Spliced Girders A Producer’s Perspective

Slides:



Advertisements
Similar presentations
Potential Solutions Goals for Design – What are we concerned about? –Primary Goal: Get the deck on successfully Stability during deck pour Stability during.
Advertisements

ODOT Structure Project Manager Training
Structural Steel Construction
Chapter-2 Parts of Steel Bridge.
AASHTO Subcommittee on Construction Virginia Beach, Virginia August 2, 2011 Barry D. Siel, P.E. Senior Geotechnical Engineer FHWA-RC AASHTO Subcommittee.
BRIDGE CONSTRUCTION INSPECTOR Practice Questions Next.
2013 Northcentral Region Construction Conference
Indianapolis Airport Interchange Bridges Presented to: TRB Bridge Aesthetics Subcommittee January 11, 2005.
St Croix River Crossing S.P Contractor Information Meeting 15 May 2013 River Spans.
New Graphic Engine New Graphic User Interface Tabbed Toolbar
Composite Beams (cont’d)
Heavy Concrete Construction Formwork
Teddy Theryo, P.E. Bryce Binney, P.E., S.E. Parsons Brinckerhoff
SPEED and STRENGTH SPEED and STRENGTH  When speed of construction and strength of slab are your concerns, the KWIK SLAB system is your fast and strong.
MDOT ACTT Workshop Structures I-94 From I-96 to East of Connor Participants Steve Stroh, URS Corp Vijay Chandra, Parson Brinckerhoff Raj Ailaney, FHWA.
Bridge Engineering (6) Superstructure – Concrete Bridges
By : Prof.Dr.\Nabil Mahmoud
Composite Construction
Reinforced Concrete QTO Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out.
Bridge over BNSF Railroad 7 km East of Windham - East Bridge Replacement Project Using Accelerated Bridge Construction.
Fundamentals of Building Construction, Materials & Methods, 5 th Edition Copyright © 2009 J. Iano. All rights reserved. Plant-Cast Precast Concrete Concrete.
SHRP2 Project R04 Bridge Designs for ABC
Spliced Precast Girders
Section 3 design of post-tensioned components for flexure Developed by the pTI EDC-130 Education Committee lead author: trey Hamilton, University of.
Bridge Engineering (7) Superstructure – Reinforced Concrete Bridges
 Project Delivery  Design Considerations  Lessons Learned.
CM 197 Mechanics of Materials Chap 14: Stresses in Beams
Region One Bridge Design – Robert Jose Tovar “If I have seen further it is by standing upon the shoulders of giants” – Isaac Newton.
EXAMPLE 9.2 – Part IV PCI Bridge Design Manual
I-5, Skagit River Bridge Collapse First Annual Missouri Bridge Conference April 9, 2015 Columbia, MO Jugesh Kapur, PE, SE.
EXAMPLE 9.2 – Part I PCI Bridge Design Manual
Chapter 10 Web splice.
Note: Moment Diagram Convention
CIA Biennial Conference Melbourne October 2005 High Performance Concrete in Bridge Decks Opportunities for Innovation.
Concrete Construction I Chapter 19. Mehta, Scarborough, and Armpriest : Building Construction: Principles, Materials, and Systems © 2008 Pearson Education,
Chapter 6 Plate girder.
Folded Plate Bridge: Steel Alternative for Short Span Bridges Maury Tayarani Accelerated Bridge Program MassDOT.
Bridge Engineering (9-1) Suspension Bridges I. *Components: Anchorage (blocks or tunnel type), towers, main cables, hangers, stiffened (box) girder and.
St. Croix River Crossing S.P Contractor Informational Meeting May 15, 2013 Contact: Paul Kivisto, P.E. St. Croix Crossing Bridge Construction.
Bridge Design to AS 5100 Sydney May 25th 2005 Using High Strength Concrete with AS 5100 opportunities and restrictions.
Self-Consolidating Concrete Applications Celik Ozyildirim, PhD, PE Virginia Concrete Conference 2011.
Moment Connection Requires Bolts Outside the Flanges
Lexington II at Market Square North, Washington D.C. Alexis Pacella – Structural Option.
Bayshore Concrete Products Corporation. Cape Charles Plant  Established in 1961  325 Employees  90 Acres of Plant Facilities  Feet of Bulkheaded.
Day 20 PRECAST AND PRE-STRESSED CONCRETE Pre Cast concrete comprise units that are made under controlled conditions, with necessary preparations for.
Chapter 43 Common Commercial Construction Materials.
1 Homes take DUSEL NSF Preliminary Baseline Review - April 13-15, 2010 Bob Altes Engineer- ISE Water Shield Engineering Figure Courtesy PDG and LBNL Homestake.
Fordham Place Bronx, NY Aric Heffelfinger Structural Option Spring 2006.
Flange Plates to be Welded to Beam Flanges.
James C. Renick School of Education PSU AE Senior Thesis 2006 Mick Leso - Structural North Carolina A&T State University - Greensboro.
Bridge Engineering (2) Bridge Forms 1. *Introduction 1.1 Beam bridges (Dongming YR Brdg)Dongming YR Brdg 1.2 Arch BridgesArch Bridges 1.3 Cable-supported.
. Client: City of Pittsburgh, Brighton Heights Community Objectives : Develop a pedestrian/bicycle bridge reconnecting Brighton Heights to Riverview park.
Construction of the Route 460 Connector Phase 1 Breaks, Virginia Timothy Barry, PE Robert Bennett, EI June 10-13, 2012 Pittsburgh, PA.
Presented By: Marvin Burns, PE Janssen & Spaans Engineering, Inc.
Condition of Prestressing of the Ft. Lauderdale- Hollywood Airport Deconstructed Segmental Bridges Luis M. Vargas Beiswenger Hoch and Associates.
Chapter-2 Parts of Steel Bridge. contents Bearings Horizontal and transversal wind bracing Classification of bridges.
Totally Precast Concrete Bridges
TOTAL BRIDGE REPLACEMENT OF M-13 OVER CHEBOYGANING CREEK
Offsite manufactured Bridges
High Bridge Re-Deck Project
Structural drawing.
New Bridge Construction
Advisor: Professor M. Kevin Parfitt
Chapter-2 Parts of Steel Bridges.
Structure II Course Code: ARCH 209 Dr. Aeid A. Abdulrazeg
- BEAM Sinusoidal Web Beam
Totally Precast Concrete Bridges
EAT 415 :ADVANCED STEEL BUILDING DESIGN PLATE GIRDER
The Great Belt East Bridge
Accelerated Bridge Construction; Raising the Bar
Presentation transcript:

