and primary mirrors much more than previously assumed. Should carry out a similar structural analysis for the Magellan telescopes ($$$) In the meantime, we will install accelerometers on one of the Magellan telescopes to directly measure this effect We need to update the emergency signs in all buildings so that they conform with the current building code. We should prepare a simple one page document that states what do in an earthquake.