Spliced Girders A Producer’s Perspective by Chad Saunders Chief Engineer Bayshore Concrete Products presented at the Virginia Concrete Conference Richmond, Virginia March 11, 2005

Bayshore Concrete Products Cape Charles, VA 90 acre casting facility on Cape Charles Harbor and Chesapeake Bay

The shape. How did we get here? PCEF Prestressed Concrete Committee for Economic Fabrication A committee established by FHWA for economic fabrication of prestressed/precast concrete Consists of Mid Atlantic states

PCEF Cross Section Variability 6” 7” 8” Different web thicknesses = diff. soffit

PCEF Cross Section Variability 58” 59” 60” 12” wider top flange = same side form with blockout removed

Form modification

VDOT PCBT 32” bottom flange width 7” thick bottom flange 7” web 47” top flange width DESIGNATION DEPTH AREA CENTROID TO BOTTOM MOMENT OF INERTIA WEIGHT (150 PCF)   (IN) (IN2) X 103 (IN4) LBS/LF PCBT-29 29 634.7 14.66 66.8 661 PCBT-37 37 690.7 18.43 126.0 720 PCBT-45 45 746.7 22.23 207.3 778 PCBT-53 53 802.7 26.06 312.4 836 PCBT-61 61 858.7 29.92 443.1 899 PCBT-69 69 914.7 33.79 601.3 953 PCBT-77 77 970.7 37.67 788.7 1011 PCBT-85 85 1026.7 41.57 1007.2 1070 PCBT-93 93 1082.7 45.48 1258.5 1128

Rte 123 over the Occoquan River Fairfax and Prince William Counties VDOT’s first PCBT spliced girder bridge

Close proximity to I-95 and Route 1 = detour = high traffic Location Close proximity to I-95 and Route 1 = detour = high traffic

Affluent neighborhood = pressure for aesthetic design Town of Occoquan Affluent neighborhood = pressure for aesthetic design

Who’s Who Owner – VDOT Designer – Moffatt & Nichol General Contractor – Archer Western Erection Engineer – McNary Bergeron Precast – Bayshore Concrete Products PT Hardware - VSL

Approach Girders (4 spans) Erection plan Approach Girders (4 spans) End Span Haunch Drop In Haunch End Span

Bridge Cross Section At Haunch Piers Other piers

Concrete Concrete – 28 day: 8000 psi Concrete - release: 5800 psi Low permeability Release strength cylinders matched cured

Approach Girders 4 span unit Pieces: 58 total beams Type: PCBT-77 Length: 144 ft Weight: 73 tons Strand: 0.6” LRS Cast two per pour Cross section

Approach Girder Casting setup Gravity abutment to withstand prestress force Conventionally prestressed with draped strands

Maturity meter testing Research for more accurate prediction and control of camber by VA Tech

Forms and casting Side forms with fall protection rail Placing concrete with Tuckerbuilt

Storage 300 ton twin gantry crane in background

Spliced Girders End span Haunch Drop-In Pieces: 28 total beams Length: 127 ft Weight: 88 tons Haunch Length: 98.5 ft Weight: 77 tons Drop-In Pieces: 14 total beams Length: 137 ft Weight: 87 tons

Special form needs End span and Drop-In Haunch Approach 34” soffit (4) sections of end block form (end span only) Extra 2” angle full length of side forms to create 6” thick top flange Haunch Complete form system including soffit and side forms Approach Standard PCBT-77

Erection Sequence Temporary support Erect haunch segment then end span segment Back span = 185 ft Erect drop-in segment Main span = 225 ft

Erection Sequence Make closures and begin PT Remove strong backs Cast deck and complete PT

End Span and Drop In cross sections Type: Modified PCBT-77 Depth: 79” Strand: 0.6” LRS Variations: 6” thick top flange 9” wide web for PT tendons = 34” wide bottom flange & 49” wide top flange Cast two per pour End Span and Drop-In End Block at End Span

End Span end condition PT ducts: (3) 4” OD for 0.6” LRS Extremely congested area due to bursting reinforcement

End Span and Drop-In connection at splice with haunch Very congested area due to splice plates with welded rebar and projecting rebar

Casting setup Ducts in place Setting ducts

End block Up close near anchorage Horizontal reinforcement

End block Termination of end block Pre-assembly of end cages

Splice End Top splice plates Bottom plates and projecting bars

Haunch Type: Modified PCBT-77 Depth: varies from 79” to 12’-6” Strand: 0.6” LRS Variations: 6” thick top flange 9” wide web for PT tendons = 34” wide bottom flange & 49” wide top flange Cast one per pour

Haunch NTS nts Challenges: 12’-6” depth at midpoint = extreme height full length Most strands located in top flange Location of the PT tendons makes concrete placement and consolidation difficult = addition of pour windows Extra setup required for storing and handling of variable depth side forms and beams

Bed setup

Pulling strand

Stressing

Rebar and PT tendons

How did he tie the bars in the top flange?

Forms

Grout vents Top Splice Plate

Look at the view from up here. Pouring with buckets

First casting is a success Girder bracing

Shipping All beams to be shipped by barge starting early April 2005

Erection Phase I – setting beams from the existing bridge

Erection Phase II – setting beams from the phase I bridge

Lessons learned Producer - Seek possible use of SCC concrete for heavily congested area Contractor - Get “construction engineer” involved early to ensure means and methods are established (i.e. temporary bracing embedments, special lifting requirements, strong back design, etc.) Engineer - Require complete shop drawings from PT supplier DOT – consider having a notch in back span girder(s) designed and included in plans to ensure maximum flexibility in construction sequence

Rte 33 over the Pamunkey River West Point and New Kent County What’s Next?

Location

Town of West Point

Who’s Who Owner – VDOT Designer – Parsons Brinckerhoff General Contractor – Tidewater Skanska Precast – Bayshore Concrete Products

Concrete Concrete – 28 day: 8000 psi Concrete - release: 6000 psi Low permeability Lightweight: 115 pcf (concrete) 125 pcf (total)

Approach Girders 3 span unit Pieces: 21 total beams Type: Modified PCBT-93 Variations: 9” thick bottom flange 8” wide web = 33” wide bottom flange & 60” wide top flange Depth = 95.5” Length: 137 ft Strand: 0.5” LRS Cast two per pour Cross section

Spliced Girders End span Haunch Drop-In Pieces: 42 total beams Length: 159 ft Haunch Pieces: 28 total beams Length: 80 ft Drop-In

Haunch Type: Modified PCBT-93 Depth: varies from 95.5” to 10’-5 1/2” Strand: 0.6” LRS Variations: 8” wide web for PT tendons = 33” wide bottom flange & 60” wide top flange Cast one per pour

Haunch Challenges: Pros: 10’-5 ½” depth at midpoint = setup remains at 12’-6” to avoid costly rework = extreme height full length Others same as previous project. Pros: Not having to set up a new stressing frame Booster Form – utilize existing forms Haunch

Special form needs End span and Drop-In Haunch Approach 33” soffit (2) sections of end block form (end span only) – different from Occoquan because same quantity of end span and drop-in 16” riser for PCBT-77 form Haunch Booster form (bolts on to bottom of standard form) Approach 16” riser for PCBT-77 form (same as above)

Questions?

Thank You Please feel free to come visit our plant OR call if we can be of assistance in any way Contact: Joe Rose 757-331-2300 jrose@bcpcorp.com

Bayshore Concrete Products Cape Charles, VA 90 acre casting facility on Cape Charles Harbor and Chesapeake Bay